LEC 8 - Project Time Management and Scheduling Techniques (12) (24) 2
LEC 8 - Project Time Management and Scheduling Techniques (12) (24) 2
Project Management
Lecture 5
Project Time Management and Scheduling
Techniques
26/12/2023 2
Project Time Management
Project Time Management includes the processes
required to manage the timely completion of the
project.
Project Time Management processes:
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule
26/12/2023 3
Plan Schedule Management
Plan Schedule Management is the process of establishing
the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project
schedule.
The key benefit of this process is that it provides guidance
and direction on how the project schedule will be managed
throughout the project.
26/12/2023 6
Schedule Management Plan
Schedule management plan can establish the
following:
Project schedule model development
Level of accuracy
Project schedule model maintenance
Control thresholds
Rules of performance measurement
Reporting formats
Process descriptions
The plan provides guidance and sets expectations for project schedule policies and procedures for
planning, developing, managing, executing, and controlling the project schedule.
7
Define Activities
Define Activities is the process of identifying and
documenting the specific actions to be performed to produce
the project deliverables.
The key benefit of this process is to break down work
packages into activities that provide a basis for estimating,
scheduling, executing, monitoring, and controlling the
project work.
26/12/2023 8
Define Activities: Tools & Techniques
26/12/2023 9
Sequence Activities
Sequence Activities is the process of identifying and
documenting relationships among the project activities.
The key benefit of this process is that it defines the logical
sequence of work to obtain the greatest efficiency given all
project constraints.
26/12/2023 10
Sequence Activities: Tools & Techniques
PDM
Precedence diagramming method (PDM) is a
technique used for constructing a schedule model in
which activities are represented by nodes and are
graphically linked by one or more logical
relationships to show the sequence in which the
activities are to be performed.
Activity-on-node (AON) is one method of
representing a precedence/ preference diagram
26/12/2023 11
Sequence Activities: Tools & Techniques
PDM
26/12/2023 12
Sequence Activities: Tools & Techniques
PDM
PDM includes four types of dependencies or logical
relationships:
Finish-to-start (FS)
The awards ceremony (successor) cannot start until the race
(predecessor) has finished.
Finish-to-finish (FF)
Writing a document (predecessor / last figure) is required to finish
before editing the document (successor) can finish.
Start-to-start (SS)
Level concrete (successor) cannot begin until pour foundation
(predecessor) begins.
Start-to-finish (SF)
The first security guard shift (successor) cannot finish until the second
security guard shift (predecessor) starts
26/12/2023 13
Sequence Activities: Tools & Techniques
Dependency Determination
Dependencies may be characterized as:
Mandatory:
Legally or contractually required or inherent in the nature of the work e.g.
building prototype before testing
Discretionary (preferred logic)
Established based on knowledge of best practices within a particular
application area or some unusual aspect of the project where a specific
sequence is desired.
Internal
Internal dependencies involve a precedence relationship between
project activities and are generally inside the project team’s control
External
Involve a relationship between project activities and non-project activities.
These dependencies are usually outside the project team’s control.
26/12/2023 14
Sequence Activities: Tools & Techniques
Leads and Lags
A lead is the amount of time whereby a successor activity
can be advanced with respect to a predecessor activity.
A lag is the amount of time whereby a successor activity
will be delayed with respect to a predecessor activity.
26/12/2023 15
Sequence Activities: Outputs
Project Schedule Network Diagrams
A project schedule network diagram is a graphical
representation of the logical relationships, also referred to as
dependencies, among the project schedule activities.
26/12/2023 16
Estimate Activity Resources
Estimate Activity Resources is the process of estimating the type and
quantities of material, human resources, equipment, or supplies required
to perform each activity.
The key benefit of this process is that it identifies the type, quantity, and
characteristics of resources required to complete the activity which
allows more accurate cost and duration estimates.
26/12/2023 17
Estimate Activity Durations
Estimate Activity Durations is the process of estimating the number of
work periods needed to complete individual activities with estimated
resources.
The key benefit of this process is that it provides the amount of time
each activity will take to complete, which is a major input into the
Develop Schedule process.
26/12/2023 18
Develop Schedule
Develop Schedule is the process of analyzing activity sequences,
durations, resource requirements, and schedule constraints to create the
project schedule model.
The key benefit of this process is that it generates a schedule model with
planned dates for completing project activities.
Estimate Activity Durations
26/12/2023 19
Develop Schedule: Tools & Techniques
Critical Path Method
The critical path method (CPM) is used to estimate the
minimum project duration and determine the amount of
scheduling flexibility on the logical network paths within the
schedule model.
Total float: the amount of time that a schedule activity can
be delayed or extended from its early start date without
delaying the project finish date or violating a schedule
constraint.
26/12/2023 20
Develop Schedule: Tools & Techniques
Critical Path Method Example
Develop Schedule: Tools & Techniques
Critical Path Method Example
https://www.youtube.com/watch?
v=tOJ8IuIqBpw
26/12/2023 22
Control Schedule
Control Schedule is the process of monitoring the status of
project activities to update project progress and manage
changes to the schedule baseline to achieve the plan.
The key benefit of this process is that it provides the means
to recognize deviation from the plan and take corrective and
preventive actions and thus minimize risk.
26/12/2023 23
Summary
Project Time Management processes:
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Control Schedule
26/12/2023 24
Reading
A guide to the project management body of
knowledge 5th edition.
Chapter 6: Project Time Management
26/12/2023 25