Project Risk Management Guide
Project Risk Management Guide
(MSIT504)
Tessfu G. (PhD)
School of Computing
Department of Computer Science
Dire Dawa Institute of Technology
Chapter 11 – Project Risk Management
Learning Objectives
3
Learning Objectives (continued)
4
Learning Objectives (continued)
5
The Importance of Project Risk Management
6
Research Shows Need to Improve Project Risk
Management
• Study by Ibbs and Kwak shows risk has the lowest maturity
rating of all knowledge areas
• A similar survey was completed with software development
companies in Mauritius, South Africa in 2003, and risk
management also had the lowest maturity (1.84 vs average of
2.29)
• A KLCI Research Group study (2001) shows the benefits of
following good software risk management practices
– 97% had procedures to identify and asess risk
– 80% identified anticipating and avoiding problems as the primary
benefit of risk management
– 70% had defined s/w development processes
– 64% has a Project Management Office
7
Project Management Maturity by Industry Group
and Knowledge Area*
KEY: 1 = LOWEST MATURITY RATING 5 = HIGHEST MATURITY RATING
Engineering/ Telecommunications Information Hi-Tech
Knowledge Area Construction Systems Manufacturing
*Ibbs, C. William and Young Hoon Kwak. “Assessing Project Management Maturity,”
Project Management Journal (March 2000).
8
Benefits from Software Risk Management Practices*
*Kulik, Peter and Catherine Weber, “Software Risk Management Practices – 2001,”
KLCI Research Group (August 2001).
9
Negative Risk
10
Risk Can Be Positive
11
Best Practice
• Some organizations make the mistake of only
addressing tactical and negative risks when performing
project risk management
• David Hillson (www.risk-doctor.com) suggests
overcoming this problem by widening the scope of risk
management to encompass both strategic risks and
upside opportunities, which he refers to as integrated
risk management
– Ensure that project delivery is tied to organizational needs
and vision
– Allowing an appropriate level of risk to be taken intelligently
with full awareness of the degree of uncertainty and its
potential effects on objectives
12
Risk Utility
• Different organizations and people have different
tolerances for risk.
• Risk utility or risk tolerance is the amount of
satisfaction or pleasure received from a potential
payoff.
– Utility rises at a decreasing rate for people who are risk-
averse
– Those who are risk-seeking have a higher tolerance for risk
and their satisfaction increases when more payoff is at stake
– The risk-neutral approach achieves a balance between risk
and payoff
13
Risk Utility Function and
Risk Preference
14
Project Risk Management Processes
15
Project Risk Management Processes
• Quantitative risk analysis: numerically estimating the effects of
risks on project objectives.
16
Project Risk Management Summary
17
Risk Management Planning
• The level of detail will vary with the needs of the project.
18
Topics Addressed in a Risk Management Plan
• Methodology: How will risk management be performed on this project?
What tools and data sources are available and applicable?
• Roles and Responsibilities: Who are the individuals responsible for
implementing specific tasks and providing deliverables related to risk
management?
• Budget and Schedule: What are the estimated costs and schedules for
performing risk-related activities?
• Risk Categories: What are the main categories of risks that should be
addressed on this project? Is there a risk breakdown structure for the
project?
• Risk Probability and Impact: How will the probabilities and impacts of
risk items be assessed? What scoring and interpretation methods will be
used for the qualitative and quantitative analysis of risks?
• Risk Documentation: What reporting formats and processes will be
used for risk management activities?
19
Contingency and Fallback Plans, Contingency
Reserves
• In addition to a risk management plan, many projects also include:
– Contingency plans – predefined actions that the project team will take if
an identified risk event occurs.
• Expecting new release of a software package, must plan to use older
version if delayed
– Fallback plans - developed for risks that have a high impact on meeting
project objectives, and are put into effect if attempts to reduce the risk are
not effective.
• College grad has main plan and contingency plans of where to live
after graduation but needs fallback plan to possibly live at home.
21
Information Technology Success Potential Scoring
Sheet
The number of questions
Success Criterion Relative Importance
User Involvement 19
corresponding to each
success criterion
Executive Management support 16
determines the number of
Clear Statement of Requirements 15
points each positive
Proper Planning 11
response is assigned
Realistic Expectations 10
Ex: User involvement:
Smaller Project Milestones 9
19/5 (or 3.8) points per
Competent Staff 8
question answered
Ownership 6
positively
Clear Visions and Objectives 3
Hard-Working, Focused Staff 3
Total 100
22
Broad Categories of Risk
• Many organizations develop their own risk questionnaires. Some of
the categories of risk might include:
– Market risk – Will the new service or product be useful to the
organization or marketable to others? Will the users accept it? Will
someone else create a better product?
– Financial risk – can the organization afford to undertake the project?
Will the project meet NPV, ROI and payback estimates?
– Technology risk – is the project technically feasible? Is it leading
edge or bleeding edge technology?
– People risk – Are people with appropriate skills available to help
complete the project? Does senior management support the project?
– Structure/process risk – What is the degree of change the new
project will introduce into user areas and business procedures? With
how many other systems does a new project/system need to interact?
23
What Went Wrong?
• KPMG, a large consulting firm, published a study in 1995 that
found that 55 percent of runaway projects—projects that have
significant cost or schedule overruns—did no risk management at
all; 38 percent did some (but half did not use their risk findings
after the project was underway); and 7 percent did not know
whether they did risk management or not.
24
Risk Breakdown Structure
25
Sample Risk Breakdown Structure
26
Potential Negative Risk Conditions Associated With
Each Knowledge Area
27
Risk Identification
• Risk identification is the process of understanding what potential
events might hurt or enhance a particular project.
– This is an ongoing process throughout the project lifecycle as
things change.
– You can not manage risks that you don’t identify.
28
Brainstorming
29
Delphi Technique
• The Delphi Technique is used to derive a consensus among a panel
of experts who make predictions about future developments.
– Developed by the RAND Corporation for the US Air Force in
the late 1960s
30
Interviewing
31
SWOT Analysis
• Helps identify the broad negative and positive risks that apply to
a project.
32
Other Risk Identification Methods
33
Other Risk Identification Methods
• An influence diagram is a simple visual representation of a decision problem. Influence
diagrams offer an intuitive way to identify and display the essential elements, including
decisions, uncertainties, and objectives, and how they influence each other.
• This simple influence diagram shows how decisions about the marketing budget and
product price influence expectations about its uncertain market size and market share.
These, in turn, influence costs and revenues, which affect the overall profit.
• The product manager, VP of marketing, and market analyst may work together to draw
such a diagram to develop a shared understanding of the key issues. The diagram
provides a high-level qualitative view under which the analyst builds a detailed
quantitative model.
34
Other Risk Identification Methods
37
Risk Register Contents (continued)
38
Sample Risk Register
39
Qualitative Risk Analysis
• After identifying risks, the next step is to understand which risks
are most important.
40
Probability/Impact Matrix
• List the risks and then label each one as high, medium, or
low in terms of its probability of occurrence and its impact if
it did occur.
41
Sample Probability/Impact Matrix
42
Risk factors
• Can also calculate risk factors.
– Numbers that represent the overall risk of specific events
based on their probability of occurring and the consequences
to the project if they do occur.
43
High-, Medium-, and Low-Risk Technologies
Example of how risk factors were used to graph the probability of
failure and consequence of failure for proposed technologies in a
research study to help design more reliable aircraft
Based on this chart, the recommendation was made to invest in
low- to medium-risk technologies and not pursue high-risk
technology
• 44
Top Ten Risk Item Tracking
• Top Ten Risk Item Tracking is a qualitative risk analysis tool
that helps to identify risks and maintain an awareness of risks
throughout the life of a project.
• 45
Top Ten Risk Item Tracking
• Keeps management and the customer aware of the major
influences that could prevent or enhance the project’s success.
• 46
Example of Top Ten Risk Item Tracking
• 47
Watch List
• A watch list is a list of risks that are low priority, but are still
identified as potential risks.
• 48
Quantitative Risk Analysis
• 49
Decision Trees and
Expected Monetary Value (EMV)
• A decision tree is a diagramming analysis technique used to help
select the best course of action in situations in which future
outcomes are uncertain.
50
Expected Monetary Value (EMV)
• 51
Simulation
• Simulation uses a representation or model of a system to analyze
the expected behavior or performance of the system.
– To use a Monte Carlo simulation, you must have three
estimates (most likely, pessimistic, and optimistic) plus an
estimate of the likelihood of the estimate being between the
most likely and optimistic values.
• 52
Steps of a Monte Carlo Analysis
• 53
Sample Monte Carlo Simulation Results for Project
Schedule
54
What Went Right?
• A large aerospace company used Monte Carlo simulation to help
quantify risks on several advanced-design engineering projects,
such as the National Aerospace Plan (NASP)
– Design a vehicle that could fly into space using a single-stage-
to-orbit approach
– The results of the simulation were used to determine how the
company would invest its internal research and development
funds
– Although the NASP project was terminated, the resulting
research has helped develop more advanced materials and
propulsion systems used on many modern aircraft
– Eli Lily uses simulation to determine the optimal plant
capacity that should be built for each drug
• 55
Sensitivity Analysis
• 56
Sample Sensitivity Analysis for Determining Break-
Even Point
• 57
Risk Response Planning
• After identifying and quantifying risks, you must decide how to
respond to them.
• 59
Response Strategies for Positive Risks
• Risk exploitation – do whatever you can to make sure the risk
occurs, call press conference to advertise new product, take out
ads, etc.
• 60
Residual and Secondary Risks
• Residual risks are risks that remain after all of the response
strategies have been implemented.
– Even though used stable h/w platform, it still may fail.
• 61
Media Snapshot
• 62
Risk Monitoring and Control
• Involves executing the risk management process to respond to
risk events.
– This is an ongoing activity – new risks identified, old risks
disappear, weaken or get stronger.
• 64
Results of Good Project Risk Management
• 65