0% found this document useful (0 votes)
39 views31 pages

CMT - Weekly Progress Report - 63

The weekly progress report provides updates on construction accomplishments, permits, productivity rates, equipment, photos, schedules, and issues over the past week. Construction is currently 67% complete and accomplishments include excavation, backfilling, rebar installation, and concrete pouring. Productivity and 2-week look ahead schedules are also included.

Uploaded by

Bethany Bermoy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views31 pages

CMT - Weekly Progress Report - 63

The weekly progress report provides updates on construction accomplishments, permits, productivity rates, equipment, photos, schedules, and issues over the past week. Construction is currently 67% complete and accomplishments include excavation, backfilling, rebar installation, and concrete pouring. Productivity and 2-week look ahead schedules are also included.

Uploaded by

Bethany Bermoy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 31

WEEKLY PROGRESS

REPORT
April 29, 2022
1. GENERAL CONSTRUCTION
REPORT
 GENERAL INFORMATION
 ACCOMPLISHMENTS
 PERMITS & CLEARANCES
 SUBMISSION’S STATUS
 MANPOWER
 PRODUCTIVITY RATE
 EQUIPMENTS
 OSM MONITORS
 LOOK AHEAD SCHEDULES
 PROJECT PHOTOS
 RECTIFICATION WORKS
 ISSUES & CONCERNS
GENERAL INFORMATION

PROJECT CASA MIRA TOWERS - LPU DAVAO


LOCATION Km. 11 Brgy. Sasa, Buhangin District, Davao City

AS OF April 29, 2022

ACTUAL START DATE March 15, 2021

DURATION 608 Days


COMPLETION DATE November 13, 2022

CONSTRUCTION PERIOD ELAPSED 410 Days


TIME ELAPSED (%) 67.43%
PERMITS AND CLEARANCES

NO. DESCRIPTION DATE APPROVED REMARKS

1 ECC October 15, 2019

2 Development Permit March 10, 2020

3 Building Permit August 19, 2021

4 Tower Cranes Permit November 11, 2021

6
ACCOMPLISHMENTS
TOTAL ACCOMPLISHMENT
REVISED ORIGINAL ACTUAL

33.58% 63.91% 35.82%

AS PER REVISED
ACTUAL AS PER ORIGINAL
PLAN
ACCOMPLISHMENT
Completed Structure Sketch up

FOUNDATION/FTB SUSPENDED SLAB REBARS INSTALLED CONCRETED


ACCOMPLISHMENTS

NO. WORK DESCRIPTION QUANTITY COMPLETED (Total) REMARKS PERCENTAGE

1.0 Bulk Excavation 45,670.00 cu.m 100%


2.0 Backfill 38,327.95 cu.m 95%
3.0 Rebars Installation 1,333,318.66 kgs. 19%
4.0 Concrete Poured 31%
1,382.50 cu.m 6,000 PSI
DURACRETE 7,941.00 cu.m 5,000 PSI
9,687.50 256.00 cu.m 3,000 PSI
cu.m
30,910.12 108.00 cu.m 6,000 PSI
QMIX cu.m 5,000 PSI
cu.m 3,000 PSI
PRODUCTIVITY RATE (APRIL 23– APRIL 29, 2022)

DESCRIPTION REBAR WORKS FORMWORKS CONCRETING


INSTALLED 18105.1 kgs 438 sq.m 105 cu.m
MANPOWER 25 45 20
PRODUCTIVITY RATE 0.066 MH/kgs 4.932 MH/sq.m 3.810 MH/cu.m
ON-HOLD ACCOMPLISHMENT

ITEM DESCRIPTION
ON HOLD
ON HOLD

1.0 BULK EXCAVATION 45,670.00 sq.m 41,430.91 sq.m 90.72% 4,239.09 sq.m 9.28% 0.39%

2.0 BACKFILL & COMPACTION 40,345.50 sq.m 36,310.50 sq.m 90.00% 2,017.73 sq.m 5.00% 0.12%

3.0 FORMWORKS 8,617.19 sq.m 7,784.66 sq.m 90.34% 832.53 sq.m 9.66% 0.22%

4.0 REBAR INSTALLATION 752,801.52 kgs 676,294.97 kgs 89.84% 76,506.54 kgs 10.16% 0.21%

5.0 CONCRETING 8,977.01 cu.m 8,274.02 cu.m 92.17% 702.99 cu.m 7.83% 0.50%

90.6% 8.39%

1.4%
ACTUAL ACCOMPLISHMENT FOR APRIL

ITEM DESCRIPTION
MARCH APRIL
PROJECTED ACTUAL

1.0 BACKFILL 2017.50 2,017.50 cu.m 0.12% cu.m 0.00%


2.0 FORMWORKS 1420.33 3,929.12 sq.m 1.03% 757.59 sq.m 0.20%
3.0 REBAR INSTALLATION 1666.87 292,580.09 kgs 0.78% 59,605.88 kgs 0.16%
4.0 CONCRETING 612.00 1,892.00 cu.m 1.47% 283.00 cu.m 0.22%
3.3% 0.58%

-2.70%
ACTUAL ACCOMPLISHMENT FOR APRIL

ITEM DESCRIPTION
APRIL MAY
PROJECTED ACTUAL

1.0 BACKFILL 2,017.50 2,017.50 cu.m 0.12% cu.m 0.00%


2.0 FORMWORKS 3,171.53 3,171.53 sq.m 0.83% sq.m 0.00%
3.0 REBAR INSTALLATION 232,974.21 232,974.21 kgs 0.62% kgs 0.00%
4.0 CONCRETING 1,609.00 1,609.00 cu.m 1.25% cu.m 0.00%
2.82% 0.00%

-2.82%
EQUIPMENT

NO. DESCRIPTION QUANTITY REMARKS

1 Excavator (Backhoe) 2
2 Dump Truck 2
3 Crawler Crane 1
4 Tower Crane 2 2 units Operational

5 Utility Truck 2

6 Bar Bender 2
7 Bar Cutter 2
8 EFCO Forms 1 lot
9
10
11
12
OSM MONITOR

NO. OSM DESCRIPTION GMQ TOTAL DELIVERED @ CONSUMED/USED REMAINING STOCK @ REMARKS
SITE/PLANT SITE/PLANT

1 Cement (Bulk) DURACRETE 166,972.75 164,568.50 2,404.25


542,595 b ag s b ag s b ag s b ag s

2 Cement (Bulk) QMIX 14,091.50 532.00 13,559.50


- b ag s b ag s b ag s b ag s

3 Cement (Bags – Job mix)


39,479 b ag s b ag s b ag s b ag s

4 Cement (Rubbed Concrete)


2,072 b ag s b ag s b ag s b ag s

5 576,555.58 399,798.28 176,757.30


Rebars (Grade 40) 4,529,900 kg s kg s kg s kg s

6 1,477,256.33 933,520.38 543,735.95


Rebars (Grade 60) 3,216,930 kg s kg s kg s kg s
INVENTORY
SITE PROGRESS PHOTO BACKFILL
SITE PROGRESS PHOTO 3F ZONE C1
SITE PROGRESS PHOTO 3F ZONE D1
SITE PROGRESS PHOTO 2F ZONE D2
SITE PROGRESS PHOTO CONCRETING
2-WEEKS LOOK AHEAD: April 22, 2022 – May 6, 2022
GF CONCRETING SCHEDULE (2ND Lift Column/ Wall >> 2.4m)

SEGMENT-4 SEGMENT-3 SEGMENT-2 SEGMENT-1

DONE

3 MAY’22 / V= 20.0 cum


2-WEEKS LOOK AHEAD: April 29, 2022 – May 13, 2022
CONCRETING SCHEDULE (STP)

MARK AREA DATE START DATE END DAYS


TOP SLAB ON GOING 30 APR’22 *****
2-WEEKS LOOK AHEAD: April 29, 2022 – May 13, 2022
2nd Floor Suspended Slab
(2,405.00 sqm)

SEGMENT-4 SEGMENT-3 SEGMENT-2 SEGMENT-1

DONE DONE

ZONE-D2
PART. DONE
Vol= 254.00 m³ ZONE-C2
Vol = 384.00 m³

MARK AREA DATE START DATE END DAYS DONE 1,435.00 m²/59.67 %
ZONE-C2 742.00 m² ON GOING 2 MAY’22 ********

ZONE-D2 492.00 m² 20 APR’22 13 MAY’22 24

TOTAL 1,234.00 m²
2-WEEKS LOOK AHEAD: April 29, 2022 – May 13, 2022
3rd Floor Suspended Slab
(5,870.00 sqm)

SOUTH TOWER NORTH TOWER

ZONE-B1
DONE
Vol = 253.00 m³
ZONE-C
ZONE-C1 ZONE-D1 A = 491.67 m²
Vol = 340.00 m³ Vol= 260.00 m³

MARK AREA DATE START DATE END DAYS


ZONE-B1 680.00 m² 2 MAY’22 16 MAY’22 15
ZONE-C1 919.00 m² ON GOING 8 MAY’22 *****
DONE 730.00 m² / 12.44 %
ZONE-D1 697.00 m² ***** ***** 15

TOTAL 3,026.00 m²
2. QA/QC REPORT
 CONCRETE TESTING STATUS
 REBAR TESTING STATUS
 SUBMISSIONS STATUS (RFA)
 NCR STATUS MONITORING
CONCRETE TESTING STATUS
(APRIL 23– APRIL 29, 2022)

DESIRED
DATE OF AVERAGE
STRUCTURE DATE OF POURING STRENGTH STRENGTH DAYS REMARKS
TESTING STRENGTH
(ps i )
6380
COLUMNS 3/23/2022 6000 4/20/2022 6365.00 28 DAYS 106% DURACRETE
6350
6430
COLUMNS 3/26/2022 6000 4/25/2022 6410.00 28 DAYS 107% DURACRETE
6390
5580
FTB 3/28/2022 5000 4/25/2022 5590.00 28 DAYS 112% DURACRETE
5600
7314
3F RETAINING WALL AND COLUMN A-
4/6/2022 6000 4/27/2022 7354 7460.00 21 DAYS 124% QMIX
G/1
7712
7314
3F RETAINING WALL AND COLUMN F-
4/20/2022 6000 4/27/2022 7354 7460.00 7 DAYS 124% QMIX
H/1
7712
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 6000 @28days Design Mix 6000 @28days
Slump Required 7"-9" Slump Required 7"-9"

Trial Mix 1 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 1 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 19 Cement Factor (bags) 19
Cement 1 (kgs) 760 53.4 Cement 1 (kgs) 760 53.4
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 220 15.4 Water (L) 220 15.4
Admixture 1 (L) Prokrete 5.5 385 Admixture 1 (L) Prokrete 5.5 385
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 620 43.4 Gravel 3/4 (kgs) 620 43.4
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 885 61.96 Sand (kgs) 885 61.96
Unit weight (kgs/cu.m) 2,490.50 Unit weight (kgs/cu.m) 2,490.50
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) Actua l Wa ter (L) added 2 L
Actua l Sl ump (Inches ) 8.5 Actua l Sl ump (Inches ) 8.75
Actua l U.W (FC) (kg/cu.m) 13.18 Actua l U.W (FC) (kg/cu.m) 13.02
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 5000 @28days Design Mix 5000 @28days
Slump Required 7"-9" Slump Required 7"-9"

Trial Mix 2 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 2 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 16.25 Cement Factor (bags) 16.25
Cement 1 (kgs) 650 45.5 Cement 1 (kgs) 650 45.5
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 195 13.65 Water (L) 195 13.65
Admixture 1 (L) Prokrete 5 350 Admixture 1 (L) Prokrete 5 350
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 650 44.1 Gravel 3/4 (kgs) 650 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 69.3 Sand (kgs) 69.3
Unit weight (kgs/cu.m) 2,460.00 Unit weight (kgs/cu.m) 2,460.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) added 0.22 L Actua l Wa ter (L) added 1.5 L
Actua l Sl ump (Inches ) 8 Actua l Sl ump (Inches ) 8
Actua l U.W (FC) (kg/cu.m) 13.00 Actua l U.W (FC) (kg/cu.m) 13.04
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 4000 @28days Design Mix 4000 @28days
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 3 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 3 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 15 Cement Factor (bags) 15
Cement 1 (kgs) 600 42 Cement 1 (kgs) 600 42
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 175 12.25 Water (L) 175 12.25
Admixture 1 (L) Prokrete 4.5 315 Admixture 1 (L) Prokrete 4.5 315
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 990 69.3 Sand (kgs) 990 69.3
Unit weight (kgs/cu.m) 2,399.50 Unit weight (kgs/cu.m) 2,399.50
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) added 1 L Actua l Wa ter (L) added 3 L
Actua l Sl ump (Inches ) 6.7 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.24 Actua l U.W (FC) (kg/cu.m) 13.04
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 3000 @28days Design Mix 3000 @28days
Slump Required 7"-9" Slump Required 7"-9"

Trial Mix 4 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 4 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 12.5 Cement Factor (bags) 12.5
Cement 1 (kgs) 500 35 Cement 1 (kgs) 500 35
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 170 11.9 Water (L) 170 11.9
Admixture 1 (L) Prokrete 4 280 Admixture 1 (L) Prokrete 4 280
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 1,100 61.96 Sand (kgs) 1,100 61.96
Unit weight (kgs/cu.m) 2,404.00 Unit weight (kgs/cu.m) 2,404.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) added 0.76L Actua l Wa ter (L) added 1.5 L
Actua l Sl ump (Inches ) 8.5 Actua l Sl ump (Inches ) 9
Actua l U.W (FC) (kg/cu.m) 13.20 Actua l U.W (FC) (kg/cu.m) 13.00
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 6000 w/ WP Design Mix 6000 w/ WP
Slump Required 7"-9" Slump Required 7"-9"

Trial Mix 5 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 5 Batch Weight/cu.m Volume Batch/cu.m

Cement Factor (bags) 19 Cement Factor (bags) 19


Cement 1 (kgs) 620 53.4 Cement 1 (kgs) 620 53.4
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 220 15.4 Water (L) 220 15.4
Admixture 1 (L) Prokrete 5.5 385 Admixture 1 (L) Prokrete 5.5 385
Admixture 2 (L) WP-8.25 WP-578 Admixture 2 (L) WP-8.25 WP-578
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 620 43.4 Gravel 3/4 (kgs) 620 43.4
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 885 61.95 Sand (kgs) 885 61.95
Unit weight (kgs/cu.m) 2,498.75 Unit weight (kgs/cu.m) 2,498.75
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) added 2.2 L Actua l Wa ter (L) added 2 L
Actua l Sl ump (Inches ) 7.3 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.18 Actua l U.W (FC) (kg/cu.m) 13.02
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 3000 w/ WP Design Mix 3000 w/ WP
Slump Required 7"-9" Slump Required 7"-9"

Trial Mix 6 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 6 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 12.5 Cement Factor (bags) 12.5
Cement 1 (kgs) 500 35 Cement 1 (kgs) 500 35
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 170 11.9 Water (L) 170 11.9
Admixture 1 (L) Prokrete 4 280 Admixture 1 (L) Prokrete 4 280
Admixture 2 (L) WP-4.0 WP-280 Admixture 2 (L) WP-4.0 WP-280
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 1,100 77 Sand (kgs) 1,100 77
Unit weight (kgs/cu.m) 2,408.00 Unit weight (kgs/cu.m) 2,408.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"

Result Result
Actua l Wa ter (L) added 1.7 L Actua l Wa ter (L) added 2.0 L
Actua l Sl ump (Inches ) 8 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.10 Actua l U.W (FC) (kg/cu.m) 13.02