CMT - Weekly Progress Report - 63
CMT - Weekly Progress Report - 63
REPORT
April 29, 2022
1. GENERAL CONSTRUCTION
REPORT
GENERAL INFORMATION
ACCOMPLISHMENTS
PERMITS & CLEARANCES
SUBMISSION’S STATUS
MANPOWER
PRODUCTIVITY RATE
EQUIPMENTS
OSM MONITORS
LOOK AHEAD SCHEDULES
PROJECT PHOTOS
RECTIFICATION WORKS
ISSUES & CONCERNS
GENERAL INFORMATION
6
ACCOMPLISHMENTS
TOTAL ACCOMPLISHMENT
REVISED ORIGINAL ACTUAL
AS PER REVISED
ACTUAL AS PER ORIGINAL
PLAN
ACCOMPLISHMENT
Completed Structure Sketch up
ITEM DESCRIPTION
ON HOLD
ON HOLD
1.0 BULK EXCAVATION 45,670.00 sq.m 41,430.91 sq.m 90.72% 4,239.09 sq.m 9.28% 0.39%
2.0 BACKFILL & COMPACTION 40,345.50 sq.m 36,310.50 sq.m 90.00% 2,017.73 sq.m 5.00% 0.12%
3.0 FORMWORKS 8,617.19 sq.m 7,784.66 sq.m 90.34% 832.53 sq.m 9.66% 0.22%
4.0 REBAR INSTALLATION 752,801.52 kgs 676,294.97 kgs 89.84% 76,506.54 kgs 10.16% 0.21%
5.0 CONCRETING 8,977.01 cu.m 8,274.02 cu.m 92.17% 702.99 cu.m 7.83% 0.50%
90.6% 8.39%
1.4%
ACTUAL ACCOMPLISHMENT FOR APRIL
ITEM DESCRIPTION
MARCH APRIL
PROJECTED ACTUAL
-2.70%
ACTUAL ACCOMPLISHMENT FOR APRIL
ITEM DESCRIPTION
APRIL MAY
PROJECTED ACTUAL
-2.82%
EQUIPMENT
1 Excavator (Backhoe) 2
2 Dump Truck 2
3 Crawler Crane 1
4 Tower Crane 2 2 units Operational
5 Utility Truck 2
6 Bar Bender 2
7 Bar Cutter 2
8 EFCO Forms 1 lot
9
10
11
12
OSM MONITOR
NO. OSM DESCRIPTION GMQ TOTAL DELIVERED @ CONSUMED/USED REMAINING STOCK @ REMARKS
SITE/PLANT SITE/PLANT
DONE
DONE DONE
ZONE-D2
PART. DONE
Vol= 254.00 m³ ZONE-C2
Vol = 384.00 m³
MARK AREA DATE START DATE END DAYS DONE 1,435.00 m²/59.67 %
ZONE-C2 742.00 m² ON GOING 2 MAY’22 ********
TOTAL 1,234.00 m²
2-WEEKS LOOK AHEAD: April 29, 2022 – May 13, 2022
3rd Floor Suspended Slab
(5,870.00 sqm)
ZONE-B1
DONE
Vol = 253.00 m³
ZONE-C
ZONE-C1 ZONE-D1 A = 491.67 m²
Vol = 340.00 m³ Vol= 260.00 m³
TOTAL 3,026.00 m²
2. QA/QC REPORT
CONCRETE TESTING STATUS
REBAR TESTING STATUS
SUBMISSIONS STATUS (RFA)
NCR STATUS MONITORING
CONCRETE TESTING STATUS
(APRIL 23– APRIL 29, 2022)
DESIRED
DATE OF AVERAGE
STRUCTURE DATE OF POURING STRENGTH STRENGTH DAYS REMARKS
TESTING STRENGTH
(ps i )
6380
COLUMNS 3/23/2022 6000 4/20/2022 6365.00 28 DAYS 106% DURACRETE
6350
6430
COLUMNS 3/26/2022 6000 4/25/2022 6410.00 28 DAYS 107% DURACRETE
6390
5580
FTB 3/28/2022 5000 4/25/2022 5590.00 28 DAYS 112% DURACRETE
5600
7314
3F RETAINING WALL AND COLUMN A-
4/6/2022 6000 4/27/2022 7354 7460.00 21 DAYS 124% QMIX
G/1
7712
7314
3F RETAINING WALL AND COLUMN F-
4/20/2022 6000 4/27/2022 7354 7460.00 7 DAYS 124% QMIX
H/1
7712
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 6000 @28days Design Mix 6000 @28days
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 1 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 1 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 19 Cement Factor (bags) 19
Cement 1 (kgs) 760 53.4 Cement 1 (kgs) 760 53.4
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 220 15.4 Water (L) 220 15.4
Admixture 1 (L) Prokrete 5.5 385 Admixture 1 (L) Prokrete 5.5 385
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 620 43.4 Gravel 3/4 (kgs) 620 43.4
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 885 61.96 Sand (kgs) 885 61.96
Unit weight (kgs/cu.m) 2,490.50 Unit weight (kgs/cu.m) 2,490.50
Slump (Inches) 7"-9" Slump (Inches) 7"-9"
Result Result
Actua l Wa ter (L) Actua l Wa ter (L) added 2 L
Actua l Sl ump (Inches ) 8.5 Actua l Sl ump (Inches ) 8.75
Actua l U.W (FC) (kg/cu.m) 13.18 Actua l U.W (FC) (kg/cu.m) 13.02
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 5000 @28days Design Mix 5000 @28days
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 2 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 2 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 16.25 Cement Factor (bags) 16.25
Cement 1 (kgs) 650 45.5 Cement 1 (kgs) 650 45.5
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 195 13.65 Water (L) 195 13.65
Admixture 1 (L) Prokrete 5 350 Admixture 1 (L) Prokrete 5 350
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 650 44.1 Gravel 3/4 (kgs) 650 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 69.3 Sand (kgs) 69.3
Unit weight (kgs/cu.m) 2,460.00 Unit weight (kgs/cu.m) 2,460.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"
Result Result
Actua l Wa ter (L) added 0.22 L Actua l Wa ter (L) added 1.5 L
Actua l Sl ump (Inches ) 8 Actua l Sl ump (Inches ) 8
Actua l U.W (FC) (kg/cu.m) 13.00 Actua l U.W (FC) (kg/cu.m) 13.04
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 4000 @28days Design Mix 4000 @28days
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 3 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 3 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 15 Cement Factor (bags) 15
Cement 1 (kgs) 600 42 Cement 1 (kgs) 600 42
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 175 12.25 Water (L) 175 12.25
Admixture 1 (L) Prokrete 4.5 315 Admixture 1 (L) Prokrete 4.5 315
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 990 69.3 Sand (kgs) 990 69.3
Unit weight (kgs/cu.m) 2,399.50 Unit weight (kgs/cu.m) 2,399.50
Slump (Inches) 7"-9" Slump (Inches) 7"-9"
Result Result
Actua l Wa ter (L) added 1 L Actua l Wa ter (L) added 3 L
Actua l Sl ump (Inches ) 6.7 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.24 Actua l U.W (FC) (kg/cu.m) 13.04
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 3000 @28days Design Mix 3000 @28days
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 4 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 4 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 12.5 Cement Factor (bags) 12.5
Cement 1 (kgs) 500 35 Cement 1 (kgs) 500 35
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 170 11.9 Water (L) 170 11.9
Admixture 1 (L) Prokrete 4 280 Admixture 1 (L) Prokrete 4 280
Admixture 2 (L) Admixture 2 (L)
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 1,100 61.96 Sand (kgs) 1,100 61.96
Unit weight (kgs/cu.m) 2,404.00 Unit weight (kgs/cu.m) 2,404.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"
Result Result
Actua l Wa ter (L) added 0.76L Actua l Wa ter (L) added 1.5 L
Actua l Sl ump (Inches ) 8.5 Actua l Sl ump (Inches ) 9
Actua l U.W (FC) (kg/cu.m) 13.20 Actua l U.W (FC) (kg/cu.m) 13.00
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 6000 w/ WP Design Mix 6000 w/ WP
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 5 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 5 Batch Weight/cu.m Volume Batch/cu.m
Result Result
Actua l Wa ter (L) added 2.2 L Actua l Wa ter (L) added 2 L
Actua l Sl ump (Inches ) 7.3 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.18 Actua l U.W (FC) (kg/cu.m) 13.02
SOUTHERN CONCRETE INDUSTRIES INC. JY ENTERPRISES INCORPORATED
Design Mix 3000 w/ WP Design Mix 3000 w/ WP
Slump Required 7"-9" Slump Required 7"-9"
Trial Mix 6 Batch Weight/cu.m Volume Batch/cu.m Trial Mix 6 Batch Weight/cu.m Volume Batch/cu.m
Cement Factor (bags) 12.5 Cement Factor (bags) 12.5
Cement 1 (kgs) 500 35 Cement 1 (kgs) 500 35
Cement 2 (kgs) Cement 2 (kgs)
Water (L) 170 11.9 Water (L) 170 11.9
Admixture 1 (L) Prokrete 4 280 Admixture 1 (L) Prokrete 4 280
Admixture 2 (L) WP-4.0 WP-280 Admixture 2 (L) WP-4.0 WP-280
Gravel 1 1/2" (kgs) Gravel 1 1/2" (kgs)
Gravel 3/4 (kgs) 630 44.1 Gravel 3/4 (kgs) 630 44.1
Gravel 3/8 (kgs) Gravel 3/8 (kgs)
Sand (kgs) 1,100 77 Sand (kgs) 1,100 77
Unit weight (kgs/cu.m) 2,408.00 Unit weight (kgs/cu.m) 2,408.00
Slump (Inches) 7"-9" Slump (Inches) 7"-9"
Result Result
Actua l Wa ter (L) added 1.7 L Actua l Wa ter (L) added 2.0 L
Actua l Sl ump (Inches ) 8 Actua l Sl ump (Inches ) 8.5
Actua l U.W (FC) (kg/cu.m) 13.10 Actua l U.W (FC) (kg/cu.m) 13.02