Ayala Turn Over Bare Sample

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views5 pages

Ayala Turn Over Bare Sample

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 5

PC Lantapan

Construction Progress
Date: August 9, 2023 Shop Handover: January 3,
2023
Scope of Works Percent Assets Delivery Date Installation Date
Completion
SSO table Installed
Demolition & Clearing Works 100%
Check-out counter Installed
Partition & Masonry Works 100%
Roll-up door Installed
Doors & Windows 100%
Glass door & store front Installed
Flooring Works 100% glass (tempered)
Ceiling Works 100% Aircon Installed
Painting Works (walls/slab ceiling) 100% Gondola Installed
Specialties (Counters, Accent wall) 100% TV Installed
Electrical Works 100% Emergency lights Installed
Mechanical Works (AC) 100% Smoke detectors Installed
Plumbing Works 100% Fire extinguishers Installed
Miscellaneous 100% Fire alarm Installed
Site Photos

Store Front Supermarket Area Staff Counter & Check-out Counter

Storage Room Toilet Dealers Area


GANTT CHART
MAN-POWER COUNT

Site In-Charge - 1
Carpenters - 2 Persons
Masons - 2 Persons
Painters - 2 Persons
Electrician - 1 Person