PC Lantapan
Construction Progress
Date: August 9, 2023 Shop Handover: January 3,
2023
Scope of Works Percent Assets Delivery Date Installation Date
Completion
SSO table Installed
Demolition & Clearing Works 100%
Check-out counter Installed
Partition & Masonry Works 100%
Roll-up door Installed
Doors & Windows 100%
Glass door & store front Installed
Flooring Works 100% glass (tempered)
Ceiling Works 100% Aircon Installed
Painting Works (walls/slab ceiling) 100% Gondola Installed
Specialties (Counters, Accent wall) 100% TV Installed
Electrical Works 100% Emergency lights Installed
Mechanical Works (AC) 100% Smoke detectors Installed
Plumbing Works 100% Fire extinguishers Installed
Miscellaneous 100% Fire alarm Installed
Site Photos
Store Front Supermarket Area Staff Counter & Check-out Counter
Storage Room Toilet Dealers Area
GANTT CHART
MAN-POWER COUNT
Site In-Charge - 1
Carpenters - 2 Persons
Masons - 2 Persons
Painters - 2 Persons
Electrician - 1 Person