ESTIMATE
S OF
REINFORC
ESTIMATING REINFORCEMENT:
COLUMNS
GENERAL INFORMATION: COLUMNS
GENERAL INFORMATION: COLUMNS
LAPPING LENGTHS
SAMPLE DRAWING:
SAMPLE DRAWING:
SAMPLE DRAWING:
SAMPLE DRAWING:
APPROX HEIGHT FROM BOT OF FOOTING TO ROOFBEAM= 8.86 METERS
ISOMETRIC VIEW SECTION OF C1
STEP 1:
MAKE/SKETCH A PROPOSED CUTTING LIST USING ALL THE PROVISIONS NEEDED.
STEP 2:FOLLOWING THE STAGGERED SPLICING:
STEP 2:FOLLOWING THE STAGGERED SPLICING:
Summary:
LENGTH OF A = 3.58 m + (16d= 0.256) =3.9m
(6PCS)
LENGTH OF B = 6 Meters (4pcs)
LENGTH OF C = 0.8m + 0.8m + 3.7m =5.3 m (2pcs)
LENGTH OF D = 0.8+ 0.3 + 0.15= 1.25m (2pcs)
THEREFORE ORDER:
TOTAL L= 3.9 (6) + 6 (4) + 5.3 (2)+ 1.2 (2)
L= 60.4
FOR VERTICAL BARS USING 16MM:
PCS OF VERTICAL BARS= 60.4 DIVIDE BY 6 METERS =
10.06 PCS
= APPROX 11PCS = MARK UP
12PCS (16MM)
STEP 3: Compute the tie bars
FOR TIES BARS USING 10-16MM:
FROM NATIONAL STRUCTURAL CODE OF THE PHILIPPINES
STEP 3: Compute the tie bars
USING THE 135 DEGREE HOOK
MINIMUM INSIDE BEND DIAMETER
4 DB = 4 (10) = 40MM
6 DB = 6 (10) = 60 MM or 75mm
STEP 3: Compute the tie bars
a. Compute for total perimeter of stirrups considering the
concrete cover =40mm
P= 200 + 400 +200 +400 – 8(40)
P= 880mm
b. For Total Straight Extension (2 HOOKS) (total hook length)
o 6 DB = 6 (10) = 60 MM or 75mm (use 75mm as
per code)
Total Hook= 3db + 75mm
Total Hook = 3(10) +75 mm
Total Hook = 105mm (use 2pcs for 2 hooks length)
c. For 5 bends (Total bend length)
3 pcs (90 degree bend = 2db) + 2pcs (135 degree bend= 3db)
3 (2db)+ 2 (3db)
3 (2)(10) + 2(3)(10)
=120mm
STEP 3: Compute the tie bars
Total Cutting Length = Perimeter of Rectangle + Total Hook Length -
Total Bend length
Total Cutting Length = 880 + 2(3db + 75 mm) – 3db (2) -2db (3)
= 880+ 2(3(10) + 75mm)- 3(10)(2) -2 (10)(3)
= 970 mm Approx 1000MM for easy cut.
d. Get the number of pcs that can 1 pc of 10mm x 6m rebars
PCS= 6meters divide by 1000meters
PCS = 6 PCS FOR EVERY 1pcs of 10mm
STEP 3: Compute the tie bars
e. For Total Column Stirrups in one column
STEP 3: Compute the tie bars
FOLLOWING THE SPACING @ the column details
STEP 3: Compute the tie bars
FOLLOWING THE SPACING @ the column details
TOTAL NUMBER OF PCS = 8PCS + 24PCS +30
PCS
= 62 PCS (1000mm length of stirrups)
THEREFORE ORDER: 62 DIVIDE 6 PCS(EVERY
1PC OF 10MM) = 10. 33
ORDER = 11 PCS OF 10MM (6M
LENGTH)
STEP 4: Solve for GI Wire
f. Solve for G.I Wire
SUMMARY:
FOR 12 PCS (16MM) -VERTICAL BARS
FOR 11 PCS (10MM) -STIRRUPS
GET THE KG/M OF 10 AND 16MM
USING THE FORMULA A.
KG/M= (16 X 16) DIVIDE (162.2)= 1.578 KG/M
KG/M= (10 X 10) DIVIDE (162.2)= 0.617 KG/M
GET THE KG OF GI WIRE
@ 12PCS FOR 16MM
GI WIRE(KG) = 1.578 (KG/M) X 6M X 12 PCS X 0.02 (% AS PER REBARS)
=2.27 KG OF GI.WIRE
= APPROX 3 KG OF GI WIRE.
@11 PCS FOR 10MM
GI WIRE(KG) = 0.617 (KG/M) X 6M X 11 PCS X 0.02 (% AS PER REBARS)
=0.81 KG OF GI.WIRE
= APPROX 1KG OF GI WIRE.
THEREFORE ORDER: 4 KGS GI.WIRE #16