Responsibility of Project Implementors 2025

The document outlines the profile and qualifications of Engr. Guilbert P. Romero, a speaker for a training session for DPWH field engineers in the Philippines. It details his educational background, private practice experience, and extensive government service within the DPWH, highlighting his roles and promotions over the years. The document also emphasizes the need for comprehensive training to enhance the technical and managerial capabilities of field engineers in response to identified deficiencies in project supervision.

Uploaded by

guilbertrmr.44
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views143 pages

Responsibility of Project Implementors 2025

The document outlines the profile and qualifications of Engr. Guilbert P. Romero, a speaker for a training session for DPWH field engineers in the Philippines. It details his educational background, private practice experience, and extensive government service within the DPWH, highlighting his roles and promotions over the years. The document also emphasizes the need for comprehensive training to enhance the technical and managerial capabilities of field engineers in response to identified deficiencies in project supervision.

Uploaded by

guilbertrmr.44
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 143

Republic of the Philippines

Department of Public Works and Highways

Speaker’s Profile: Day 17: March 5, 2025

Comprehensive Training
for
Field
Engineers

DPWH Regional Office Series of Trainings


Multi-Purpose Hall, Rawis, Legazpi City

DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Who is your
Lecturer &
Speaker for
the Day?
DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Educational Attainment:
 He graduated with BSCE course in 1984 at
the University of Nueva Caceres, Naga City;
 He is a licensed Civil & Geodetic
Engineer since 1985;
 While waiting for the released of the
Licensure Examinations, he took up his
Masteral Course in Public Administration
and graduated in 2006; and
 Through his enthusiasm to pursue a career,
He took up his Doctoral Course in
Behavioural Management & graduated with
Excellence in Oral Defense in 2011.
DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Private Practice:
 In 1988 to 1990, he is a Consultant in Bicol
First Agribusiness Resources Management
Services (BFARMS), Naga City;
 In 1994 to 1995, he is a Consultant Engineer
in Jaimaca Realty & Marketing Corporation
(JRMC), a subdivision developer from
Laguna and Manila;
 In 2011 to 2014, he is a Part-time Associate
Professor in the Engineering & Technology
Department, Naga College Foundation
(NCF);
DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Private Practice:
 In 2012 to 2014, he is also a Part-time
Professor, College of Engineering
Department, Ateneo de Naga University
(AdNU);

 In 2016, He was trained as an Occupational Safety


and Health (OSH) Practitioner, by DOLE and in the
same year, he became an ASEAN ENGINEER;

 Since 1999 until the present, he is usually invited as


lecturer, if not all in the Department’s Regional series
of Seminars, Trainings & Workshops, and in some
agencies, schools and universities within the region;
DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Government Service:
 He entered in the government service in 1988
as Project Coordinator & In-Charge of
Hydrology Sector at the Provincial
Development Planning & Evaluation Office,
Provincial Capitol, Pili, Cam. Sur;

 He entered in the DPWH as a Senior


Geodetic Engineer in the Cam. Sur District
Engineering Office in 1989 after the
Department’s Re-organization

DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Government Service:
 Till then, He rouse from the rank:
As Assistant Planning Engineer,
Assistant Building Official,
Assistant Construction Engineer, and
Internal Control Unit (ICU) with an Item
of Engineer II, until his break in 2001,
He became an Officer In-charge (OIC) of
Planning and Design Section (PDS) with the
same District Engineering Office;

DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Government Service:
 In 2002, He became Officer In-charge (OIC)

of Maintenance Section after the DEO rank


no.13 out of 13 DEO’s in the entire Region V.

After the 2nd Regional Quarterly Rating in


2002, the DEO rank no. 3 and in the
succeeding years rank no. 2 (from rank
no.138 in the National Rating to rank no. 68
until 2003), for this he was promoted as
Engineer III;
DE ROMERO
Republic of the Philippines
Department of Public Works and Highways

Government Service:
 In 2007, He became OIC-Assistant District
Engineer (OIC-ADE) in Cam Sur 2nd DEO, as
being a senior of all the civil engineers in the
District Engineering Office;
 In 2010, He became a full-pledge Assistant
District Engineer (ADE) in the same District
Engineering Office until Oct.15, 2014 and
re-assigned to Albay 1st District Engineering
Office on Oct. 16, 2014 up to May 31, 2022.
On June 1, 2022 up to the present, he was
designated as OIC-District Engineer of
Camarines Norte Sub-DEO. DE ROMERO
Republic of the Philippines
Department of Public Works and Highways
Republic of the Philippines
Department of Public Works and Highways

My fellow Engineers in the


Department. . .
Let us
Welcome our Speaker
for this day. . .

Engr. Guilbert P. Romero, Ph.D.


OIC-District Engineer

DE ROMERO
Republic of the Philippines
Department of Public Works and Highways
Albay 1st District Engineer Office

Module VII – On-the-Job


Training (OJT)

DUTIES & RESPONSIBILITIES OF


DPWH FIELD ENGINEERS
March 5, 2022 Multi-Purpose Hall
DPWH Regional Office V, Rawis, Legazpi City

DE ROMERO
“The road to the Golden Age of
Infrastructure will surely inevitably
entail some obstacles, but I am
very optimistic that our
unwavering effort and steadfast
commitment will bridge any
hindrance and bring about the
realization of our collective goal of
a no less than great infrastructure
development…

Sec. Manuel M. Bonoan


DPWH Secretary

Unity…Strength…Teamwork DE ROMERO
03/05/2025 Department Of Public Works and Highways 14

Root Observation:
An Assessment of the adequacy and capability of
project /resident engineers to undertake/supervise DPWH
Projects was undertaken in response to the instruction of the
Secretary to come-up with recommendations on how the
capability of the DPWH field engineers could be enhanced.
The idea was supported by the fact that despite the continuous
assessment being conducted by the Department ‘s Quality
Unit’s (QAUs) on various on-going & completed projects,
there are still some projects that exhibit defects/deficiencies &
do not conform with the approved plans & specifications.

MEMO SUBJECT : Department of Public Works & Highways


Integrated Training Calendar
Dated March 4, 2016
CamNorte Sub-District Engineering Office DE Romero
03/015/202
5 Department Of Public Works and Highways 15

Purpose of Issuance:
The results of the study revealed that majority of the
DPWH Field Engineers as Project/Resident Engineer in terms
of their education & eligibility but they have very little technical
training & have inadequate knowledge of DPWH standards &
specifications. Based on these findings, it was recommended
that a 21-day Comprehensive Training for Accreditation of
DPWH Field Engineers be carried out to enhance their
Technical & Managerial Capabilities.

MEMO SUBJECT : Department of Public Works & Highways


Integrated Training Calendar

Dated March 4, 2016


CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 16

DUTIES AND RESPONSIBILITIES


OF FIELD ENGINEERS
PER D.O. NO. 115 S. 2018
RE: ACCREDITATION & ASSIGNMENT
OF DPWH PROJECT ENGINEERS
AND INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 17

Reiterated Dos in this Issued Order

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


06/01/2022 Department Of Public Works and Highways 18

Purpose of Issuance:
In order to ensure that only qualified and
competent field engineers will be assigned to
supervise DPWH Projects.

Effective January 2, 1999 only Accredited


Project Engineers & Inspectors may be
assigned to supervise DPWH Projects.

D.O. 73 SUBJECT : ACCREDITATION & ASSIGNMENT OF DPWH PROJECT

:
ENGINEERS AND INSPECTORS

Series of 1998
Albay 1st District Engineering Office ADE Romero
03/05/2025 Department Of Public Works and Highways 19

Committee:
The Committee created to accredit field Engineers,
under Department Order No. 170, Series of 1997,
shall carry out the evaluation for accreditation and
recommend the issuance of certificates of
accreditation for approval of the Secretary

D.O. 73 SUBJECT : ACCREDITATION & ASSIGNMENT OF DPWH PROJECT

:
ENGINEERS AND INSPECTORS

Series of 1998
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 20

Purpose of Issuance:

D.O. 209 SUBJECT : 1st Partial Lists of Accredited Project Engineers


and Inspectors
Series of 1998
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 21

Purpose of Issuance: ANNEX A

D.O. 209 SUBJECT : 1st Partial Lists of Accredited Project Engineers


and Inspectors
Series of 1998
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 22

D.O. 25 SUBJECT : RECOMPOSITION OF ACCREDITATION COMMITTEE


FOR DPWH FIELD ENGINEERS
Series of 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 23

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 24

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &

Series of 2018 ASSIGNMENT OF DPWH PROJECT ENGINEERS AND


INSPECTORS
:
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 25

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 26

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 27

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 28

D.O. 95
Series of 2021
CamNorte Sub-District Engineering Office DE Romero
0/05/2025 Department Of Public Works and Highways 29

D.O. 95 SUBJECT : INTERIM PROCEDURES ON DESIGNATING AN


ACCREDITED DPWH FIELD ENGINEER FOR DPWH
Series of 2021 :
PROJECTS DURING THE COVID-19 PANDEMIC

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 30

D.O. 95 SUBJECT : INTERIM PROCEDURES ON DESIGNATING AN


ACCREDITED DPWH FIELD ENGINEER FOR DPWH
Series of 2021 :
PROJECTS DURING THE COVID-19 PANDEMIC

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 31

D.O. 95 SUBJECT : INTERIM PROCEDURES ON DESIGNATING AN


ACCREDITED DPWH FIELD ENGINEER FOR DPWH
Series of 2021 :
PROJECTS DURING THE COVID-19 PANDEMIC

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 32

D.O. 95 SUBJECT : INTERIM PROCEDURES ON DESIGNATING AN


ACCREDITED DPWH FIELD ENGINEER FOR DPWH
Series of 2021 :
PROJECTS DURING THE COVID-19 PANDEMIC

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 33

D.O. 95 SUBJECT : INTERIM PROCEDURES ON DESIGNATING AN


ACCREDITED DPWH FIELD ENGINEER FOR DPWH
Series of 2021 :
PROJECTS DURING THE COVID-19 PANDEMIC

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 34

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 35

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 36

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 37

Construction Supervision &


Management
Topics A: DUTIES,
RESPONSIBILITIES &
QUALITIES OF PROJECT
ENGINEERS, PROJECT
INSPECTOR, MATERIALS
ENGINEERS
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 38

DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall
planning and control of
the project.

b.) Ensures that materials and


workmanship are at all times
in accordance with plans and
specifications.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 INSPECTORS
:
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 39

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-
 Per DMC No. 49 S. 1994, Defining responsibilities of DPWH
Engineers Involved in the Implementation of DPWH
Projects.
 Quality of Materials is the primary responsibility of

Materials Engineers;
 Quality Control is primary responsibility of Quality
Engineers
 It must be kept in mind that the overall
supervision of the project shall be the
responsibility of the Project Engineer
D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &
ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


Department Of Public Works and Highways 40

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 41

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 42

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-
 What is a neglect of Duty?
defines simple neglect of duty or simple negligence
to mean “the failure of an employee or official to give
proper attention to a task expected of him or her,
signifying a disregard of a duty resulting from
carelessness or indifference.”

(underscoring and emphasis in the original)


[(The Supreme Court in the case of
Republic vs. Canastillo) No. 172729, June 8,
2007, 524 SCRA 546, 555]

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office ADE Romero


03/05/2025 Department Of Public Works and Highways 43

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-
What is the penalty for simple neglect of duty?
Simple neglect of duty is a less grave offense punishable
by suspension of one month and one day to six months;
whereas conduct prejudicial to the best interest of the
service, a grave offense, is punishable by suspension of
six months and one day to one year.

(underscoring and emphasis in the original)


[G.R. No. 224651 – Civil Service Commission &
The Office of the Solicitor General, Petitioner,
vs Edgar B. Catacutan, Respondent. July 03,

D.O. 115
2019 ]
SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &
ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 44

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-
 Based on the Managerial Policies of the government on

Administrative Supervision: " That it is the duty and


responsibility of respondent, as register of deeds, to
direct and supervise the activities of her office
(Projects) can never be over-emphasized. Whether
respondent exercised prudence and vigilance in
discharging his/her duties, he/she has not shown.”
[Office
(underscoring of the
and emphasis inOmbudsman
the original)
(Mindanao) vs. Cruzabra, G.R. No.
183507, 24 February 2010]

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 45

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


a.) In-charge of overall planning and control of the project-
 What is the difference between supervision and
directing?
Direction: It refers to issuing orders and instructions and
motivating subordinates to achieve the objectives and
goals. Supervision: It refers to observing the progress of
assigned tasks of employees or subordinates. Direct
supervision is a term that is used to refer to situations in
which a supervisor is present at all times. The supervisor
oversees activities as they occur and provides constant
direction, feedback, and assistance.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 46

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 47

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


b.) Ensures that materials and workmanship are at all times
in accordance with plans and specifications.
- The Project Engineer is authorized to reject materials
which fail to meet specifications requirements even though
they have previously passed requirements.
- The Project Engineer is authorized to require the
contractor to discontinue operations if the workmanship or
methods employed would adversely affect the quality,
durability or appearance of work.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 48

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 Ensures that materials and workmanship are at all times in
accordance with plans and specifications.
- The Project Engineer shall directly supervise the
sampling and quality control testing as well as check test to
verify the quality of materials for incorporation into the work.
- The Project Engineer may order the pre-testing/retesting
of construction materials. Under the conditions for
acceptance of materials, any material which had been
sampled and passed as satisfactory may be resample and
retested.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 49

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 What is ACCEPTANCE?
…defines as the procedure through which the client
agrees that an item of work, unit of material or project
has been furnished in accordance with the approved
specifications.
…means agreeing to receive something or the act of
receiving it.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 50

CONDITIONS FOR ACCEPTANCE OF


MATERIALS
1.) No material shall be incorporated into the work until
tested and found satisfactory.
2.) The approval of preliminary samples shall not be
considered as a guarantee of acceptance of all
materials from the same source, as the quality or
quantity of such materials.
3.) Any material which had been sampled and passed as
satisfactory may be resampled and retested.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 51

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 52

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


c.) Ensures that
inspections and tests
are carried out
promptly and timely.

d.) Witnesses critical activities of


the project. Signs-off at hold points
prior to proceeding with the next
activity
D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &
ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 53

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


c.) Ensures that inspections and tests are carried out
promptly and timely.
- If necessary, test shall be conducted for as long as the
project is not yet completed and there are materials not yet
tested prior to its actual use.
- Inspection are carried out promptly to:
a. Ensure that requirements of the contract documents
will be carried out.
b. Avoid use of unacceptable substitutes.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 54

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 Ensures that inspections and tests are carried out
promptly and timely.
c. Avoid making errors that might
result to unnecessary maintenance
cost.
d. Minimize extra work.
e. Materials and workmanship that
are guaranteed will be evaluated at
the time of inspection.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 55

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 56

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 57

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 58

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 59

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 60

Purpose of Issuance:

D.O. 193 SUBJECT : Administrative Action on Contracts


with Negative Slippage in Accordance
S. 2016 with the Revised IRR of R.A. 9184
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 61

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


Purpose of Issuance:
It has been observed that some projects with defects/deficiencies are
paid, either partially or fully, even without said corrected.
defects/deficiencies being corrected.

Henceforth, no project with noted defects/deficiencies shall be


accepted without prior correction.

For strict compliance.

D.O. 139 SUBJECT : Correcting Projects with Noted


Defects/Deficiencies Prior to Partial/Full
Series of 1994 Payment
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 62

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


d.) Witnesses critical activities of the project. Signs-off at
hold points prior to proceeding with the next activity
 What is the difference between a hold point and a witness
point?
The Hold point and Witness point are always found and
indicated in the Inspection and Test Plan. They are the
construction stages which may need supplementary
inspection or verification. The purpose is to make sure
specification requirements are complied accordingly and to
proceed for the following activities.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 63

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


Here is the best definition of Hold Point & Witness Point:

Hold Point is a mandatory verification point beyond which


a work cannot proceed without approval by the Project
Engineer or Project Inspector. The work cannot proceed
until the Project Engineer is able to verify the quality of the
completed work and releases the Hold by means of
Inspection Request approval.
Witness Point is an identified point in the process where the
Project Engineer may review, witness, inspect method or
process of work. The activities however may proceed.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 64

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Witness critical activities of the project.

- Suggested Frequency of Inspection


a. One Time: Only one inspection is required.
b. Critical Point: A one time inspection that may be performed at
a specific point in the construction sequence, before the next
phase of construction takes place.
c. Intermittent Spot-Checks: Random or regular spot checks.
d. Continuous Monitoring: Some operations, due to their
inherent critical or variable nature, require the full presence of an
inspector.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 65

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 66

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


e.) Checks/verifies
physical(AC)and
financial (DR) status
of the project.

f.) Checks/verifies statement


of
work accomplished.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 67

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Checks/verifies physical and financial status of the project.
- “It is very important to keep the Head of the
implementing office inform about the project status, cost
timing and prospects. This will enable to maintaining
credibility, protect the organization from high risk, and
allow them to intercede when needed.”
(Chapter 5, Title V (DPWH), Book IV, Executive
Oder (EO) No. 292 s. 1987, the “Administrative
Code of 1987,” as amended, 25 July 1987)
(Chapter 4, Title V (DPWH), Book IV, EO 292, s.
1987 the “Administrative Code of 1987,” as
amended, 25 July 1987)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 68

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Checks/verifies physical and financial status of the
project.
 “SEC. 23. District Engineer. – The District Engineer
of or within a province or city shall be accountable
for the efficient and effective conduct of the duties
and responsibilities of the District Office of which he
is the head. x x x.” (Chapter 5, Title V)

(DPWH), Book IV, Executive Order (EO) No. 292 s. 1987, the
“Administrative Code of 1987,” as amended, 25 July 1987)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 69

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Checks/verifies physical and financial status of the project.
 “SEC. 32. Nature of Public Office. – Public office is a
public trust. Public officers and employees must at
all times be accountable to the people, serve them
with utmost responsibility, integrity, loyalty, and
efficiency, act with patriotism and justice, and lead
modest lives.” [underscoring supplied] (Chapter 9,
Executive
Book I, (EO) No. 292 s. 1987, the “Administrative Code of 1987,”
as amended, 25 July 1987) &
[Article XI ACCOUNTABILITY OF PUBLIC OFFICERS], 1987 Philippine
Constitution]

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 70

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


f.) Checks/verifies statement of work accomplished.
- The Project Engineer shall ascertain and determine by
measurement the value of work done. He shall certify the
monthly statement of work accomplished by the contractor.
“Quantities reported in the CQCA should tally with
the quantities being claimed for payment in the SWA.
There should be corresponding test results accompanying
the CQCA”.
(DPWH, DO No. 84 series of 2013 )

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 71

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


f.) Checks/verifies statement of work accomplished.
The Following Reminders are provided to improve upon Project &
Contract Management:
1. With regard to terminated contracts;
2. With regard to application of Discounts to Pay Items in
Contracts & PCMA;
3. Approval of VO and/or TE for an extended period of time;
4. Approved VO and/or TE must have an Approved Revised
Construction Schedule as per MEMO dated May 25, 2011;
5. If the approved VO does not include a TE…Please be reminded of
Contract Time Extension Policies in DO 144 s 2016;
(DPWH MEMO dated April 16,
2018 )

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 72

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


f.) Checks/verifies statement of work accomplished.
6. Implementing Office (IOs) which report completion of units in a pay

item, and then have a VO which reduces that pay item quantity to
less than what has been reported as accomplished, is a cause for
concern given either the reporting is being overstated to begin with,
or the VO is incorrect. Neither is an acceptable practice so IOs are
cautioned to avoid merely “desk reporting” on pay item
accomplishments and ensure actual accomplishment as per the
PCMA Procedure Manual;

(DPWH MEMO dated April 16,


2018 )

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 73

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 74

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


g.) Approves Concrete
Pouring Permit & Other
Job Control Forms

h.) Issues work


suspension orders and
other site instructions.
D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &
ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 75

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 Approves concrete pouring permit.
Before issuance of pouring permit, check the following:
1.) Vibrators (at least 2)
2.) Concrete saw (at least 2)
3.) Protective Covering Materials or Plastic covers
4.) Steel Forms/Formworks
5.) FDT
6.) Line and grade alignment
7.) Barricades/Warning Signs/Flagman
(DPWH, DO No. 211 series of 2000 & DPWH Pouring Permit
Newform 2020)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 76

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 And other job control forms…

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 77

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 And other job control forms…

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 78

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


h.) Issues work suspension orders and other site instructions.
- The Project Engineer shall have the authority to suspend the work
wholly or partially by written order for such period as may be
deemed necessary.
- The Project Engineer, during the progress of the works, has the
power to order (site instruction) in writing from time to time;
1.) the removal from site any material not in accordance with
the contract or plans and specifications.
2.) the substitution of proper and suitable materials, and
3.) the removal and proper re-execution of any work which, in
respect of materials, is not accordance with the contract.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 79

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 80

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


j.) Maintains and/or updates field
documentation such as logbook,
plans and program of works,
schedules, S-curve, laboratory test
results etc.

i.) Prepares proposed Change Order,


Extra Work Order or Supplemental
Work Agreement, when necessary.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 81

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


i.) Prepares proposed Change Order, Extra Work Order
or Supplemental Work Agreement, when necessary.
- The approved plans and specifications prescribe a complete work
or improvement. However, due to differing subsurface or latent
physical conditions at site and/or unforeseen conditions, adjustment
of plans to field conditions which are not foreseeable at the time of
advertisement will be necessary during construction. Adjustments
maybe done thru variation orders. When the need arises, the Project
Engineer shall prepare;
1.) the proposed order or supplemental agreement,
2.) the corresponding plans and detailed estimates, and
3.) the justifications.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 82

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


j.) Maintains and/or updates field documentation such as
logbook, plans and program of works, schedules, S-curve,
laboratory test results etc.

- The Project Engineer should see to it that field office


shall have a ready copy of all documents relative to the
project and that all records including a copy of the “As
Built plan” will be turned over to the implementing office
after its completion.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 83

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 84

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


k.) Resolves problems
encountered in the
implementation of the
project.

l.) Coordinates with Project


Consultants, NGO’s and other
officials concerned in project
implementation.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 85

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


 Resolves problems encountered in the implementation of
the
project.
- The Project Engineer may or may not approve of the
authorized representative of the contractor who oversees the
execution of the work. He is at liberty to object to and require
the contractor to remove from the works any personnel who
misconducts himself or is incompetent or negligent in the
proper performance of his work or undesirable person.
- The Project Engineer has the authority to require the
contractor to remove and replace or correct work he finds not in
conformity with plans and specifications.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 86

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Resolves problems encountered in the implementation of the

project.
- The Project Engineer may maintain the completed work
chargeable against the contractor’s money if he fails to
satisfactorily maintain said completed work.
- The Project Engineer shall inform the contractor re-findings
of the final inspection team and give necessary instructions.
- The Project Engineer shall refer to higher authorities
questions/inquiries he could not answer with the assurance
that the answer with the assurance that the answer shall be
obtained.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CasmNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 87

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


l.) Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 The Project Engineer shall:
- As a public official, listen attentively and sympathetically to
questions or complaints and to treat them with respect,
- Welcome public interest in his project,
- Give truthful information which are in line with engineering
ethics, and
- Advise the implementing office of the completion of the project.
He and the constituted Inspectorate Team shall undertake final inspection
of the works. Final acceptance of the project will only be made if all
works contemplated for the project have been done in accordance with
plans and specifications.

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 88

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Coordinate with other departments, agencies, institutions and
organizations, especially local government units in the district in
the planning and implementation of infrastructure projects.
(Chapter 5, Title V [DPWH], Book IV, EO 292, s. 1987 the “Administrative
Code of 1987,” as amended, 25 July 1987)

 Communicate frequently with client and other interested parties to


ensure continual understanding of their requirements, needs and
expectations. (Clause 5.1.1. ISO 9000, the “Introduction and Support Package:
Guidance on the Concept and Use of the Process Approach for
Management Systems,” ISO/TC 176/SC 2/N 544R3, 15 October
2008; Executive Order (EO) No. 605 s. 2007; and Republic Act
(RA) No. 9013)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 89

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 “Section 8. Government officials shall make themselves available
to their staff for consultations and dialogues.”
(Rule III, Rules Implementing Republic Act (RA) No. 6713, the
“Code of Conduct and Ethical Standards for Public Officials and
Employees,” 21 April 1989)
 “Section 5. Every department, office and agency shall consult the
public they serve for the purpose of gathering feedback and suggestions
on the efficiency, effectiveness and economy of services. They shall
establish mechanisms to ensure the conduct of public consultations and
hearings.”
[underscoring supplied] (Rule III, Rules Implementing Republic Act
(RA) No. 6713, the “Code of Conduct and Ethical Standards
for Public Officials and Employees,” 21 April 1989)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 90

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 “SEC. 22. District Office. Conduct continuing
consultations with the local communities, take
appropriate measures to make the services of the
Department responsive to the needs of the general
public, compile and submit such information to the
Regional Office and recommend such appropriate
actions as may be necessary;
(Chapter 5, Title V (DPWH), Book IV, Executive
Order (EO) No. 292 s. 1987, the “Administrative
Code of 1987,” as amended, 25 July 1987)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 91

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CAmNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 92

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
HIGHLIGTHS:

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 93

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
HIGHLIGTHS:

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &

ASSIGNMENT OF DPWH PROJECT ENGINEERS AND


Series of 2018 INSPECTORS
:
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 94

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
HIGHLIGTHS:

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 95

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
HIGHLIGTHS:

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018 :
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 96

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
Sec.1.(c) It is likewise the policy of the State to require
all national agencies and offices to conduct periodic
consultations with appropriate local government units,
non-governmental and people's organizations, and
other concerned sectors of the community before any
project or program is implemented in their respective
jurisdictions. [underscoring supplied] DILG-Local Gov’t
Code of the Philippines, General Provision,
Chapter 1, Title 1, Sec. 1,Par. (c)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 97

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS


o Coordinates with Project Consultants, NGO’s and other
officials concerned in project implementation.
 Reiterated Dos in this Issued Order-
SEC. 25. (b) National agencies and offices with project
implementation functions shall coordinate with one
another and with the local government units
concerned in the discharge of these functions. They
shall ensure the participation of local government
units both in the planning and implementation of said
national projects. [underscoring supplied] DILG-Local Gov’t
Code of the Philippines, General Provision,
Chapter 3, Article 1, Sec. 25. Par. (b)

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
INSPECTORS
Series of 2018
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 98

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 99

CamNorte Sub-District Engineering Office DE Romero


REMINDERS...

TO ALL
DOING THE RIGHT PROJECTS, AT THE RIGHT PRICE AND THE RIGHT QUALITY

100
03/05/2025 Department Of Public Works and Highways 101

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS

Reminders:

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 102

4.0 DUTIES & RESPONSIBILITIES OF FIELD ENGINEERS

D.O. 115 SUBJECT : REVISED GUIDELINES ON THE ACCREDITATION &


ASSIGNMENT OF DPWH PROJECT ENGINEERS AND
Series of 2018 :
INSPECTORS

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 103

Purpose of Issuance:

D.O. 21 SUBJECT : Revised Guidelines on the Installation of


Project Billboards
S. 2017
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 104

Purpose of Issuance:

D.O. 11 SUBJECT : Amendment to DO No.21 series of 2017


Revised Guidelines on the Installation of

S. 2022 Project Billboards

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 105

Purpose of Issuance:

D.O. 11 SUBJECT : Amendment to DO No.21 series of 2017


Revised Guidelines on the Installation of

S. 2022 Project Billboards

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 106

Purpose of Issuance:

D.O. 15 SUBJECT : Guidelines on the Processing and


Approval of “As-Staked” Plan
S. 2016
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 107

Purpose of Issuance:

(COA Circular No. 2012-001 dated June 14, 2012)

D.O. 55 SUBJECT : Standards for Photographs for Progress


Billing for Roads Infrastructure Projects
S. 1994
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 108

Purpose of Issuance:

D.O. 12 SUBJECT : Disposal & Stockpiling of Materials including


Parking of Equipment within the Construction
S. 2016 Limits or Vicinity of all DPWH on-going
Projects
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 109

Purpose of Issuance:

D.O. 12 SUBJECT : Disposal & Stockpiling of Materials including


Parking of Equipment within the Construction
S. 2016 Limits or Vicinity of all DPWH on-going
Projects
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 110

Purpose of Issuance:

D.O. 12 SUBJECT : Disposal & Stockpiling of Materials including


Parking of Equipment within the Construction
S. 2016 Limits or Vicinity of all DPWH on-going
Projects
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 111

Purpose of Issuance:

D.O. 12 SUBJECT : Disposal & Stockpiling of Materials including


Parking of Equipment within the Construction
S. 2016 Limits or Vicinity of all DPWH on-going
Projects
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 112

Purpose of Issuance:

D.O. 135 SUBJECT : Strict Compliance to Road Works Safety & Traffic
Management & Construction safety & Health
Requirements during Construction & Maintenance of
S. 2015 Roads & Bridges
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 113

Purpose of Issuance:

SUBJECT : Guidelines in the Disposal & Management


D.O. 168of Spoils & Debris generated from all on-going &
S. 2015 Completed Construction & Maintenance Projects and
the Impositions
CamNorte Sub-District Engineering Office of Sanctions for Violations thereof
DE Romero
03/05/2025 Department Of Public Works and Highways 114

Purpose of Issuance:

SUBJECT : Guidelines in the Disposal & Management


D.O. 168of Spoils & Debris generated from all on-going &
S. 2015 Completed Construction & Maintenance Projects and
the Impositions of Sanctions for Violations thereof
Albay 1st District Engineering Office
ADE Romero
06/01/2022 Department Of Public Works and Highways 115

Root Observation:

D.O. 05
S. 2012
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 116

Purpose of Issuance:

D.O. 05
S. 2012
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 117

PRESIDENTIAL DECREE NO. 1759


PENALIZING CONTRACTORS AND SUB-
CONTRACTORS WHO VIOLATE ANY
MATERIAL PROVISIONS OF CONTRACTS
INVOLVING PUBLIC WORKS PROJECTS
OF THE GOVERNMENT, AND PUBLIC
OFFICIALS WHO ALLOW SUCH
VIOLATIONS, AND FOR OTHER
PURPOSES

P.D. 1759
S. 1981
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 118

SECTION 1
Any provisions of Law to the contrary notwithstanding,
contractors and sub-contractors who violate any material
provisions of contracts involving public works projects, either
as to materials, quality and quantity of work, resulting to the
prejudice of the government, shall suffer the penalty of from
twelve (12) years to life imprisonment at the discretion of the
Court and shall, in addition suffer perpetual disqualification
from participating in any government contracts.

P.D. 1759
S. 1981
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 119

The offending contractor or sub-contractor shall


further be liable for the cost of reconstructing such
public works project in accordance with the
specifications agreed upon.
In case of corporations, partnerships or
associations, the President, General Manager or
any responsible Chief Executive Officer/s shall be
liable.

P.D. 1759
S. 1981
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 120

SECTION 2
Any public official who, by reason of the duties
of his office, shall consent, or through abandonment
or negligence, permit the contractor or sub-contractor
to commit the violations mentioned in Section 1
hereof, shall suffer the penalty of from twelve (12)
years to life imprisonment and perpetual
disqualification to hold any public office.

P.D. 1759
S. 1981
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 121

D.O. 193
S. 1992
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 122

Purpose of Issuance:

D.O. 171 SUBJECT : Policy Guidelines on the Maintenance of


National Roads & Bridges
S. 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 123

MECHANISMS FOR IMPOSITION OF SANCTION and ISSUANCE


OF REWARD

D.O. 171 SUBJECT : Policy Guidelines on the Maintenance of


National Roads & Bridges
S. 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 124

MECHANISMS FOR IMPOSITION OF SANCTION and ISSUANCE


OF REWARD

D.O. 171 SUBJECT : Policy Guidelines on the Maintenance of


National Roads & Bridges
S. 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 125

MECHANISMS FOR IMPOSITION OF SANCTION and ISSUANCE


OF REWARD

D.O. 171 SUBJECT : Policy Guidelines on the Maintenance of


National Roads & Bridges
S. 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 126

MECHANISMS FOR IMPOSITION OF SANCTION and ISSUANCE


OF REWARD

D.O. 171 SUBJECT : Policy Guidelines on the Maintenance of


National Roads & Bridges
S. 2015
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 127

Questions?

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 128

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 129

ROADS
 Materials other than the required for
Item 200/Item 201 were used

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 130

ROADS
CORRECTIVE
ACTIONS/RECOMMENDATIONS:
Deduct the amount equivalent to the actual
quantity of materials incorporated into the project
not in accordance with the required materials.

Replace with correct materials in accordance with


item 200/201 at the expense of the contractor.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 131

BRIDGE
 Plywood was used instead of the
required pre-molded joint filler from
back wall to girder joints.
CORRECTIVE
ACTIONS/RECOMMENDATIONS:
 Require the contractor, at his own expense, to
remove the plywood used for the back wall to
girder joints and replace it with the required
pre-molded joint filler.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 132

SCHOOL BUILDING
S Deficient in thickness of the on fill slab was noted.

CORRECTIVE
ACTIONS/RECOMMENDATIONS:
 Require the Project/Resident/Materials Engineers
to explain in writing why the defects/deficiencies
occurred despite their presence in the project.

Deduct payment due to the contractor the amount


equivalent to the thickness deficiency of the slab.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 133

WATER SUPPLY PROJECTS


 Poor location of the completed deep well.

CORRECTIVE ACTIONS/RECOMMENDATIONS:

 Require the Project Engineer to explain in


writing why the deep well was constructed at a
poor location.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 134

FLOOD CONTROL AND DRAINAGE


 Sections of driven steel sheet piles were not
interlocked with each other.
CORRECTIVE ACTIONS/RECOMMENDATIONS:
 Require the contractor, at his own expense, to
correct the interlocking of the sections of driven
steel sheet piles.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 135

MISCELLANEOUS
 Partial billing was made even without the required
test, test reports on beam samples as basis for
payment.
CORRECTIVE
ACTIONS/RECOMMENDATIONS:
Require the Project/Materials Engineer to explain in writing
why partial payment was allowed in the project even
without the required test reports on beam samples.

 Undertake core tests to determine if concrete strength is


acceptable.
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 136

MISCELLANEOUS
 The project has already incurred a negative
slippage.
CORRECTIVE ACTIONS/RECOMMENDATIONS:
 Require the Project Engineer to explain in
writing why no calibrated action was
undertaken on the negative slippage per
D.O. 102, series of 1988.

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 137

CamNorte Sub-District Engineering Office DE Romero


03/05/2025 Department Of Public Works and Highways 138

FINAL CLAUSE
&
THINGS TO
REMEMBER
CamNorte Sub-District Engineering Office DE Romero
03/05/2025 Department Of Public Works and Highways 139

CamNorte Sub-District Engineering Office DE Romero


DPWHDepartment of
Public Works
& Highways

CamNorte Sub-District
Engineering Office
End of Presentation . . .

Thank
DOING THE RIGHT PROJECTS, AT THE RIGHT PRICE AND THE RIGHT QUALITY

141
Republic of the Philippines
Department of Public Works and Highways

THANK YOU !
142
03/05/2025 Department Of Public Works and Highways 143

CamNorte Sub-District Engineering Office DE Romero