SPM Unit Iv

The document discusses the challenges of software effort estimation, including the complexity of software, subjective nature of estimates, and the impact of changing technologies. It outlines the importance of accurate estimates for project success, detailing various estimation techniques such as bottom-up, top-down, and analogy-based methods. Additionally, it highlights the consequences of over- and under-estimating projects, emphasizing the need for historical data and careful measurement of work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views24 pages

SPM Unit Iv

The document discusses the challenges of software effort estimation, including the complexity of software, subjective nature of estimates, and the impact of changing technologies. It outlines the importance of accurate estimates for project success, detailing various estimation techniques such as bottom-up, top-down, and analogy-based methods. Additionally, it highlights the consequences of over- and under-estimating projects, emphasizing the need for historical data and careful measurement of work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 24

Software effort

estimation
Difficulties of Estimation
 Where are estimates done?
 Problems of over- and under- estimate
 Estimation techniques


What makes a successful
project?
Deliverin
g: Stage
● agreed s:
functionality 1. set
● on targets
time 2. Attempt to achieve
● at the agreed cost targets

● with the required quality

BUT what if the targets are not


achievable?
2
What makes a successful
project?
 Targets are set for a project and the project
manager tries to meet them

 A project manager has to produce:


 An estimate of the effort.
 An estimate of the activity durations.

 An estimate of

 effort Cos
affects t
 An estimate
of
 activity durations The delivery
4
affects time
Some problems with
estimating
 Nature of
 Complexity and invisibility of software.
software.
 Subjective nature of much of estimating
 Over-estimating small tasks and
 Under-estimating large ones.
 Political pressures
 Different objectives of people in an organization
 Managers may wish to reduce estimated costs in
order to for
support winacceptance of a project
proposal
4
Some problems with
estimating
 Changing technologies
 Technology is rapidly changing, making the
experience of previous project estimates difficult
to use in new ones.
 Projects differ
 Experience on one project may not be
applicable to another

5
Where are estimates
done?
Estimates are carried out at different stages of a
software project for a variety of reasons.
 Feasibility study
 Estimates here conforms that the benefits of
the potential system will justify the costs
 Strategic planning
 Project portfolio management will involve:
 Estimating benefits and costs of new
applications (projects) to allocate priorities.
 Such estimates may also influence the scale
of development staff recruitment
6
Where are estimates
done?
 System specification
 Design shows how user requirements will be
fulfilled.
 Estimating The efforts needed to implement
different design
proposals.
 Estimates at the design stage will also confirm
that the
feasibility study is still valid

7
Where are estimates
done?
 Evaluation of suppliers proposals
 A manager could consider putting development to
tender
 Potential contractors would examine the
system specifications and produce estimates (their
bid).
 The manager can still produce his own estimates
why?
 To question a bid that for instance that seems too
low which could be an indication of a bad understanding
of the system specifications.
8
 Or to compare the bids to in-house development
Where are estimates
done?
 Project planning
 As the planning and implementation of the
project becomes more detailed
 More estimates of smaller work components
will be made
 These will confirm earlier broad
estimates
 And support more detailed planning (e.g.
staff allocation)

9
Over- and under-
estimating
 An over-estimate is likely to cause project to take
longer than it would otherwise

 This can be explained by the application of two laws:


 Parkinson’s Law: ‘Work expands to fill the time
available’
 Thus, e.g. for an easy task over
estimating the duration required to complete it
will cause some staff to work less hard to fill the
time.
 Brook’s Law: putting more people on a late job
makes it later
10
 So overestimating the effort required to
Over- and under-
estimating
 Underestimating a project: Can cause the project to not
be delivered on time or cost
 but still could be delivered faster than a more generous
estimate
 On the other side the danger of underestimating a

project is the effect on the quality

 Zeroth law of reliability: if a system doesn't have to be


reliable it can meet any other objective

11
Basis for successful
estimating
A. The need for historical data.

 Most estimating methods need information about past


projects

 Care has to be considered when applying past


performance to new projects because of possible
differences in factors such as:
 Different programming languages
 Different experience of staff
 Different terminology

There are international Data Base containing data about thousands of


projects that can be used as reference
12
Basis for successful
estimating
B. Measuring work.

 The time and cost to implement software depends on:


 The developer’s capability and experience
 The technology that will be used

 The usual practice is to start by


expressing work size independently of the
effort, using measures such as:
(
a
)
S
L
O
13
C
O
A taxonomy of
estimating
methods
 Bottom-up - activity based, analytical

 Parametric or algorithmic models e.g.


function points

 Expert opinion - just guessing?

 Analogy - case-based, comparative

 Parkinson and ‘price to win’

14
Bottom-up versus top-
down

 Bottom-up
 use when no past project data
 identify all tasks that have to be done
– so quite time- consuming
 use when you have no data about similar
past projects

 Top-down
 produce overall estimate based on project
cost drivers
 based on past project data
 divide overall estimate between jobs to be
15
done
Bottom-up estimating

1.Break project into smaller and smaller


components

2.Stop when you get to what one person can do in


one/two weeks

3.Estimate costs for the lowest level activities

4.At each higher level calculate estimate by adding


estimates for lower levels

16
Top-down Estimation

 It is associated with parametric or algorithmic


models.
 A formula for a parametric model:
 Effort = (System Size) * (Productivity Rate)

 The model of forecasting the SW


development effort has two components
 System size is a method of assessing the
amount of
work
 Productivity rate is a method of assessing the
rate of work at which the task can be done
17
Top-down Estimation

 Example:

System Size = 3 KLOC.

Productivity Rate = 40 days per


KLOC.

Effort = (System Size) *

(Productivity Rate) Effort = 3* 40

=120 Days.

System Size is a size driver.

Productivity Rate is a productivity driver.


18
Top-down Estimation

 Other parametric models:


 Function points is concerned more with task
sizes.
 C O C O M O is concerned more with
productivity rate.

19
Top-down estimates

Estimat  Produce overall


overal estimate using
e
100
l effort driver(s)
days
projec
 distribute
t proportions of
design code test overall estimate to
30% 30% 40% components
i.e. i.e. i.e. 40
30 30 days
days days

SPM (5e) Software effort estimation© 21


The McGraw-Hill Companies, 2009
Estimation by Analogy

 It is also called case-based reasoning.


 For a new project the estimator identifies the
previous
completed projects that have similar characteristics to
it.
 The new project is referred to as the target
project or target case
 The completed projects are referred to as the source
projects or source case
 The effort recorded for the matching source case is
used as the base estimate for the target project
 The estimator calculates an estimate for the new
project by adjusting the (base 21estimate) based on the
differences
Estimation by Analogy

 There are software tools that automate this


process by selecting the nearest project cases to
the new project.
 Some software tools perform that by
measuring the
 Euclidean distance between cases
(projects).
 The Euclidean distance is calculated as
follows:
distance= square-root of ((target_parameter1-
source_parameter1)2 ….
22
+ (target_parametern -source_parametern )2 )
Estimation by Analogy
Example
 Assume that cases are matched on the basis of
two parameters, the number of inputs and the
number of outputs.
• The new project (target case) requires 7 inputs
and 15 output
•You are looking into two past cases (source
cases) to find a better analogy with the target
project:
• Project A: has 8 inputs and 17 outputs.
• Project B: has 5 inputs and 10 outputs.
Which is a more closer match for the new project A or
23
project B?
Answe
r

 Distance between new project and project A:


 Square-root of ((7-8) 2 + (15-17) 2)= 2.24

 Distance between new project and project B:


 Square-root of ((7-5) 2 + (15-10) 2)= 5.39
Project A is a better match because it has less distance than project B to
the new project

24