Chapter 3 Feasibility Analysis
Chapter 3 Feasibility Analysis
Feasibility
Analysis
1
Feasibility Study
- Feasibility study is related to analysis
of the viability of the identified
project to support decision making of
investment.
- As its name implies, it is a study to
decide whether the identified project
is attractive enough to go for
implementation.
- The study needs inputs from many
professional disciplines for 2
Feasibility Analysis: A Schematic Diagram
P
r Generation of
e
l
ideas
i
m Initial Screening
i
n
a
r Is the Idea Prima Facie
y Promising?
w Yes No
o Plan Feasibility
r Analysis Terminate
k
A
Conduct Conduct
n
Market Technical
a
l Analysis Analysis
y Conduct
s
i E Financial
s v Analysis
a
l Conduct Economic and Ecological
u analysis
a
t Is the project
i Worthwhile? No
o Yes Termina
n Prepare Funding
Proposal te 3
Why Feasibility Study?
- To find if there is adequate demand for the
project’s output.
- To find if there is availability of suitable
technology and inputs
- To find the best options
- To examine the project’s financial and
economic viability
- To answer if the project meets the
environmental regulations and priority of
the nation
4
Areas of Analysis in Feasibility study
Demand/ Need and Market Analysis
Technical Analysis
Management Analysis
Financial Analysis
Economic Analysis
Environmental Analysis
Social Analysis
5
Demands
Should government make six lane fast track
road?
Should proposed cement factory plant be
able to produce 100 metric ton of cement per
day?
How many rooms to build in Sheraton Hotel?
6
Market and Demand Analysis
7
Activity
Conduct a market demand feasibility analysis for the
project idea you have identified in the previous section (in
this case, you may use the template given below):
Objective:
To assess the demand for the proposed product or service in the target
market.
Steps:
1. Define the Target Market:
◦ Identify the demographics (age, gender, income level, etc.).
◦ Determine geographic location and market segments.
2. Analyze Market Trends:
◦ Research industry growth rates.
◦ Identify consumer preferences and emerging trends.
3. Competitor Analysis:
o Identify key competitors.
8
o
Activity…Cont’d
9
Technical Analysis
Every project must be technically feasible.
Technical analysis is related to examining
whether the project under study is
technically feasible to setup and
operate to produce service/product.
For example, in agricultural project of
Apple farming, types of field, soil test,
temperature required in selected location,
location selection, plantation distance
between plants, variety, etc. need to be
analyzed.
10
Technical Aspects to be
Considered
Technology:
• Choice of technological process and/ or
appropriate technology,
• Is the technology proven or tested?
• Does the technology/ process/ equipment
technically fit with the facility’s existing
technology/process/ equipment & machinery?
• Equipment capacity & whether it is as per
requirement
• List of recommended equipment suppliers.
• Reputation of the suppliers and
performance guarantees 11
Technical Aspects to be considered…Cont’d
15
Types of Project Selection
Models
Subtypes of Numeric Models
a) Ranking by Inspection
b) Return on investment (ROI)
c) Payback Period
d) Accounting Rate of Return
(ARR)
16
A) Ranking by Inspection (RI)
Basic question: Given alternative investments
which one should be implemented and which
one should be discarded in a mutually
exclusive investments?
There may be an alternative as to build
a hotel or a factory on the same site.
The investor might choose to start one with
limited resources he/she has.
RI consists of choosing the best investment
by comparing the net proceeds of
alternative investments.
The project that has more cash proceeds will
be preferred though are some peculiarities on
17
Ranking by Inspection (RI) Steps……
Comparing the net proceeds of A & B
projects, we can find out which project has
shorter life period
Compare the net proceeds of the short
lived project with long lived one
If the two have the same initial investment
& proceeds throughout the period of the
short lived investment; & if the long lived
investment continues to earn income after
the end of the short lived one, then the long
lived one is more desirable as the second
project continues to earn proceeds while the
first one has ended
18
Net Cash Flow of 4 Hypothetical Projects with Identical
Initial Investment Outlays & Life Periods
Project Initial Net Cash Proceeds in Years
Investment Cost
1 2 Total
20
E.g of ROI Computations
Investmen Cost ($) Average Average Ranking
t income ($) income on
cost (%)
A 20,000 0 0 4
B 20,000 660 3.3 3
C 20,000 800 4 1
D 20,000 800 4 1
N.B: Project C & D are preferred than A or B, but B is
preferred than A.
Weakness of ROI: It doesn’t take into account the timing of
the cash flow.
21
C) Payback
Period
The payback period is the length of time from
the beginning of the project until the sum of
net incremental benefits of the project equal
to total capital investment.
It is the amount of time it takes to recover the
original/investment cost.
The method is very simple.
Moreover, it is a good measure when the
project has problem of liquidity.
The pay-back period is also a common, rough
means of choosing among projects in business
enterprise, especially when the choice entails
high degree of risk.
◦ Payback rule: If the calculated payback period is less
than or equal to some pre-specified payback period,
then accept the project. Otherwise reject it. 22
Payback Period
This method has two important weaknesses:
First, it fails to consider the time & amount of net
benefits after the payback period.
Second, it does not adequately take into account the
time value of money even in the payable periods.
Payback Analysis
◦ how long will it take (usually, in years) to pay
back the project, and accrued costs:It indicates
the number of years the project will take to repay
its investment cost
It is the length of time between the starting time
of the project and the time when the initial
investment is recovered in the form of yearly
benefits
23
Payback Period
Peak
cumulative
cash flow
Payback period
Total
+ve profit
Birr
Time
h
as
- ve
fc
w o
flo te
Ra
Cash trough Calculate annual net cash flow
Accumulate year on year
Cumulative net Plot on graph of CNCI against time
cash inflow
24
Payback Period
Ifthe expected cash inflow is a constant
sum:
25
Payback Period
But if the net cash inflow is the same across
years, we use a simple formula to get the
payback period.
Example:
1. If Birr 2 million is invested to earn Birr 500,000
per annum for 7 years, the pay back period is
computed as follows:
Pay back period = Br 2million/500,000= 4yrs
26
Payback Period
Example 1:
$200 $420 $645 $855
Time
0 1 2 3 4
$-600
27
Payback Period
Assume that a firm is considering two
projects: project A and project B, each
requiring an investment of Br100 million. The
cost of capital is 10%. Below is the summary
of expected net cash flows in millions.
Then find the payback period for the two
projects and indicate which project should be
chosen.
28
Payback Period
29
Payback Period
Alternative Year Investment cost Net incremental Cumulative net
projects benefits incremental benefits
I 0 20000 -
1 2000 31000
2 8000
3 12000
4 9000
II 0 20000 -
1 2000 34000
2 12000
3 8000
4 12000
III 0 20000 -
1 1000 37000
2 5000
3 6000
4 8000
5 10000
6 5000
7 2000
30
Merits of payback period as an
investment appraisal technique
A. Simplicity
B. Rapidly changing technology, If new plant
is likely to be scrapped in a shorter period
because of obsolescence, a quick payback
is essential,
C. Payback favors projects with a quick return
Rapid project payback leads to rapid
company growth
Rapid payback minimizes risk, Etc
31
Critics of payback period as an
investment appraisal technique
Project return may be ignored- in
particular, cash flows arising after the
payback period are ignored.
Timing is ignored
Lack of objectivity-what length of time
should be set as the minimum payback
period
Project profitability is ignored-
32
D) Accounting Rate of Return (ARR)
The accounting rate of return (ARR),
expresses the profit forecast as a
percentage of the capital expenditure
involved.
ARR is also known as accrual accounting rate
of return, unadjusted rate of return model and
the book value model
ARR is a measure of profitability in accounting
terms.
This method aims to quantify the profits
expected from investment projects under
consideration
There are different methods of calculating the
ARR 33
Formulas For ARR
ARR=Average Income after tax
Initial Investment
ARR=Average Income after tax
Average Investment
ARR=AIAT, but before Interest
Initial Investment
ARR=AIAT, but before Interest
Average Investment
ARR= Average Inc. b/r Int. &tax
Initial Investment
ARR= Average Inc. b/r Int. &tax
Average Investment
34
Accounting Rate of Return (ARR)…Cont’d
Illustration:
Assume 90,000 Br is invested in a project
with the following after tax net profits.
Year 1 2 3
36
Gross cash flows
Time 0 1 2 3 4 5
(yrs)
Revenu 100 100 200 200 200
e
Costs (300) 20 20 20 20 20
Gross -300 80 80 180 180 180
cash
flows
37
Undiscounted Cash flow before
tax
Year 0 1 2 3 4 5
Cash -300 80 80 180 180 180
flows
Cum cash -300 -220 -140 40 220 400
flow
38
Graphic Representation of Cash Flows
500
400
300
200
100
Cash flows
Cum cash flow
0
0 1 2 3 4 5
-100
-200
-300
-400
39
Time Value of Money
Cash flow is an important concept in today’s
business language
Cash inflow or outflow usually occurs over a
period of time.
This leads us to consider the time value of
money
The value of money depends on when the
cash flow occurs
Thus, the earlier value of money is
greater than the latter one
Why?
Reasons: interest or rent, uncertainty,
inflation
40
Methods of estimating time value
of money
a)Compounding and discounting
◦ Cash flows occur at different points of
time
◦ For meaningful comparison, all these
cash flows should be assessed at
the same point of time
◦ Either the cash flow occurring today
has to be converted into its
equivalent at a future date or the
cash occurring later has to be
converted back to today’s value.
◦ The future value is calculated 41
b) Compounding
With simple interest, the future value is
determined
t
by:
FVt PV (1 r )
43
d) NPV
The process of discounting, used for
calculating the PV, is simply the inverse of
compounding.
t
FVt PV (1 r )
44
NPV
Present value of a single amount
What is the PV of Birr 1,000 in 3 years at 10%
interest rate?
=909.09
091
=826.44
628
=751.31
48
45
NPV: as Investment Criteria
NPV: it determines the net present value of all cash flows
by discounting them by the required rate of return.
n
Ct
NPV A0 t
i 1 (1 r )
Where,
Ct = the net cash flow in period t
46
Discounted cash flows for
interest 10%
Year 0 1 2 3 4 5
Cash -300 80 80 180 180 180
flows
DF (10%) 1 0.909 0.826 0.751 0.683 0.621
Discounte -300 72.72 66.08 135.18 122.94 111.78
d Cash
flow
(DCF)
Cum DCF -300 -227.28 -161.2 -26.02 96.92 208.7
NPV = 208.7
DPBP= 3.2 years
47
Graphical Representation of Cash
flows
500
400
300
200
100
0
1 2 3 4 5
-100
-200
-300
Cash flows NDCF Discounted Cash flow (DCF) Cum DCF
48
Collaborative Learning Exercise
49
NPV
Year Cash flow
0 Birr (1,000,000)
1 200,000
2 200,000
3 300,000
4 300,000
5 350,000
If the cost of capital (discount rate) is 10%, then NPV is calculated as follows
50
NPV
The NPV represents the net benefit over and above the
compensation for time and risk. Hence, the decision rule
associated with the net present value criterion is:
accept the project if the NPV is positive and reject it if
NPV is negative.
Properties of NPV:
◦ NPVs are additive:- The NPV of a package of projects is
simply the sum of the net present values of individual
projects included in the package.
◦ Intermediate Cash Flows are Invested at Cost of
Capital:- The NPV rule assumes that the intermediate
cash flows of a project-that is, cash flows that occur
between the initiation and the termination of the project-
are reinvested at a rate of return equal to the cost of
capital
◦ NPV calculation permits time-varying discount
rates:- when the discount rate changes over time, we use 51
NPV
Interest rate 14% 15% 16% 18% 20%
Investment 12000
Cash flow 4,000 5,000 7,000 6,000 5,000
52
Exercise
Find the NPV of the following projects and choose the best
project
Projects Initial Cash Flows
Investment
Year 1 Year 2
(Outlay)
A 10,000 10,000 -
B 10,000 10,000 1,100
C 10,000 3762 7762
D 10,000 5762 5762
53
Find the NPV of an environmental project from the
following table and suggest whether the project
should be accepted
1 200,000 50,000
2 200,000 50,000
3 300,000 100,000
4 300,000 100,000
5 350,000 100,000
Initial Investment: Birr 1,000,000
Discount Rate: 10%
54
Present Value of an Annuity
In annuity, we have the same amount of cash
inflows every single year
Assume that we have Birr 1,000 annually for
three years.
What is the present value of the benefits at
10% discount rate?
The answer is:
1,000(1/1.10)1 + 1,000(1/1.1)2 + 1,000(1/1.1)3
= 1,000*0.9091 + 1,000 * 0.8264 + 1,000
* 0.7513
= Birr 2,486.8
55
Exercise
Assume that the initial investment of a project
is Birr 450,000. In the first and second years,
the net benefits are 50,000 and 75,000
respectively. In the third, fourth and fifth years,
the net benefits stand at 100,000; 125,000
and 150,000. respectively. The discount rate
is 10%.
Based on this information, find the NPV and
show whether the project should be accepted
or rejected.
Will your decision change if the discount
factor is increased to 15%?
56
NPV
To include the impact of inflation where we have is the predicted
rate of inflation p during period t
t
n
Ct
NPV A0 t
i 1 (1 r pt )
57
NPV (exercise)
Early in the life of a project, net cash flow is likely to be
negative
The major outflow at this stage is the initial investment in
the project
The project is acceptable if the sum of the NPVs of all
estimated cash flows over the life of the project is positive.
Example, the investment is 100,000 with a net cash inflow
of 25,000 per year for a period of eight years. The discount
rate is 15%, an inflation rate is 3% per year. Calculate NPV.
Use the above formula.
The answer is = 1939.
The NPV of the inflows is greater than the NPV of the
outflow-i.e., the NPV is positive-the project is deemed
acceptable.
58
f) IRR
Internal Rate of Return (IRR);- emerges from the cost-
benefit data of the project
It is the discount rate that reduces the NPV of a project to zero
NPV
NPV
IRR
Discount Rate
59
IRR
NPV
IRR Project-A
IRR Project-B
Discount rate
60
IRR
Interpolation
NPV
61
IRR
Internal rate of return (IRR)
The internal rate of return is defined as the rate of discount,
which brings about equality between the present value of
future net benefits & initial investment. It is the value of r in
the following equation.
n
Ct
I 1 r
t 1
t
I – investment cost
Ct – Net benefit for year t
r - IRR
n - Life of the project
Illustration: For project A in the below table can be
IRR is PV(Benefits)
formulated = PV(Costs). Use algebra or a spreadsheet
as follows:
62
IRR
Calculation of IRR
Year Cash flow
0 -100000
1 30000
2 30000
3 40000
4 45000
The IRR is the value of r which satisfies the following
equation:
1000,000 30,000 30,000 40,000 45,000
0 0
1
2
3
(1 r ) (1 r ) (1 r ) (1 r ) (1 r ) 4
30,000 30,000 40,000 45,000
100,000
(1 r ) 1 (1 r ) 2 (1 r ) 3 (1 r ) 4
The calculation of r consists of a process of trial & error by assuming various
values of r say eg. 12, 14, 15, 16 and so on. The IRR % may fall anywhere
between these % values.
63
IRR
Year 0 1 2 3 4
Cash flow (100,000) 30,000 30,000 40,000 45,000
Since the value is slightly higher than our target value, which is 100,000, we
increase the value to 16%.
64
IRR
Since this value is now less than 100,000, we conclude that
the value of r lies between 15 and 16%. For most of the
purposes, this indication suffices.
If a more refined estimate of r is needed, we use the
following procedure:
1. Determine the NPV of the two closest rates of return
(NPV/15%) = 802
(NPV/16%) = 1,359
2. Find the sum of the absolute values of the NPVs obtained
in Step 1
802+1,359 = 2,161
3. Calculate the ratio of the NPV of the smaller discount rate,
identified in Step 1, to the sum obtained in Step 2
802/2,161 = 0.37
4. Add the number obtained in Step 3 to the smallest discount
rate
15+0.37 = 15.37
65
Exercise
Find the NPV and IRR of an environmental project from the following table
1 200,000 50,000
2 200,000 50,000
3 300,000 100,000
4 300,000 100,000
5 350,000 100,000
Initial Investment: Birr 700,000
66
Modified IRR (MIRR)
Example: A project’s cash flows are -400,
325 and 200. Appropriate r is 12%
T
FV (inf lows ) Ct (1 r )T t if Ct 0
t 0
T
Ct
PV (outflows ) t
if Ct 0
t 0 (1 r )
400
PV (outflows ) 0
400
(1.12)
67
Modified IRR (MIRR)
1/ T
FV FV
PV MIRR 1
(1 MIRR )T PV
1/ 2
564
MIRR 1 0.1874
400
68
Criterion of IRR
70
f. Benefit-Cost Ratio (BCR) Computation
BCR =
Or
71
BCR
Benefit t
t T
t 1 1 r
t
BCR t T
Cost t
t 1 1 r
t
72
Find the BCR and decide whether to accept the
project
1 100 100
2 100 50
DF: 10%
73
Find the BCR
1 100 100 0
2 100 50 50
74
BCR
75
Quiz
The details of a project which costs Birr. 25,000 as initial
investment are given below:
Year Cash flow
0 (25,000)
1 5,000
2 7,000
3 13,000
4 16,000
Calculate:
a)Net present Value(NPV) at 10%, 15%, and17%:
b) Internal Rate of Return(IRR): Try at 19%
c) Payback Period:
Use graphs to display your answers
76
DF 10% 15% 17%
Payback Period(PBP) PBP < target period PBP > target period
Accounting Rate
of Return(ARR) ARR > target rate ARR < target rate
Internal Rate of
Return(IRR) IRR > cost of capital IRR < cost of capital
78
Find IRR
C0 C1 C2
-160,000 1,000,000 -1,000,000
-160,000+1,000/(1+r)1 – 1,000,000/(1+r)2
79
Environmental Analysis
A project may causes environmental
impacts in many ways
Identification and analysis of adverse
effects on the environment
Identification of positive impacts
Required Mitigation measures
Designing environmental
management plan
Provision of fund for environment
management plan 80
Environmental Analysis
Main acts/guidelines in Nepal are
Environment Protection Act 1996,
The Environment Protection
Regulation 1997,
National Environmental Impact
Assessment Guidelines, 1993.
The analysis should meet the
requirements mentioned by these acts
and regulations
81
Social Analysis
A project may cause social impacts in
many ways
Will the project have any adverse
effects on the society?
What are the positive and negative
impacts?
Viable measures to address negative
impacts
Estimating cost for addressing social
impacts 82
Feasibility Analysis Matrix
Feasibility Analysis Matrix – a
tool used to rank candidate
systems.
Weighting Candidate 1 Candidate 2 Candidate 3
Description
Technical Feasibility
Managerial Feasibility
Social Feasibility
Cultural Feasibility
Economic Feasibility
Environmental
Feasibility
Ranking
83
Initiating the Feasibility Study
Appointment of an experienced
manager and Selection of study
team members
Scope of the study
External Advisers to support study
team
Plan and Schedule the Study
Starting study as per plan and
schedule
Controlling study to complete as per 84
Completing the Feasibility study
86