0% found this document useful (0 votes)
12 views31 pages

Lecture 4

The document provides an overview of the Critical Path Method (CPM) used in project planning and scheduling, detailing key parameters such as Early Start, Early Finish, Late Start, and Late Finish. It explains the processes of forward and backward pass calculations, as well as the determination of total float and free float for project activities. Additionally, it includes examples and exercises to illustrate the application of CPM in project management.

Uploaded by

Sayantan Khamrui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views31 pages

Lecture 4

The document provides an overview of the Critical Path Method (CPM) used in project planning and scheduling, detailing key parameters such as Early Start, Early Finish, Late Start, and Late Finish. It explains the processes of forward and backward pass calculations, as well as the determination of total float and free float for project activities. Additionally, it includes examples and exercises to illustrate the application of CPM in project management.

Uploaded by

Sayantan Khamrui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 31

CM776- Construction

Project Planning &


Scheduling
MBA CPM/CEQS 2020-2021
Riddha Basu
Lecture 4
Critical Path Method on
PDM
Critical Path Method: The Key
Parameters
Early Start
• The earliest time by when an activity can be started in a project
• If an activity has no predecessor, then its early start = project start date
• If there are predecessors, then its early start is calculated based on the early start/ early finish date of the
predecessors.
Early Finish
• The earliest time by when an activity can be finished in a project
• Early finish (EF)= Early start (ES) + Duration of the activity
Late Start
• The latest time by when an activity has to start, if the activity start is delayed beyond its late start date then the
whole project will be delayed
• Late start (LS)= Late Finish (LF)- Duration of the activity
Late Finish
• The latest time by when an activity has to finish, if the activity finish is delayed beyond its late finish date then the
whole project will be delayed
• If an activity has no successor then its late finish= the project completion date
• If there are successors, then the late finish date is calculated based on late start/ late finish date of its successors
Forward Pass: Formula for ES
and EF
In critical path method, forward pass is the process of calculating ES and EF of each activity in the project

i j

Relationship with Formula for Early Start of j Formula for Early Finish j
predecessor (i)
Finish to start Early Finish of Predecessor +/- lead or lag Early Start of the activity + duration of the
lead/ lag activity
Start to start Early Start of Predecessor +/- lead or lag Early Start of the activity + duration of the
lead/ lag activity
Finish to finish Early Finish of the activity- duration of the Early Finish of Predecessor +/- lead or lag
activity lead/ lag
Start to finish Early Finish of the activity- duration of the Early Start of Predecessor +/- lead or lag
activity lead/ lag
Forward Pass: Formula for ES
and EF
How to calculate ES or EF if there are multiple predecessors for an activity?
• Step 1: Calculate ES/EF dates for the relationships given with each predecessor
individually.
• Step 2: Take the maximum values as final ES and EF of the activity.

This is because, the ES/EF of an activity should be calculated in such a manner that all of
its predecessors must start/finish before the start/ finish of the concerned activity
depending upon its relationships with the predecessors.
Backward Pass: Formula for ES
and EF
In critical path method, backward pass is the process of calculating LS and LF of each activity in the project

i j
Relationship with Formula for Late Start of i Formula for Late Finish of i
Successor j
Finish to start Late Finish of the activity – duration of the Late Start of Successor +/- lead or lag
activity lead/ lag
Start to start Late Start of Successor +/- lead or lag Late Start of the activity + duration of the
lead/ lag activity
Finish to finish Late Finish of the activity – duration of the Late Finish of Successor +/- lead or lag
activity lead/ lag
Start to finish Late Finish of Successor +/- lead or lag Late Start of the activity + duration of the
lead/ lag activity
Backward Pass: Formula for LS
and LF
How to calculate LS or LF if there are multiple successors for an activity?
• Step 1: Calculate LS/LF dates for the relationships given with each successor
individually.
• Step 2: Take the minimum values as final LS and LF of the activity.

This is because, the LS/LF of an activity should be calculated in such a manner that none
of its successors are delayed beyond their respective LS/LF dates.
Critical Path Method: The Key
Parameters
Total Project Duration:
EF of last activity in the project- ES of first activity in the project
Critical path:
• Longest path in a project which provides the minimum time required to
complete a project
• Sometimes a project may have more than one critical paths.
Critical activity:
• Activities on critical path(s) are called critical activities
Critical Path Method: The Key
Parameters
Total Float Total float of Critical
Total Float: Activities
• Definition: Total float of an activity is Time available to complete the >0
the time by which the activity can be project > Time required to
complete the project
delayed without delaying total project Time available to complete the 0
duration. project = Time required to
• Total float of an activity j is calculated complete the project
Time available to complete the <0 (Negative float)
as: project < Time required to
• TFj= LSj- ESj (Also called start float) complete the project
• Or TFj= LFj- EFj (Also called finish float)
Critical Path Method: The Key
Parameters
Free Float:
It is the time by which an activity can be delayed without delaying the total project
duration.
i j
Relationship with j Formula for calculating FF of i
FS ESj- lagij- EFi
SS ESj- lagij- ESi
FF EFj- lagij- EFi
SF EFj- lagij- ESi

If there are more than one successor for an activity; then calculate FF for each
successor individually and take the minimum as final FF of the activity
Finish to Start
Relationships
ES/ EF & LS/LF
Finish to Start
Relationships
Total Float & Free Float
Start to Start Relationships
ES/ EF & LS/LF
Start to Start Relationships
Total Float & Free Float
Finish to Finish
Relationships
ES/ EF & LS/LF
Finish to Finish
Relationships
Total Float & Free Float
Start to Finish
Relationships
ES/ EF & LS/LF
Start to Finish
Relationships
Total Float & Free Float
Example 1
Calculate ES/EF/LS/LF/TFL and FFL of each activity and determine the critical path and
total project duration
Solution:
4 /0 4 /0 4 /4 12/16/13 18/22/19
0 /0 0 /0
0 1 3 8 8 13 13 14 16 22
0 1 7 12 12 17 17 18 16 22
4/0/3 5 /1/4 0 /0 0 /0 Legend:
4 8 12 18 TFL/FFL
4 8 12 18 ES EF
ACTIVITY
3/3 LS DUR LF
2 11
5 14
Critical Path: A-C-F-H
Project Duration: 22 days
Example 2
• Draw a precedence diagram based upon the information given below,
and do CPM calculations to complete the table
A/c Duration IPA ES EF LS LF TF FF
A 2
B 5 A SS+5
C 7 A
D 10 A SS+3
E 4 B FF+2
F 6 C,D
G 1 E,F
Solution:
Legend:
TFL/FFL
0/0 4/4 0 /0 ES EF
0 2 9 13 19 ACTIVITY
A 2 C F
0 2 7 6 LS DUR LF
2 6 13 13 19
0 /0 Critical Path: A-D-F-G
Project Duration: 20 days
3 D 13
0 /0
3 10 13 19 20
7 /0 G
5 10 19 1 20
B
12 5 17
7 /7 2
8 E 12
15 4 19
Critical Path Method on
ADM
Common CPM Computations
Activity Computations
• Early Dates (ESij and EFij)
• Late Dates (LSij and LFij)
• Floats
– Total Float (TFLij)
– Free Float (FFLij)
Event Computations:
• Early Event Time (EETi)
• Late Event Time (LETi)
Project Computations:
• Project Duration
• Critical Path(s)
Forward Pass
Backward Pass
Float Calculations
Total Float
Independent Float

Free Float Interfering Float


Example 1
Solution
TFL/FFL
EETi ESij Activity i-j EFij EETj
i j
LETi LSij D ij LFij LETj

Project Duration: 19 days


Calculate ES, EF, LS, LF, TFL Critical Path: A-C-E-F
& FFL of the activities.
Determine project
duration & critical path
Class Assignment
Calculate ES, EF, LS, LF, TFL & FFL of the activities. Determine project duration & critical path
I
30 E 70 90
6 3
F O
B 5 R M 5
7
4 5

A C J Q
G 110 120
10 20 40 60 80
4 8 3 5
3

D H N
5 K 8 P
4 7 4

L
50 100

12
Project Duration: 40 days TFL/FFL
Critical Path: A-D-H-G-J-N-P-Q EETi ESij Activity i-j EFij EETj
i j
LETi LSij D ij LFij LETj

11 8 3 1
10 10 16 24 24I
30 E 70
27 28
9030
10
15 21
10 6 27 27 27 3 30
28
15 24 28
5 0 30
15 F5 5 27 30 O2 2
2 0
B 5 3 0 R M 5
7
4 5 33 0 0
0 0 5 5 0 0 15 20 0 0 35
3 20 23 23 25 Q 40
A 8 C J 35 35 40
3 3 7 12 12 G 20 20 23 23 110 120
10 0 0 20 3 40 6020 80 35 35 40 40
0 3 8 12 12 12 20 20 23 23 23 5
0 3 3 4 8 20 3 14 35
3 12 12 23 35
3 23 0 0 0 0
0 0 H 5 N
00 D 9 9
K 8 P
4 7 4
7 7 31
7 7 12 12 31 31 31
7 7 16 7 L 19 10031
50
7 19 31 31
12
Thank You

You might also like