The Ennore SEZ Thermal Power Project, with a capacity of 2 X 660MW, is located in Kattupalli, North Chennai, and has an estimated cost of Rs. 18085.49 crores, with 70.50% physical progress as of now. The project is expected to be completed by March 2026, following a 4th extension approval, and has faced challenges due to legal issues regarding construction in the Kosathaliyar River area. M/s BHEL is currently seeking revised cost approval and additional time for reengineering activities related to the coal handling system and sea water intake piping.

Uploaded by

baluthemagician
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views8 pages

Minister PPT English 25.11.2024 Ensez SE M Corrected

The Ennore SEZ Thermal Power Project, with a capacity of 2 X 660MW, is located in Kattupalli, North Chennai, and has an estimated cost of Rs. 18085.49 crores, with 70.50% physical progress as of now. The project is expected to be completed by March 2026, following a 4th extension approval, and has faced challenges due to legal issues regarding construction in the Kosathaliyar River area. M/s BHEL is currently seeking revised cost approval and additional time for reengineering activities related to the coal handling system and sea water intake piping.

Uploaded by

baluthemagician
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Tamil Nadu Power Generation Corporation Limited

Ennore SEZ STPP

Welcomes

Honourable Minister for Electricity, Prohibition and


Excise

25.11.2024
Ennore SEZ Thermal Power Project (2 X 660MW)
Location Kattupalli,North Chennai
Announcement Year 2013
Department Energy Department
Estimated cost (Rs.in Crores) Rs.18085.49 crs (Project cost revised from
Rs.9800 crs to Rs.18085.49 crs)
Value of award (in Rs. crore) Rs.8587.68 crs
Whether Work Commenced Yes
If yes Date of work 27.09.2014
Commencement
If no, Present stage -
Physical Progress (in%) 70.50%
Expenditure ( Rs.in Crores) Rs.10363.10
Financial progress (in%) 67.67%
Estimated date of completion Unit-I & II March 2026 as per the 4th extension
approval
Remarks if any • Approval for additional claim by M/s BHEL is under
process for taking pipe conveyor and Sea Water In
Take piping along the MoEF approved route in CRZ
area and for taking deviation in non CRZ area on
27.09.2024.
• 4th Extension for the project had been approved by
TANGEDCO as per request of M/s BHEL by
rescheduling the project completion by March-2026
for Both Units I & II .
• Additional loan of Rs.5486.56 Crores sanctioned by
PFC and action is being taken for getting BOARD
Status of present progress of Project Works - Unit 1
&2
SYSTEM : Completed percentage
Boiler I & II : 81%
Power House I & II : 42%
ESP I & II : 76%
External coal handing system : 42% (Except CRZ zone)

Ash handling system : 34% (civil alone)


Chimney : 86%
NDCT : 65%
RODM & PT : 57%
CW Pump House : 42% (civil alone)
GIS : 96%
Turbo Generator Erection : 3%

3
Probable Completion
SYSTEM : Completion Month
TG I & II (Turbine Box up) : June -25
Startup Power : June - 25
Cooling water system : December - 25
Coal handling system : July -25 (Expect CRZ zone)

Ash handling system : December - 25


Power house & CCR : May - 25
NDCT : March -25
RODM & PT : May -25
Transformer yard : June - 25
GIS : December - 24
June – 25
Sea water intake system
: (Expect piping in CRZ
(civil)
zone)
M/s BHEL sub vendor M/s L&T had commenced the
construction of Coal Handling Piers in the CRZ zone water
body in Jan 2021. But in July 2021, local villagers and an NGO
filed a case in the Hon'ble High Court of Madras objecting the
construction of civil works in the water bodies in the
Kosathaliyar River challenging that the construction activities
are being carried out in the deviated route of MOEF approved
route and sand filling causing hindrance to the fishermen
activities. As a result, civil work in the external coal handling
system area from TH-1 to PR 30 was halted on 26.07.2021.
The Joint Action Committee (JAC) has directed that before
resuming any further work in the external coal handling
system area along the Kosathaliyar River, revised approval for
the coal corridor along the existing route must be obtained
from the Ministry of Environment, Forest, and Climate Change
(MoEF).
An Environmental Impact Assessment (EIA) study was carried
out by Cholamandalam MS Risk Services, and the report was
submitted in March 2023. Based on the findings of the EIA,
MoEF has directed to execute the work in the original MoEF
approved route in the Kosathaliyar River area.
TANGEDCO had given clearance to M/s BHEL to
proceed with the erection activities in the original MoEF
approved route on 27.09.24
M/s. BHEL has demanded to issue change order and
revised cost approval to proceed with the re-engineering
activity and submitted revised cost. The matter is currently
under discussion, and further meeting with M/s. BHEL is
scheduled on 26.11.2024. However, M/s BHEL has
requesting 23 months period for completion of
reengineering, supply and erection of the coal corridor
works (for Coal handling system and Sea Water Intake
Piping) in the new route of approx. 2126 M length.
THANK
YOU