A Presentation On Turbine Rolling Atrs Final
A Presentation On Turbine Rolling Atrs Final
Supdt, Operation
TG ROLLING PREPARATION
1. VACUUM PULLING & SEAL STEAM CHARGING 2. MS LINE WARMING & CHARGING 3. HP BYPASS CHARGING 4. LPBYPASS CHARGING
VACUUM PULLING
ENSURE DRAIN BEFORE CRH NRV TO SDFT CRHV 101 , MS/HRH STRAINER DRAINS (to remove impurities) TO SDFT(MSV109,110 & HRHV 105,106) ARE OPEN. STATRT VACUUM P/P 1 RECIRCULATION P/P & OBSERVE THAT SEAL WATER FLOW (remember the water ring around impeller!) IS ADEQUATE,START VACUUM P/P 1. AIR IV V/V OPENS ON INTERLOCK & VAC STARTS BUILDINGUP. START 2ND VAC P/P FOR HOGGING OPERATION FOLLOWING THE SAME
Stage 2 or 3
HP BYPASS CHARGING
Drain v/vs BPV 101 & BPV 102 to UFT of BP1 & BP2 warm up line are open & also ensure opening of bypass spray block v/v(BD v/v) man isolating v/v. Open BP1 & BP2 line warm up v/vs BPV3,BPV-4 & close their drains to UFT. Open BP1 & BP2 5% manually & check HPBP D/S temp is rising & also temp is maintained by spray control v/vs BPE1 & BPE2. Raise boiler firing by increasing HFO pr. & close SH start up vents.
LP BYPASS CHARGING
Open LPT exh hood spray isolation v/v & charge LPBP warm up line drains. LPBP spray from CEP is lined up. LPBP both temp dependent solenoid v/vs are reset. Keep LPBP controller in manual mode & give command to controller until water injection v/v 1 & 3 open, then both bypass stop v/vs & control v/vs open in sequence. Regulate CVs opening & maintain HRH pr approx 4-6 ksc. IF LPBP D/S flow increases > 45%, check & ensure opening of second stage water injection v/vs. LPBP operation with ACI: it automatically opens LPBP CVs to 25% & holds it until HRH pr. reaches 12 Ksc, then ACI switches off.
TYPES OF TG ROLLING
1. Cold Start up If HPC metal Tempr<1500C. 2. Warm start up If HPC metal tempr betwn 150 to 3500C. 3.Hot start up If HPC metal temp > 3500C.
START UP CONSIDERATIONS
During the startup the Turbine is subjected to Non-Steady state operation. This covers the operating condn where Speed, steam Pressure and temperature change with time. Under these condn turbine components which are exposed to temperature changes subjected to thermal stress and expansion. For turbine life point of view, it is very much necessary to limit the extent of these temperature changes. To take care of the above factor the operator has to follow the recommendations from Turbine Stress Evaluator and start the Rolling procedure by
SEQUENCE STEP 1 SGC Turbine startup sequence on COMMAND SLC DRAINS: ON SEQUENCE STEP 2
1. 2. 3. SLC DRAINS: ON All HP & IP ESVs :CLOSED OR STARTING DEVICE > 42% AND ESVs: OPEN ALL HPCVs & ALL IPCVs: CLOSED AND CRH NRV: CLOSED OR STARTING DEVICE >56% AND TURBINE POSITION CONTROLLER SET POINT > 0%
4. ALL EXTRAXTION NRVs (A2, A3, A4.1, A4.2, A5) POSITION < 5 % OR GENERATOR LOAD > 10%
COMMANDMS STRAINER DRAIN1: MS STRAINER DRAIN2: HRH STRAINER DRAIN1 : HRH STRAINER DRAIN2 : MONITORING TIME: 2 Secs
SEQUENCE STEP - 3
1. CONDENSER PRESSURE < -0.5 Ksc 2. TRIP FLUID PRESSURE > 5 Ksc 3. CEP DISCHARGE HEDER PRESSURE > 19 Ksc 4. SLC DRAINS: NO FAULT 5. TURBINE SPEED > 15 RPM 6. HPC MID TOP/BOTTOM DT > -550K AND < 550 K 7. IPC FRONT TOP/BOTTOM DT > -300K AND < 300 K 8. IPC REAR TOP/BOTTOM DT > -300K AND < 300 K 9. MS STAINER 1,2 & HRH STRAINER 1,2 DRAINS: NOT CLOSED OR TURBINE SPEED > 300 RPM
SEQUENCE STEP - 4
1. DRAINS BEFORE HPCV 1,2 (MAL 11, MAL 12): CLOSED OR ESVs: OPEN
COMMAND
:NIL
SEQUENCE STEP 5
1. FLAME IN BOILER: ON 2. HP CF TEMP > 500C 3. STEAM TEMP BEFORE HPBP (BP1,BP2) SUPERHEAT > 300 K AND STEAM TEMP BEFORE LPBP 1,2 SUPERHEAT > 300 K OR
5. DT (WET STEAM BEFORE HPBP 1,2 HPCV 1,2 MIDWALL TEMP ) < X2 6. LUB OIL TEMP AFTER OIL COOLER > 350 C
COMMAND : raise
Starting device
NOTE: CRITERION X1 & X2 SHOULD BE FULFILLED BEFORE OPENING THE HP ESVs CRITERIA X3 (PRESSURE CRITERIA ) IS ALSO REQUIRED WHILE OPENING THE ESVs. MAX MS PRESS BEFORE ESVs, pMS = f ( TMCV50% ) IF TMCV50% > TSAT , PRESSURE CRITERIA IS NOT OBSERVED TMCV50% = MIDWALL TEMP OF MCV1,2 TSAT = SAT STEAM TEMP BELONGING TO MS
X1 CURVE
600
10 0
20 0
300
400 500
600
1.
SEQUENCE STEP 6
SEQUENCE STEP 7
1. BOTH HP ESVs: OPEN NO COMMAND MONITORING TIME: 60 Secs
SEQUENCE STEP 8
1. MS FLOW > 15 %
OR TURBINE SPEED > 2850 rpm 2. STEAM TEMP BEFORE HPBP 1,2 SUPERHEAT >300 K
SEQUENCE STEP 10
1. TRACKING DEVICE: ON 2. BOTH INTCPT ESVs: OPEN COMMAND : Speeder gear raise ( Condition : Turbine speed <2800 rpm AND Speeder gear <100% )
SEQUENCE STEP 11
1. 2. 3. 4. 5. 6. DRAINS: NO FAULT GLAND STEAM PRESS CONTROL: AUTO SPEEDER GEAR > 100% LUB OIL TEMP CONTROL: AUTO GENERATOR CONDITIONS: FULFILLED ANY ONE VAPOUR EXTRACTOR: ON
8. SEAL OIL PRE-CHAMBER EE LEVEL < MAX 9. LIQUID IN GENERATOR TE < MAX 10. LIQUID IN GENERATOR CENTRE< MAX 11. LIQUID IN GENERATOR LEAD BOTTOM 1 &2 < MAX 12. ANY ONE AIR SIDE AC SEAL OIL PUMP: ON 13. H2 SEAL OIL PUMP: ON 14. AIR SIDE DC SEAL OIL PUMP VOLTAGE: PRESENT 15. PW TEMP CONTROL: AUTO 16. PW CONDUCTIVITY <1 mho 17. ANY ONE GENERATOR BEARING
SEQUENCE STEP 12
1. GENERATOR CONDITIONS FULFILLED 2. STEAM PRESS BEFORE HP ESVs SUPERHEAT > X3 3. DT (STEAM TEMP BEFORE HP ESV 1,2 -HP 5. CASING) > STEAM TEMP BEFORE LPBP MEAN DT (HRH X4 TEMP IP CASING T > 15 rpm 4. TURBINE SPEEDIPT50%)> X5 AND RH STEAM TEMP BEFORE LPBP > 4800C OR TURBINE SPEED > 2850 RPM 6. DRAIN BEFORE HPCV 1 & 2: NOT CLOSED OR TURBINE SPEED > 2850 RPM 7. POWER SET POINT > 10% 8. CONDENSER PRESSURE < -0.8 Ksc COMMANDTURBINE SPEED SET POINT : RAISE
SEQUENCE STEP 13
1. TURBINE SPEED SET POINT > 360 RPM OR GENERTOR BREAKER: ON COMMAND :NIL
SEQUENCE STEP 14
TURBINE SPEED > 300 RPM
COMMAND : MS strainer 1 drain close MS strainer 2 drain close HRH strainer 1 drain close HRH strainer 2 drain close
SEQUENCE STEP 15
1. TSE TEST PROGRAMME: BLOCKED AND SGC TURBINE STEP 14 ON DELAYED: 180 Secs OR WALL TEMP HP CASING > 2500 C TSE MARGIN > 300 K OR TURBINE SPEED > 2850 RPM DT (MS TEMP BEFORE HPBP 1 & 2 MIDWALL TEMP HP CASING) < X6 MS STRAINER DRAINS 1 & 2: CLOSE HRH STRAINER DRAINS 1 & 2: CLOSE
2.
3. 4. 5.
dn/dt PROTECTION
BRINGS DOWN TURBINE SPEED TO SOAKING SPEED (360 RPM)
1.IF ATRS PROGRAMME IS MADE OFF BEFORE NR > 2850 RPM 2.IF TSE MARGIN RESTRICTS TURBINE ACCELERATION < 108 RPM/MIN THROUGH EHC.
SEQUENCE STEP - 16
DRAINS BEFORE HPCV 1 & 2: MANUAL
COMMAND :Turbine Speed set point raise Drain before HPCV 1 close Drain before HPCV 2 close
SEQUENCE STEP 17
1. TURBINE SPEED SET POINT > 3036 RPM OR GENERATOR BREAKER : ON COMMAND NIL
SEQUENCE STEP 18
1. TURBINE SPEED SET POINT < 2950 RPM OR GENERATOR BREAKER : ON
COMMAND:AVR in auto
SEQUENCE STEP 19
1. AVR: AUTO OR GENERATOR BREAKER: ON 2. FIELD BREAKER: ON COMMAND DRAIN BEFORE HPCV 1 & 2 : CLOSE
SEQUENCE STEP 20
1. BOTH AOPs OFF TD10s 2. DT (RH STEAM TEMP BEFORE LPBP MEAN TEMP IP SHAFT) < X7 3. H2 CASING PRESS > 3 Ksc 4. CG TEMP AFTER H2 COOLER A & B < 450 C 5. CG TEMP AFTER H2 COOLER C & D < 450 C 6. DRAIN BEFORE HPCV 1 & 2: CLOSE
SEQUENCE STEP 21
1. 2. 3. SGC TURBINE STEP 20 COMMAND DELAYED: 15 Secs AVR on AUTO GENERATOR VOLTAGE > 95 % OR GENERATOR BREAKER ON AND GENERATOR LOAD > 10 %
SEQUENCE STEP - 22
1. GENERATOR BREAKER: ON COMMAND Speed set point raise
SEQUENCE STEP - 23
1. WAITING TIME: 2 Secs OR GENERATOR LOAD >10%
SEQUENCE STEP - 24
1. GENERATOR BREAKER: ON 2. TURBINE SPEED > 2850 RPM
END OF PROGRAMME
SYNCHRONIZATION
Generator breaker will close once permissive are matched. Immediately raise speed reference to pick up the load on the machine to avoid reverse power trip or low forward power trip. Increase the load as per TSE margin and close HP/LP bypass valves. Close all the drains which were opened during rolling. Turn off the synchroscope switch to de energize synchroscope. Ensure that load reference set point is higher than the actual load value. Observed that changeover from speed controller to load controller takes place once output of load
SYNCHRONIZATION
The load controller active light glows on Turbine desk. Ensure tracking device is on. Increase the load limiter value to about 150MW. Check the Generator winding, exciter air, cold gas temp., generator stator core temp. & all TSI parameter are normal. Raise the HP bypass pressure set point to 10KSC more than throttle steam pr and temp. Set point to about 340C to avoid HP by pass opening on auto. Ensure that LP bypass stop valves and spray valves are closed.
LP HEATER CHARGING
Check that LPH-1 inlet/outlet valves are in open condition and bypass valve in closed condition. Ensure all LP heater shell vents to condenser are in open condition. Charge both LP heaters 2 and 3 from condensate side by opening I/L valves and O/L valve and closing their bypass valve respectively. Charge LP heater-2 by opening its extraction valve. Note there is increase in level. Put its cascading drip to LP heater-1 and emergency drip to auto when the normal level is reached. Before putting to auto ensures that level set point of emergency drip is greater than normal drip set point. Repeat above for LP heater-3.
Starting Mill
Line-up from local and check all the per missives. Start Coal mill A(bottom most available Mill) open HAG/CAG & dampers to achieve air flow > 80T/Hr & temp>65C Start feeder and ensure flame gets stabilized. If pressure rises, Then increase load. Control MS & HRH temp to get sufficient margin. Maintain 100C more MS & HRH temp than HPS/HPC/IPS/HPSV/HPCV.
Maintain MST & HRH temp by BT & spray. Take another mill into service. Pr 90 KSC & load 200MW. Take another Mill into service. Pr 110 ksc & load 250MW. Take another mill into service. Pr 120 Ksc & load 300MW. Remove oil support. Take another Mill and raise the load. Pr 130KSC & load 400MW Take 6th Mill in to service & raise the load.Pr 170 & load 500MW. Maintain O2 3.5%. CO less than 40.
Charge ESP when flue gas temperature at outlet of APH reaches above 100C Steam Temperature Control
To line-up &charge super heater attemperation system. To line-up & charge reheater attemperation system.
Close the breaker when in-synchronism light glows and hold it for 2sec. Note that the incomer breaker from SA/SB bus, is tripped.
At load around 150-200 MW take feed water Hi-range in service. Now varying the BFP speed will control drum level. If the speed is put to auto , FW master will give the command to BFP speed. FW master may be put in auto if normal level is achieved. It is advisable to put primary air pressure control in auto to facilitate good control over firing.
STARTING OF TDBFP Lube oil system Jacking Oil system Turbine on Barring Gear Steam charging and rolling TO LINE UP AND TAKE HP HEATER IN SERVICE RAISE THE LOAD TO RATED VALUE