Material Requirement (MRP) 
This article is protected against manual editing because it is automatically generated from Openbravo meta­data. 
Learn more about writing and translating such documents. 
Back to User Guide 
Contents 
1 Introduction 
2 Material Requirement Planning 
2.1 Configuration 
2.2 Execution 
3 Connection with other application areas 
4 Application Menu 
4.1 Transactions 
4.2 Setup 
Introduction 
In Material Requirement Planning the application is used to automatically review the demand and display suggestions concerning required supply. In the Manufacturing Plan, the 
application suggests required Work Requirements and Requisitions. In the Purchasing Plan, the application suggests required Purchase Orders. 
Material Requirement Planning 
The Master Requirement Planning consists of two plans: 
Manufacturing Plan: plan to display calculations related to products that go through Production. The suggested documents to be created in this plan are the Work Requirement 
and the Requisition. 
Purchasing Plan: plan to display calculations related to products that are procured. The suggested document to be created in this plan is the Purchase Order. 
Planning Methods are entered to define what supply components are taken into account with the calculations of these plans. 
Configuration 
Apart from the set up screens in the MRP module that are configured, additional set ups are required. 
For the products that are planned in the Manuafacturing Plan, the following configurations are required: 
the Process plan is set up for the product. 
the production checkbox and the Process Plan name are selected in the Product screen. 
the Manufacturing tab in the Product screen is filled out with the information required for MRP to make the calculations for the Manufacturing plan. 
http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)#Material_Requirement_Planning 1/2
6/23/2014 Material Requirement (MRP) - OpenbravoWiki 
For the products that are planned in the Purchasing Plan, the following configurations are required: 
the purchase checkbox is selected in the Product screen. 
the price of the product is defined for the price list of the vendor that is entered in the Purchasing tab. 
the Purchasing tab in the Product screen is filled out with the information required for MRP to make the calculations for the Purchasing Plan. 
the vendor that is reflected as the Business Partner in the above mentioned Purchasing tab is filled out in the Business Partner screen: 
Vendor/Creditor tab with at least the following fields filled out: 
Purchase Pricelist 
PO Payment Method 
PO Payment Terms 
Location/Address tab 
The Manufacturing tab in the Product screen is filled out with the Planning Method and Planner information. 
Execution 
The material planner enters a Manufacturing Plan for a product for a certain time period and processes the plan. 
In the created overview the material planner reviews and analyzes the lines. Based on the information that is processed by MRP, the plan suggests Work Requirements and 
Requisitions for certain quantities and certain dates. 
If required, adjustments to the set ups, for example the planning method, are done. The lines of the plan are recalculated by clicking the Recalculate Dates/Quantities 
button. 
If required, manual changes to the created lines with regards to quantities and dates are made. 
once the plan is correct, any suggested requisitions are created by clicking the Generate Material Requisitions button and any suggested Work Requirements are created by 
clicking the Generate Work Requirements button. 
the material planner completes the created requisition(s) and processes the created Work Requirement(s). 
The material planner then enters a Purchasing Plan for a product for a certain time period and processes the plan. 
In the created overview the material planner reviews and analyzes the lines. Based on the information that is processed by MRP, the plan suggests Purchase Orders for certain 
quantities and certain dates. 
If required, adjustments to the set ups, for example the planning method, are done. The lines of the plan are deleted and the plan is reprocessed. 
If required, manual changes to the created lines with regards to quantities and dates are made. 
once the plan is correct, any suggested purchase orders are created by clicking the Create Purchase Orders button. 
the material planner completes the created purchase order. 
Connection with other application areas 
The MRP interacts with the following modules: 
Procurement Management: 
Requisitions are created from the Manufacturing Plan 
Purchase Orders are created from the Purchasing Plan 
Sales Management: 
Sales Orders are optionally taken into account in the calculations of both plans 
Warehouse Management: 
Stock levels are automatically taken into account in the calculations of both plans 
Production Management: 
the Process Plan is used for the calculation of the Manufacturing Plan 
Work Requirements are created from the Manufacturing Plan 
Application Menu 
Please find below detailed descriptions of the windows of the MRP Management application area. 
Transactions 
empty 
Manufacturing Plan 
Purchasing Plan 
Sales Forecast 
Setup 
ManualDoc:SectionMaterial Requirement (MRP) Setup(Openbravo Admin) 
Planning Method 
Planner 
Back to User Guide 
Retrieved from "http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)" 
This page has been accessed 6,665 times. This page was last modified on 11 January 2012, at 12:51. Content is available under Creative Commons Attribution­ShareAlike 
2.5 Spain 
License. 
Categories: User Guide | Generated Doc 
http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)#Material_Requirement_Planning 2/2

More Related Content

PPT
IIG's Process Manufacturing Solution for Sage 100
PDF
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
PPT
Material Requisite Planning
PPTX
Sap pp online training
PPTX
Live SAP PP Training
PPTX
DOC
Product costing part4-costing run
DOC
Product costing part3-quantity structure
IIG's Process Manufacturing Solution for Sage 100
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
Material Requisite Planning
Sap pp online training
Live SAP PP Training
Product costing part4-costing run
Product costing part3-quantity structure

What's hot (18)

PDF
Bn1010 demo ppt sap pp
DOC
Product costing part1-cost center planning
DOC
Sap mm bom
PPTX
sap b one production module
PPT
Stock requirements list md04
PPTX
SAP Production Planning and Execution presentation
PPT
Production
PPTX
Report w13
DOCX
Bom in sap
PDF
SAP SOP process flow for production process
PPT
Consumable Materials
DOC
Uop bus 599 assignment 3 part 1
PDF
Sample sap mm pp course material
PPTX
Computer-aided Manufacturing Resource Planning
PPTX
Material Requirement Planning
DOC
Product costing part5-actual costs
DOC
Uop bus 599 assignment 3 part 1
Bn1010 demo ppt sap pp
Product costing part1-cost center planning
Sap mm bom
sap b one production module
Stock requirements list md04
SAP Production Planning and Execution presentation
Production
Report w13
Bom in sap
SAP SOP process flow for production process
Consumable Materials
Uop bus 599 assignment 3 part 1
Sample sap mm pp course material
Computer-aided Manufacturing Resource Planning
Material Requirement Planning
Product costing part5-actual costs
Uop bus 599 assignment 3 part 1
Ad

Similar to Material requirement Planning (mrp) openbravo (20)

PPTX
Operations MRP
PPTX
Material Requirement Planning (mrp)
PPTX
Production and operations management (POM)
PPTX
MRP- Lecture PPT.pptx
PPTX
Production planning & mrp
PPTX
PPT
PDF
Sap MRP materials requirements planning
PDF
PPTX
Material requirement planning (mrp)
DOCX
Sap mrp-configuration-pp
PPT
Operations Management Material Requirements Planning (MRP)
PPT
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
PDF
Material requirement planning in SAP MM.pdf
PPT
Ch17 Mrp
PPSX
Material requirement planning and its importance om
PDF
Production planning english
PDF
Production planning english
PPTX
Material Requirements Planning (MRP).pptx
PPT
Operations MRP
Material Requirement Planning (mrp)
Production and operations management (POM)
MRP- Lecture PPT.pptx
Production planning & mrp
Sap MRP materials requirements planning
Material requirement planning (mrp)
Sap mrp-configuration-pp
Operations Management Material Requirements Planning (MRP)
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
Material requirement planning in SAP MM.pdf
Ch17 Mrp
Material requirement planning and its importance om
Production planning english
Production planning english
Material Requirements Planning (MRP).pptx
Ad

More from MD Abul Khayer (20)

PDF
Openbravo Retail Web POS User Guide 2020
PDF
Retail_Configuration Guide - OpenbravoWiki.pdf
PDF
ManualDoc_Common OBConcepts&Processes - OpenbravoWiki.pdf
PPTX
Arabic Type - Document Design ERP in SaaS
PDF
Reporting Server_Reporting Server Domains - OpenbravoWiki.pdf
PDF
e-Government Master Plan for Digital Bangladesh Final.pdf
PDF
Obbridge docs
PDF
Feature list of openbravo for distribution business
PDF
Openbravo
PDF
Journal entries report Openbravo for Inventory and COGS
PDF
Manual doc common ob_concepts&processes - openbravo
PDF
User guide openbravo
PDF
User interface introduction openbravo
PDF
Procurement management openbravo
PDF
Sales management openbravo
PDF
Warehouse management openbravo
PDF
Production management openbravo
PDF
Project and service management openbravo
PDF
Financial management openbravo
PDF
Openbravo live development builds
Openbravo Retail Web POS User Guide 2020
Retail_Configuration Guide - OpenbravoWiki.pdf
ManualDoc_Common OBConcepts&Processes - OpenbravoWiki.pdf
Arabic Type - Document Design ERP in SaaS
Reporting Server_Reporting Server Domains - OpenbravoWiki.pdf
e-Government Master Plan for Digital Bangladesh Final.pdf
Obbridge docs
Feature list of openbravo for distribution business
Openbravo
Journal entries report Openbravo for Inventory and COGS
Manual doc common ob_concepts&processes - openbravo
User guide openbravo
User interface introduction openbravo
Procurement management openbravo
Sales management openbravo
Warehouse management openbravo
Production management openbravo
Project and service management openbravo
Financial management openbravo
Openbravo live development builds

Material requirement Planning (mrp) openbravo

  • 1. 6/23/2014 Material Requirement (MRP) - OpenbravoWiki Log in / create account Openbravo.com Partner Portal Issues Blogs Forge Exchange University Downloads View source | Discuss this page | Page history | Printable version Material Requirement (MRP) This article is protected against manual editing because it is automatically generated from Openbravo meta­data. Learn more about writing and translating such documents. Back to User Guide Contents 1 Introduction 2 Material Requirement Planning 2.1 Configuration 2.2 Execution 3 Connection with other application areas 4 Application Menu 4.1 Transactions 4.2 Setup Introduction In Material Requirement Planning the application is used to automatically review the demand and display suggestions concerning required supply. In the Manufacturing Plan, the application suggests required Work Requirements and Requisitions. In the Purchasing Plan, the application suggests required Purchase Orders. Material Requirement Planning The Master Requirement Planning consists of two plans: Manufacturing Plan: plan to display calculations related to products that go through Production. The suggested documents to be created in this plan are the Work Requirement and the Requisition. Purchasing Plan: plan to display calculations related to products that are procured. The suggested document to be created in this plan is the Purchase Order. Planning Methods are entered to define what supply components are taken into account with the calculations of these plans. Configuration Apart from the set up screens in the MRP module that are configured, additional set ups are required. For the products that are planned in the Manuafacturing Plan, the following configurations are required: the Process plan is set up for the product. the production checkbox and the Process Plan name are selected in the Product screen. the Manufacturing tab in the Product screen is filled out with the information required for MRP to make the calculations for the Manufacturing plan. http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)#Material_Requirement_Planning 1/2
  • 2. 6/23/2014 Material Requirement (MRP) - OpenbravoWiki For the products that are planned in the Purchasing Plan, the following configurations are required: the purchase checkbox is selected in the Product screen. the price of the product is defined for the price list of the vendor that is entered in the Purchasing tab. the Purchasing tab in the Product screen is filled out with the information required for MRP to make the calculations for the Purchasing Plan. the vendor that is reflected as the Business Partner in the above mentioned Purchasing tab is filled out in the Business Partner screen: Vendor/Creditor tab with at least the following fields filled out: Purchase Pricelist PO Payment Method PO Payment Terms Location/Address tab The Manufacturing tab in the Product screen is filled out with the Planning Method and Planner information. Execution The material planner enters a Manufacturing Plan for a product for a certain time period and processes the plan. In the created overview the material planner reviews and analyzes the lines. Based on the information that is processed by MRP, the plan suggests Work Requirements and Requisitions for certain quantities and certain dates. If required, adjustments to the set ups, for example the planning method, are done. The lines of the plan are recalculated by clicking the Recalculate Dates/Quantities button. If required, manual changes to the created lines with regards to quantities and dates are made. once the plan is correct, any suggested requisitions are created by clicking the Generate Material Requisitions button and any suggested Work Requirements are created by clicking the Generate Work Requirements button. the material planner completes the created requisition(s) and processes the created Work Requirement(s). The material planner then enters a Purchasing Plan for a product for a certain time period and processes the plan. In the created overview the material planner reviews and analyzes the lines. Based on the information that is processed by MRP, the plan suggests Purchase Orders for certain quantities and certain dates. If required, adjustments to the set ups, for example the planning method, are done. The lines of the plan are deleted and the plan is reprocessed. If required, manual changes to the created lines with regards to quantities and dates are made. once the plan is correct, any suggested purchase orders are created by clicking the Create Purchase Orders button. the material planner completes the created purchase order. Connection with other application areas The MRP interacts with the following modules: Procurement Management: Requisitions are created from the Manufacturing Plan Purchase Orders are created from the Purchasing Plan Sales Management: Sales Orders are optionally taken into account in the calculations of both plans Warehouse Management: Stock levels are automatically taken into account in the calculations of both plans Production Management: the Process Plan is used for the calculation of the Manufacturing Plan Work Requirements are created from the Manufacturing Plan Application Menu Please find below detailed descriptions of the windows of the MRP Management application area. Transactions empty Manufacturing Plan Purchasing Plan Sales Forecast Setup ManualDoc:SectionMaterial Requirement (MRP) Setup(Openbravo Admin) Planning Method Planner Back to User Guide Retrieved from "http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)" This page has been accessed 6,665 times. This page was last modified on 11 January 2012, at 12:51. Content is available under Creative Commons Attribution­ShareAlike 2.5 Spain License. Categories: User Guide | Generated Doc http://wiki.openbravo.com/wiki/Material_Requirement_(MRP)#Material_Requirement_Planning 2/2