Module – 5:
• Material Requirement Planning (MRP):
• Dependent versus independent demand, an
overview of MRP – MRP inputs and outputs,
MRP processing, ERP capacity requirement
planning, benefits and limitations of MRP.
• Purchasing and Supply Chain Management
(SCM):
• Introduction, Importance of purchasing and
SCM, the procurement process, Concept of
tenders, Approaches to SCM, Vendor
development. 2
Dept. of ME, JSSATE, Bengaluru
Module Outcome:
At the end of this module, you will be able to:
CO# Course Outcome
Bloom’s
Level
5
Apply MRP, purchasing and SCM techniques into
practice.
3
3
Dept. of ME, JSSATE, Bengaluru
Forecasting
Learning Objectives:
After completing this module, you should be able to:
4
Dept. of ME, JSSATE, Bengaluru
• A technique of determining the quantity and timing
for the acquisition of dependent demand items
needed to satisfy the MPS requirements.
• A computerized inventory control and production
planning system.
• The main objective of any inventory system is to
ensure that material is available when needed.
• One objective of MRP is to maintain the lowest
possible level of inventory.
• MRP does this by determining when component
items are needed and scheduling them to be ready at
that time, no earlier and no later.
Material Requirement Planning
5
Dept. of ME, JSSATE, Bengaluru
Material Requirement Planning
Source: OM by Russel & Taylor
6
Dept. of ME, JSSATE, Bengaluru
• MRP is useful for dependent and discrete demand
items, complex products, job shop production, and
assemble-to-order environments.
• Managing component demand inventory is different
from managing finished goods inventory.
• Independent demand is demand for a finished
product, such as a computer, a bicycle, or a pizza.
• Dependent Demand: Demand for components that are
derived from the demand for the other items.
• Parent and component items: A parent is an assembly
made up of basic parts or components.
When to use MRP; Terms
7
Dept. of ME, JSSATE, Bengaluru
Source: OM by Russel & Taylor
Terms used in MRP
8
Dept. of ME, JSSATE, Bengaluru
• Lot size: The quantity of items required for an order
(purchased from vendor or produced in-house).
• Time phasing: Scheduling to produce or receive an
appropriate amount (lot) of material so that it will be
available in the time periods when needed – not before
or after.
• Time bucket: The time period used for planning
purposes in MRP, usually a week.
• Bill of materials: A listing of all the components
(subassemblies and materials) that go into an
assembled item. It includes the part numbers and
quantity required per assembly.
Terms used in MRP
9
Dept. of ME, JSSATE, Bengaluru
• Gross requirements: The total expected demand for an
item or raw material during each time period without
regard to the amount on hand.
• For end items, these quantities are shown in the master
schedule; for components, these quantities are derived
from the planned-order releases of their immediate
“parents.”
• Projected on hand: The expected amount of inventory
that will be on hand at the beginning of each time
period (scheduled receipts plus available inventory
from last period).
• Net requirements: The actual amount needed in each
time period.
Terms used in MRP
10
Dept. of ME, JSSATE, Bengaluru
• Scheduled receipt: Materials already on order from a vendor
or in-house shop. In MRP, both the quantity and the
projected time of receipt are shown.
• Planned receipt: Materials that will be ordered from a
vendor or in-house shop. Otherwise, it is similar to scheduled
receipt (no difference in some MRPs)
• Lead-time offset: The supply time, or number of time
buckets between releasing an order and receiving the
materials.
• Planned order release: The plan (quantity & date) to initiate
the purchase or manufacture of items so that they will be
received on schedule after the lead time offset.
• Time fence: Management-specified date within which no
changes in the master schedule are allowed.
Terms used in MRP
11
Dept. of ME, JSSATE, Bengaluru
Source: OM by Russel & Taylor
Inputs and Outputs of MRP
Which end items are to be
produced, when they are
needed, and in what quantities.
A listing of all of the assemblies,
subassemblies, parts, part costs, and
raw materials that are needed to
produce one unit of a finished product.
A database of information
on every item produced,
ordered, or inventoried.
Bill of Materials
12
Dept. of ME, JSSATE, Bengaluru
• A listing of all of the assemblies, subassemblies, parts,
part costs, and raw materials that are needed to
produce one unit of a finished product.
• Single level BoM and Indented BoM
• Engineering bill of materials (EBOM) and Manufacturing
bill of materials (MBOM)
• EBOM- finished product details as it was originally
designed.
• (MBOM) contains information on all the parts and
assemblies required to build a complete
and shippable product (includes packing materials).
Bill of Materials
13
Dept. of ME, JSSATE, Bengaluru
https://help.openbom.com/2018/09/08/bom-single-level-multi-level-flattened/
Bill of Materials
14
Dept. of ME, JSSATE, Bengaluru
Bill of Materials
15
Dept. of ME, JSSATE, Bengaluru
Bill of Materials
Indented or Multi-level BoM
16
Dept. of ME, JSSATE, Bengaluru
• A visual depiction of the requirements in a bill of
materials, where all components are listed by levels.
Product Structure Tree
Source: OM by Stevenson, W J
Assembly Diagram
17
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
Source: OM by Stevenson, W J
18
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
Source: OM by Stevenson, W J
19
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
20
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
21
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 1
• Use the information presented in the figure to do the
following:
• Determine the quantities of B, C, D, E, and F needed to
assemble one X.
• Determine the quantities of these components that will
be required to assemble 10 Xs, taking into account the
quantities on hand (i.e., in inventory) of various
components:
Source: OM by Stevenson, W J
22
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
Source: OM by Stevenson, W J
23
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
Thus, for one X, quantities of components required are:
B = 2; C = 1; D = 6; E = 24+2+2 = 28; F = 2
Solution: a
24
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree
Solution: b
Thus, for 10 Xs, quantities of components
required are:
B = 16; C = 0; D = 40; E = 100+16 = 116; F
= 0
Source: OM by Stevenson, W J
25
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
• An end product P is assembled by three subassemblies,
A, B and C. Subassembly A consists of two units of D,
two units of E and one unit of F. To make B, one G and
three units of H are needed. Subassembly C requires
two units of J and one unit of F. Component D requires
two units of J and one K.
• (a) Construct product structure tree for P mentioning
the levels.
• (b) Develop an indented level of bill of materials
• (c) Compute the quantities of each component to
produce 200 units of P
26
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
P Level 0
27
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
P Level 0
B C
A Level 1
28
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
P Level 0
B C
A
G H 3
J 2
D 2 F
E 2 F
Level 1
29
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
P Level 0
B C
A
G H 3
J 2
D 2 F
E 2 F
Level 1
K
J 2
30
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
Bill of Materials
Part No. or
Name
Qty. Level
A 1 1
D 2 2
J 2 3
K 1 3
E 2 2
F 1 2
B 1 1
G 1 2
H 3 2
C 1 1
F 1 2
J 2 3
Product P Level 0
31
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 2
Bill of Materials
Part No.
or Name
Qty. per
one P
Total Qty. Required
A 1 1 x 200 = 200
B 1 1 x 200 = 200
C 1 1 x 200 = 200
D 2 2 x 1 x 200 = 400
E 2 2 x 1 x 200 = 400
F 1 (1 x 200 )+ (1 x 200) = 400
G 1 1 x 1 x 200 = 200
H 3 3 x 1 x 200 = 600
J 4 (2 x 2 x 1 x 200) + (2 x 1 x 200)
= 1200
K 1 1 x 2 x 200 = 400
Total P required = 200 units
32
Dept. of ME, JSSATE, Bengaluru
MRP Processing (Logic)
• The MRP process consists of four basic steps:
• (1) exploding the bill of material
• (2) netting out inventory
• (3) lot sizing, and
• (4) time-phasing requirements.
• The process is performed again and again, moving down
the product structure until all items have been
scheduled.
Source: OM by Russel & Taylor
33
Dept. of ME, JSSATE, Bengaluru
MRP Processing (Logic) - Matrix
Source: OM by Russel & Taylor
34
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 3
• Complete the following MRP matrix for an item X:
• In what periods should orders be released, and what
should be the size of those orders?
Source: OM by Russel & Taylor
35
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 3
• Solution:
Source: OM by Russel & Taylor
36
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 4
• Complete the following MRP matrix for an item X.
Determine when orders should be released and the size
of those orders.
Source: OM by Russel & Taylor
37
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 3
• Solution:
Source: OM by Russel & Taylor
Item X Period in Weeks
Lot size: 50
LT: 2 weeks
1 2 3 4 5 6 7 8
Gross requirements 25 30 56 25 100 40 30 20
Scheduled receipts 50
Projected on hand 30 5 25 19 44 0 10 30 10
Net requirements 31 06 56 40 20 0
Planned order receipts 50 50 56 50 50
Planned order releases 50 50 56 50 50
38
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 4
• Complete the following MRP matrix for an item X. Determine
when orders should be released and the inventory at the end of
week 8.
Item X Period in Weeks
Lot size: 500
LT: 4 weeks
1 2 3 4 5 6 7 8
Gross requirements 150 150 150 150 200 200 180 320
Scheduled receipts 500 500 500
Projected on hand 300 150 0 350 200 0 300 120 300
Planned order releases 500 500
39
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 4
• Complete the following MRP matrix for an item X. Determine
when orders should be released and the inventory at the end of
week 8.
• MRP should have planned order releases of 500 units in week 2
and 4.
• There are 300 units on hand at the end of week 8.
Item X Period in Weeks
Lot size: 500
LT: 4 weeks
1 2 3 4 5 6 7 8
Gross requirements 150 150 150 150 200 200 180 320
Scheduled receipts 500 500 500
Projected on hand 300 150 0 350 200 0 300 120 300
Planned order releases 500 500
40
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
• Eighty units of end item E are needed at the beginning of week 6.
Three cases (30 units per case) of J have been ordered and one
case is scheduled to arrive in week 3, one in week 4, and one in
week 5.
• Note: J must be ordered by the case, and B must be produced in
multiples of 120 units. There are 60 units of B and 20 units of J
now on hand. Lead times are two weeks each for E and B, and
one week for J.
• Prepare a material requirements
plan for component J.
41
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
• Prepare a material requirements plan for component J.
• Suppose that in week 4 the quantity of E needed is changed
from 80 to 70. The planned-order releases through week 3
have all been executed. How many more Bs and Js will be on
hand in week 6?
42
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
Item E Period in Weeks
Lot size: 80
LT: 2 weeks
1 2 3 4 5 6
Gross requirements 80
Scheduled receipts
Projected on hand
Net requirements 80
Planned order receipts 80
Planned order releases 80
43
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
Component B (2) Period in Weeks
Lot size: 120 units
LT: 2 weeks
1 2 3 4 5 6
Gross requirements 160
Scheduled receipts
Projected on hand 60 60 60 60 20 20 20
Net requirements 100
Planned order receipts 120
Planned order releases 120
44
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
Component J (4) & J (3) Period in Weeks
Lot size: 30 units (1 case)
LT: 1 week
1 2 3 4 5 6
Gross requirements 480 240
Scheduled receipts 30 30 30
Projected on hand 20 20 20 50 80 110 110
Net requirements 460 160
Planned order receipts 480 180
Planned order releases 480 180
45
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 5
Component J (4) & J (3) Period in Weeks
Lot size: 120 units
LT: 1 week
1 2 3 4 5 6
Gross requirements 480 240
Scheduled receipts 30 30 30
Projected on hand 20 20 20 50 80 50 50
Net requirements 460 160
Planned order receipts 480 180
Planned order releases 480 180
46
Dept. of ME, JSSATE, Bengaluru
Product Structure Tree – Example 6
47
Dept. of ME, JSSATE, Bengaluru
Purchasing
and
Supply Chain Management
48
Dept. of ME, JSSATE, Bengaluru
Purchasing, Procurement
• Purchasing is the first phase of Materials
Management.
• Purchasing refers to the actual buying of materials
and the activities associated with it.
• Procurement includes purchasing, transportation,
warehousing and inbound receiving.
• Procurement is a closed loop process that begins
with the requisition and ends with the payment.
49
Dept. of ME, JSSATE, Bengaluru
Purchasing
• Purchasing is a managerial activity that goes beyond
the simple act of buying.
• It includes research and development for the proper
selection of materials and sources, follow-up to ensure
timely delivery; inspection to ensure both quantity and
quality; to control traffic, receiving, storekeeping and
accounting operations related to purchases.
• The modern thinking is that Purchasing is a strategic
managerial function and any negligence will ultimately
result into decrease in profits.
50
Dept. of ME, JSSATE, Bengaluru
Purchasing - Importance
• Purchasing function provides materials to the factory
without which wheels of machines cannot move.
• A one percent saving in materials cost is equivalent to a 10
percent increase in turnover. Efficient buying can achieve
this.
• Increasing proportion of one’s requirements are now
bought instead of being made as was the practice in the
earlier days. Buying, therefore, assumes significance.
• Purchasing is the main factor in timely execution of
industrial projects.
• Materials management organisations that exist now have
evolved out or purchasing departments.
51
Dept. of ME, JSSATE, Bengaluru
Purchasing -Objectives
• To pay reasonably low prices for the best values
obtainable, negotiating and executing all company
commitments.
• To keep inventories as low as is consistent with
maintaining production.
• To develop satisfactory sources of supply and maintain
good relations with them.
• To secure good vendor performance including prompt
deliveries and acceptable quality.
• To locate new materials or products as required.
• To implement such programmes as value analysis, cost
analysis, and make-or-buy to reduce cost of purchases.

More Related Content

PPTX
Inventory Management , MRP, JIT and SCM
PDF
07.1 lathe numerical
PPTX
Material requirement planning - Production and Operation Management
PPTX
Material selection for manufacturing
PPT
Planned order release
PDF
PDF
Production planning and control - PPC
PDF
Principles and practices of maintenance planning
Inventory Management , MRP, JIT and SCM
07.1 lathe numerical
Material requirement planning - Production and Operation Management
Material selection for manufacturing
Planned order release
Production planning and control - PPC
Principles and practices of maintenance planning

What's hot (20)

PPT
Presentation on Total Productive Maintenance
PPTX
Generic Product Development Process
PPTX
Production Planning And Control
PPTX
Casting
PPT
Master Scheduling
PPTX
Repair methods for basic machine elements
PPTX
Material requirement planning (mrp)
PPTX
Limits, fits and tolerances
PPT
production scheduling
PDF
What is master production schedule
PPTX
GD&T - PPT
PPT
manufacturing operations
PDF
Metal Additive Manufacturing Manufacturing
PPT
Tpm final
PPTX
Geometrical Dimensioning & Tolerencing, GD&T Course. Day2
PDF
Total Productive Maintenance (TPM)
PDF
4.2 job evaluation and merit rating
PPT
09 shop floor control
PPTX
Components of an Injection Mold
PPTX
manufacturing resource planning
Presentation on Total Productive Maintenance
Generic Product Development Process
Production Planning And Control
Casting
Master Scheduling
Repair methods for basic machine elements
Material requirement planning (mrp)
Limits, fits and tolerances
production scheduling
What is master production schedule
GD&T - PPT
manufacturing operations
Metal Additive Manufacturing Manufacturing
Tpm final
Geometrical Dimensioning & Tolerencing, GD&T Course. Day2
Total Productive Maintenance (TPM)
4.2 job evaluation and merit rating
09 shop floor control
Components of an Injection Mold
manufacturing resource planning
Ad

Similar to 18ME56-OM_ Module 5 - MRP, Purchase and SCM.pdf (20)

PPTX
MATERIAL REQUIREMENTS PLANNING (MRP)
PPTX
Operations Management Classroom Presentation
PPTX
MRP CASE STUDY
PPT
Session 5
PPT
Chapter 5_OM
PPT
Heizer 14
PDF
18ME56-OM_ Module 1-Curriculum COs Mapping.pdf
PPTX
MASTER PRODUCTION SCHEDULE (MPS).pptx
DOCX
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
DOC
Preguntas y respuestas examen de SAP PP
PDF
18ME56 Operations Management- Module 1-curriculum c_os mapping
PDF
OPS 571 Effective Communication - tutorialrank.com
PDF
Scps -materials_requirements_planning
PPTX
Managing productions across Supply Chain
PPTX
Managing production across supply chain
DOCX
OPS 571 Social Responsibility - snaptutorial.com
DOCX
OPS 571 Exceptional Education - snaptutorial.com
PDF
Ops 571 Education Organization-snaptutorial.com
DOCX
OPS 571 Education Specialist / snaptutorial.com
MATERIAL REQUIREMENTS PLANNING (MRP)
Operations Management Classroom Presentation
MRP CASE STUDY
Session 5
Chapter 5_OM
Heizer 14
18ME56-OM_ Module 1-Curriculum COs Mapping.pdf
MASTER PRODUCTION SCHEDULE (MPS).pptx
MFG 240 - Manufacturing DesignFinal ProjectScope of Project.docx
Preguntas y respuestas examen de SAP PP
18ME56 Operations Management- Module 1-curriculum c_os mapping
OPS 571 Effective Communication - tutorialrank.com
Scps -materials_requirements_planning
Managing productions across Supply Chain
Managing production across supply chain
OPS 571 Social Responsibility - snaptutorial.com
OPS 571 Exceptional Education - snaptutorial.com
Ops 571 Education Organization-snaptutorial.com
OPS 571 Education Specialist / snaptutorial.com
Ad

More from Dr. Bhimsen Soragaon (12)

PDF
18ME56-OM_ Module 3-Facility and Capacity Planning.pdf
PDF
18ME56-OM_ Module 2-Forecasting.pdf
PDF
18ME56-OM_ Module 4-Aggregate Planning.pdf
PDF
21SFH19-SFH_Module 4 - Avoiding risks and harmful habits.pdf
PDF
21SFH19-SFH_Module 1-Good Health & Its Balance for Positive Mindset.pdf
PDF
21SFH19-SFH_Module 2 - Building of healthy lifestyles for better future.pdf
PDF
18ME56 Operations Management- Module 2-Forecasting
PPTX
CIM 15ME62 Module-3
PPT
CIM 15ME62 Module-2: CAD and Computer Graphics Software; Module 3: Line Bal...
PPTX
CIM 15ME62 Module-1
PDF
Buckling of Columns
PDF
Bending stresses in beams
18ME56-OM_ Module 3-Facility and Capacity Planning.pdf
18ME56-OM_ Module 2-Forecasting.pdf
18ME56-OM_ Module 4-Aggregate Planning.pdf
21SFH19-SFH_Module 4 - Avoiding risks and harmful habits.pdf
21SFH19-SFH_Module 1-Good Health & Its Balance for Positive Mindset.pdf
21SFH19-SFH_Module 2 - Building of healthy lifestyles for better future.pdf
18ME56 Operations Management- Module 2-Forecasting
CIM 15ME62 Module-3
CIM 15ME62 Module-2: CAD and Computer Graphics Software; Module 3: Line Bal...
CIM 15ME62 Module-1
Buckling of Columns
Bending stresses in beams

Recently uploaded (20)

PDF
LS-6-Digital-Literacy (1) K12 CURRICULUM .pdf
PDF
BBC NW_Tech Facilities_30 Odd Yrs Ago [J].pdf
PDF
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering
PPTX
Soft Skills Unit 2 Listening Speaking Reading Writing.pptx
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PDF
IAE-V2500 Engine for Airbus Family 319/320
PPTX
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
PPTX
Research Writing, Mechanical Engineering
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PPTX
SC Robotics Team Safety Training Presentation
PPTX
Solar energy pdf of gitam songa hemant k
PPT
Module_1_Lecture_1_Introduction_To_Automation_In_Production_Systems2023.ppt
PPT
Programmable Logic Controller PLC and Industrial Automation
PDF
IAE-V2500 Engine Airbus Family A319/320
PPTX
Software-Development-Life-Cycle-SDLC.pptx
PPTX
Wireless sensor networks (WSN) SRM unit 2
DOCX
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
PPTX
AI-Reporting for Emerging Technologies(BS Computer Engineering)
PDF
B461227.pdf American Journal of Multidisciplinary Research and Review
PDF
Research on ultrasonic sensor for TTU.pdf
LS-6-Digital-Literacy (1) K12 CURRICULUM .pdf
BBC NW_Tech Facilities_30 Odd Yrs Ago [J].pdf
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering
Soft Skills Unit 2 Listening Speaking Reading Writing.pptx
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
IAE-V2500 Engine for Airbus Family 319/320
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
Research Writing, Mechanical Engineering
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
SC Robotics Team Safety Training Presentation
Solar energy pdf of gitam songa hemant k
Module_1_Lecture_1_Introduction_To_Automation_In_Production_Systems2023.ppt
Programmable Logic Controller PLC and Industrial Automation
IAE-V2500 Engine Airbus Family A319/320
Software-Development-Life-Cycle-SDLC.pptx
Wireless sensor networks (WSN) SRM unit 2
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
AI-Reporting for Emerging Technologies(BS Computer Engineering)
B461227.pdf American Journal of Multidisciplinary Research and Review
Research on ultrasonic sensor for TTU.pdf

18ME56-OM_ Module 5 - MRP, Purchase and SCM.pdf

  • 2. Module – 5: • Material Requirement Planning (MRP): • Dependent versus independent demand, an overview of MRP – MRP inputs and outputs, MRP processing, ERP capacity requirement planning, benefits and limitations of MRP. • Purchasing and Supply Chain Management (SCM): • Introduction, Importance of purchasing and SCM, the procurement process, Concept of tenders, Approaches to SCM, Vendor development. 2 Dept. of ME, JSSATE, Bengaluru
  • 3. Module Outcome: At the end of this module, you will be able to: CO# Course Outcome Bloom’s Level 5 Apply MRP, purchasing and SCM techniques into practice. 3 3 Dept. of ME, JSSATE, Bengaluru Forecasting Learning Objectives: After completing this module, you should be able to:
  • 4. 4 Dept. of ME, JSSATE, Bengaluru • A technique of determining the quantity and timing for the acquisition of dependent demand items needed to satisfy the MPS requirements. • A computerized inventory control and production planning system. • The main objective of any inventory system is to ensure that material is available when needed. • One objective of MRP is to maintain the lowest possible level of inventory. • MRP does this by determining when component items are needed and scheduling them to be ready at that time, no earlier and no later. Material Requirement Planning
  • 5. 5 Dept. of ME, JSSATE, Bengaluru Material Requirement Planning Source: OM by Russel & Taylor
  • 6. 6 Dept. of ME, JSSATE, Bengaluru • MRP is useful for dependent and discrete demand items, complex products, job shop production, and assemble-to-order environments. • Managing component demand inventory is different from managing finished goods inventory. • Independent demand is demand for a finished product, such as a computer, a bicycle, or a pizza. • Dependent Demand: Demand for components that are derived from the demand for the other items. • Parent and component items: A parent is an assembly made up of basic parts or components. When to use MRP; Terms
  • 7. 7 Dept. of ME, JSSATE, Bengaluru Source: OM by Russel & Taylor Terms used in MRP
  • 8. 8 Dept. of ME, JSSATE, Bengaluru • Lot size: The quantity of items required for an order (purchased from vendor or produced in-house). • Time phasing: Scheduling to produce or receive an appropriate amount (lot) of material so that it will be available in the time periods when needed – not before or after. • Time bucket: The time period used for planning purposes in MRP, usually a week. • Bill of materials: A listing of all the components (subassemblies and materials) that go into an assembled item. It includes the part numbers and quantity required per assembly. Terms used in MRP
  • 9. 9 Dept. of ME, JSSATE, Bengaluru • Gross requirements: The total expected demand for an item or raw material during each time period without regard to the amount on hand. • For end items, these quantities are shown in the master schedule; for components, these quantities are derived from the planned-order releases of their immediate “parents.” • Projected on hand: The expected amount of inventory that will be on hand at the beginning of each time period (scheduled receipts plus available inventory from last period). • Net requirements: The actual amount needed in each time period. Terms used in MRP
  • 10. 10 Dept. of ME, JSSATE, Bengaluru • Scheduled receipt: Materials already on order from a vendor or in-house shop. In MRP, both the quantity and the projected time of receipt are shown. • Planned receipt: Materials that will be ordered from a vendor or in-house shop. Otherwise, it is similar to scheduled receipt (no difference in some MRPs) • Lead-time offset: The supply time, or number of time buckets between releasing an order and receiving the materials. • Planned order release: The plan (quantity & date) to initiate the purchase or manufacture of items so that they will be received on schedule after the lead time offset. • Time fence: Management-specified date within which no changes in the master schedule are allowed. Terms used in MRP
  • 11. 11 Dept. of ME, JSSATE, Bengaluru Source: OM by Russel & Taylor Inputs and Outputs of MRP Which end items are to be produced, when they are needed, and in what quantities. A listing of all of the assemblies, subassemblies, parts, part costs, and raw materials that are needed to produce one unit of a finished product. A database of information on every item produced, ordered, or inventoried. Bill of Materials
  • 12. 12 Dept. of ME, JSSATE, Bengaluru • A listing of all of the assemblies, subassemblies, parts, part costs, and raw materials that are needed to produce one unit of a finished product. • Single level BoM and Indented BoM • Engineering bill of materials (EBOM) and Manufacturing bill of materials (MBOM) • EBOM- finished product details as it was originally designed. • (MBOM) contains information on all the parts and assemblies required to build a complete and shippable product (includes packing materials). Bill of Materials
  • 13. 13 Dept. of ME, JSSATE, Bengaluru https://help.openbom.com/2018/09/08/bom-single-level-multi-level-flattened/ Bill of Materials
  • 14. 14 Dept. of ME, JSSATE, Bengaluru Bill of Materials
  • 15. 15 Dept. of ME, JSSATE, Bengaluru Bill of Materials Indented or Multi-level BoM
  • 16. 16 Dept. of ME, JSSATE, Bengaluru • A visual depiction of the requirements in a bill of materials, where all components are listed by levels. Product Structure Tree Source: OM by Stevenson, W J Assembly Diagram
  • 17. 17 Dept. of ME, JSSATE, Bengaluru Product Structure Tree Source: OM by Stevenson, W J
  • 18. 18 Dept. of ME, JSSATE, Bengaluru Product Structure Tree Source: OM by Stevenson, W J
  • 19. 19 Dept. of ME, JSSATE, Bengaluru Product Structure Tree
  • 20. 20 Dept. of ME, JSSATE, Bengaluru Product Structure Tree
  • 21. 21 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 1 • Use the information presented in the figure to do the following: • Determine the quantities of B, C, D, E, and F needed to assemble one X. • Determine the quantities of these components that will be required to assemble 10 Xs, taking into account the quantities on hand (i.e., in inventory) of various components: Source: OM by Stevenson, W J
  • 22. 22 Dept. of ME, JSSATE, Bengaluru Product Structure Tree Source: OM by Stevenson, W J
  • 23. 23 Dept. of ME, JSSATE, Bengaluru Product Structure Tree Thus, for one X, quantities of components required are: B = 2; C = 1; D = 6; E = 24+2+2 = 28; F = 2 Solution: a
  • 24. 24 Dept. of ME, JSSATE, Bengaluru Product Structure Tree Solution: b Thus, for 10 Xs, quantities of components required are: B = 16; C = 0; D = 40; E = 100+16 = 116; F = 0 Source: OM by Stevenson, W J
  • 25. 25 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 • An end product P is assembled by three subassemblies, A, B and C. Subassembly A consists of two units of D, two units of E and one unit of F. To make B, one G and three units of H are needed. Subassembly C requires two units of J and one unit of F. Component D requires two units of J and one K. • (a) Construct product structure tree for P mentioning the levels. • (b) Develop an indented level of bill of materials • (c) Compute the quantities of each component to produce 200 units of P
  • 26. 26 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 P Level 0
  • 27. 27 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 P Level 0 B C A Level 1
  • 28. 28 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 P Level 0 B C A G H 3 J 2 D 2 F E 2 F Level 1
  • 29. 29 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 P Level 0 B C A G H 3 J 2 D 2 F E 2 F Level 1 K J 2
  • 30. 30 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 Bill of Materials Part No. or Name Qty. Level A 1 1 D 2 2 J 2 3 K 1 3 E 2 2 F 1 2 B 1 1 G 1 2 H 3 2 C 1 1 F 1 2 J 2 3 Product P Level 0
  • 31. 31 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 2 Bill of Materials Part No. or Name Qty. per one P Total Qty. Required A 1 1 x 200 = 200 B 1 1 x 200 = 200 C 1 1 x 200 = 200 D 2 2 x 1 x 200 = 400 E 2 2 x 1 x 200 = 400 F 1 (1 x 200 )+ (1 x 200) = 400 G 1 1 x 1 x 200 = 200 H 3 3 x 1 x 200 = 600 J 4 (2 x 2 x 1 x 200) + (2 x 1 x 200) = 1200 K 1 1 x 2 x 200 = 400 Total P required = 200 units
  • 32. 32 Dept. of ME, JSSATE, Bengaluru MRP Processing (Logic) • The MRP process consists of four basic steps: • (1) exploding the bill of material • (2) netting out inventory • (3) lot sizing, and • (4) time-phasing requirements. • The process is performed again and again, moving down the product structure until all items have been scheduled. Source: OM by Russel & Taylor
  • 33. 33 Dept. of ME, JSSATE, Bengaluru MRP Processing (Logic) - Matrix Source: OM by Russel & Taylor
  • 34. 34 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 3 • Complete the following MRP matrix for an item X: • In what periods should orders be released, and what should be the size of those orders? Source: OM by Russel & Taylor
  • 35. 35 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 3 • Solution: Source: OM by Russel & Taylor
  • 36. 36 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 4 • Complete the following MRP matrix for an item X. Determine when orders should be released and the size of those orders. Source: OM by Russel & Taylor
  • 37. 37 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 3 • Solution: Source: OM by Russel & Taylor Item X Period in Weeks Lot size: 50 LT: 2 weeks 1 2 3 4 5 6 7 8 Gross requirements 25 30 56 25 100 40 30 20 Scheduled receipts 50 Projected on hand 30 5 25 19 44 0 10 30 10 Net requirements 31 06 56 40 20 0 Planned order receipts 50 50 56 50 50 Planned order releases 50 50 56 50 50
  • 38. 38 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 4 • Complete the following MRP matrix for an item X. Determine when orders should be released and the inventory at the end of week 8. Item X Period in Weeks Lot size: 500 LT: 4 weeks 1 2 3 4 5 6 7 8 Gross requirements 150 150 150 150 200 200 180 320 Scheduled receipts 500 500 500 Projected on hand 300 150 0 350 200 0 300 120 300 Planned order releases 500 500
  • 39. 39 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 4 • Complete the following MRP matrix for an item X. Determine when orders should be released and the inventory at the end of week 8. • MRP should have planned order releases of 500 units in week 2 and 4. • There are 300 units on hand at the end of week 8. Item X Period in Weeks Lot size: 500 LT: 4 weeks 1 2 3 4 5 6 7 8 Gross requirements 150 150 150 150 200 200 180 320 Scheduled receipts 500 500 500 Projected on hand 300 150 0 350 200 0 300 120 300 Planned order releases 500 500
  • 40. 40 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 • Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. • Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times are two weeks each for E and B, and one week for J. • Prepare a material requirements plan for component J.
  • 41. 41 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 • Prepare a material requirements plan for component J. • Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned-order releases through week 3 have all been executed. How many more Bs and Js will be on hand in week 6?
  • 42. 42 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 Item E Period in Weeks Lot size: 80 LT: 2 weeks 1 2 3 4 5 6 Gross requirements 80 Scheduled receipts Projected on hand Net requirements 80 Planned order receipts 80 Planned order releases 80
  • 43. 43 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 Component B (2) Period in Weeks Lot size: 120 units LT: 2 weeks 1 2 3 4 5 6 Gross requirements 160 Scheduled receipts Projected on hand 60 60 60 60 20 20 20 Net requirements 100 Planned order receipts 120 Planned order releases 120
  • 44. 44 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 Component J (4) & J (3) Period in Weeks Lot size: 30 units (1 case) LT: 1 week 1 2 3 4 5 6 Gross requirements 480 240 Scheduled receipts 30 30 30 Projected on hand 20 20 20 50 80 110 110 Net requirements 460 160 Planned order receipts 480 180 Planned order releases 480 180
  • 45. 45 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 5 Component J (4) & J (3) Period in Weeks Lot size: 120 units LT: 1 week 1 2 3 4 5 6 Gross requirements 480 240 Scheduled receipts 30 30 30 Projected on hand 20 20 20 50 80 50 50 Net requirements 460 160 Planned order receipts 480 180 Planned order releases 480 180
  • 46. 46 Dept. of ME, JSSATE, Bengaluru Product Structure Tree – Example 6
  • 47. 47 Dept. of ME, JSSATE, Bengaluru Purchasing and Supply Chain Management
  • 48. 48 Dept. of ME, JSSATE, Bengaluru Purchasing, Procurement • Purchasing is the first phase of Materials Management. • Purchasing refers to the actual buying of materials and the activities associated with it. • Procurement includes purchasing, transportation, warehousing and inbound receiving. • Procurement is a closed loop process that begins with the requisition and ends with the payment.
  • 49. 49 Dept. of ME, JSSATE, Bengaluru Purchasing • Purchasing is a managerial activity that goes beyond the simple act of buying. • It includes research and development for the proper selection of materials and sources, follow-up to ensure timely delivery; inspection to ensure both quantity and quality; to control traffic, receiving, storekeeping and accounting operations related to purchases. • The modern thinking is that Purchasing is a strategic managerial function and any negligence will ultimately result into decrease in profits.
  • 50. 50 Dept. of ME, JSSATE, Bengaluru Purchasing - Importance • Purchasing function provides materials to the factory without which wheels of machines cannot move. • A one percent saving in materials cost is equivalent to a 10 percent increase in turnover. Efficient buying can achieve this. • Increasing proportion of one’s requirements are now bought instead of being made as was the practice in the earlier days. Buying, therefore, assumes significance. • Purchasing is the main factor in timely execution of industrial projects. • Materials management organisations that exist now have evolved out or purchasing departments.
  • 51. 51 Dept. of ME, JSSATE, Bengaluru Purchasing -Objectives • To pay reasonably low prices for the best values obtainable, negotiating and executing all company commitments. • To keep inventories as low as is consistent with maintaining production. • To develop satisfactory sources of supply and maintain good relations with them. • To secure good vendor performance including prompt deliveries and acceptable quality. • To locate new materials or products as required. • To implement such programmes as value analysis, cost analysis, and make-or-buy to reduce cost of purchases.