Project Failure Modes: Lessons from the Field Roger Layton MD, NIRO Project Management (Pty) Ltd MD, Roger Layton Associates (Pty) Ltd
Basic Premises Failure Avoidance it is possible to avoid failure completely or to minimise the impact at the earliest time but this requires comprehensive understanding of all possible types and modes of failure as well as best practice approaches to deal with issues and threats to success Learning from Other’s Mistakes What can we learn from large-scale failures that can help to avoid future failures Can we all learn from the lessons of a few disasters? Improving our Understanding of Failure We need to focus more on the understanding of failure than on success We will encounter the potential for failure every day
What is Project Failure? Analysis of Google search on “Project Failure” identifies almost exclusively IT Project Failure! Many good case studies reported – but virtually NO companies (customers) or suppliers prepared to comment on their own failures Need to distinguish levels and modes of failure…
Defining “Failure” The inability of the project to deliver the intended benefits to the  identified stakeholders However – Failure is relative – there are many levels of failure from complete failure to mild failure, and each should be seen in context
Projects and Complexity A project is a complex arrangement of time, costs, resources, scope, benefits, risks, issues, quality and structures Failure is very easy  : any one part or link can cause failure – there are millions of way to fail Success is very difficult  : there is  only ONE way to succeed  – the correct balance of the project elements
Levels of Failure Complete Failure Cancelled before completion Failure after implementation so serious that have to roll-back to previous version or manual alternative Organisation is significantly worse off than before, and may be at risk of bankruptcy Serious Failure Continues into operation, but does not achieve full benefits May be less effective and efficient than existing system More costs than benefits and significant loss of brand value Medium Failure Some benefits received, but not all Many tolerances overrun Major fixes required to recover Mild Failure Largely meets benefits but some of the tolerances exceeded (time, cost, quality, benefits, risks, knowledge transfer, …)
If it ain’t broke, don’t fix it! How often are organisations forced into the conservative position of not starting new projects because of a fear of failure (CYA) At the same time they deny themselves the opportunities and benefits that may emerge from new projects and products. Without new IT and business projects,  organisations will over time become more ineffective, more inefficient and eventually will become extinct.
If it ain’t broke yet, then break it! How often are organisations placed into a worse position by having tried to develop and install a new system and failed. We rely on IT systems more and more in our world. When large systems fail to be delivered, or fail after deployed, they can impact on the lives of thousands or millions of people.
Managing Change All programmes and projects are a reaction to the need for change – driven by business strategy and policy Programmes deliver the changes and the benefits by producing new products, processes and services Projects will create these products
Change Strategy Conservative Evolutionary If it ain’t broke, don’t fix it If it ain’t broke yet, then break it Do nothing… Risk of stagnation and extinction Lose competitive advantage Lose efficiency and effectiveness OR Sit back and watch competitors fail! Risk of high costs, not meeting deadlines and not receiving any benefits Being in a worse position than before with nothing to show Bad publicity and brand damage Legal actions We are in trouble if we do, and in trouble if we don’t Do ALL large IT projects have to endure the high risk of failure?
Examples from the Field Source : Information Week, 13/16 Oct 2006, Paul McDougall “ in most cases overly complex IT makeovers are doomed to fail because their success depends upon too many unpredictable variables falling nicely into place” “ Some elements of success include :- Meticulous business case analysis Sound strategies for change management Workable back-up plans if the big one happens ”
Selection of Field Examples Only using documented examples as have appeared in press No local examples cited Specific elements of failure extracted to serve as lessons learned
Example 1 : MacDonalds 2001 : Intranet to connect 30,000 outlets with real-time information $170 million written off Early termination when estimated costs of completion reached $1 billion Decided that money could be better used PROBLEM : scope too broad – no possible way to construct it MODE OF FAILURE: Business Case failure TO THEIR CREDIT : Decided to stop before spending any more!
Example 2 : US IRS GOAL : Upgrade the fraud-detection system Switched off old system PROBLEM: System did not work – could not be deployed – and old system already switched off COSTS : Estimated losses of $318 million in lost revenue/undetected fraud MODE OF FAILURE: Many – classified as “maintenance upgrade” instead of new system
Example 3 : IRS infrastructure 8 year project to revise infrastructure Personnel retiring and lack of expertise Failure to deploy meant rebooting the old system for 2007 tax season Costs to Date : $8 billion MODE OF FAILURE: Many – too large a project – too long a timeframe – solutions out of date before deployed – loss of skills
Example 4 : Neilsen Media Research Viewer stats in TV industry Complete rewrite of the system Wanted to get finished within one year 8 years on still no new system Costs and time overrun MODE OF FAILURE : Unrealistic schedules – always overdue and rushing – quality second to time, costs get lost
Example 5 : UK NHS Rewrite of complete national health system More than 12 vendors – no compatibility in systems – squabbling among vendors Users inadequately consulted Contractors get no money until system delivered One large contractor has pulled out at loss of $450 million Costs to date = $10 billion overrun Major vendor (iSoft) under threat of bankruptcy
Example 5 / contd MODES OF FAILURE : many Government contracting policy – try to reduce risk by spreading work among vendors Government tender policies – splitting specifications from implementation over different organisations Job too large – biting off too much
Analysis of Failures Need a formal method for analysis of failures so that we do not have to learn same lessons over and over again Need a means of reporting failure and disclosure so that maximum benefits are gained for the future Need to ensure that organisations accountable for their work and cannot simply hide details in order to protect reputations HOWEVER : Analysis of Failure is itself Complex
Analysis of Failure/2 Historical Research = What Happened? Many histories – many viewpoints Can we get to the truth or are all interpretations naturally biased Is there such a thing as an independent analysis? Analysis can only be successful if there is a well-documented project
Risks that can induce Failure Organisation Failure to constitute a Project Board properly Lack of involvement from corporate management Lack of involvement from customer Lack of involvement from user Wrong people selected to assist Responsibilities not explicit Some key responsibilities not allocated
Risks that can induce Failure/2 Communication Lack of reporting structure Lack of sufficient information from decision-making Lack of usage of the information as reported – get the information but not acted on People who receive reports do not know what they are supposed to do with them – think that someone else is acting on them
Other Risks that can induce Failure Specification + Scope Management Business Case Management + Realised Benefits Quality Control Change Control + Issue Management Risk Analysis + Risk Management Configuration Control User Involvement Incompetence of Personnel Unsuitable Technology
Recommendations Recommend that all projects be divided into smaller units – easier to manage – impact of failure is reduced = DIVIDE AND CONQUER High-level Programme Management takes the long-term view – identifies evolving technologies and decides on appropriate solution structures
Recommendations/2 Need a Project Management Method that be used throughout the organisations Common Language for Projects E.g. what is an issue, what is a risk, what does “quality” imply, what is a “tolerance” Simple method that is easy to apply  Method that can be used for early detection of failure modes

More Related Content

PPT
Business Intelligence Analysis - The key to organisational and business success
PPT
Analyzing Project Failure Modes: Lessons learnt from the field
PPT
Escape Analysis Paralysis
PPT
Where Business Analysis ends
PPT
Federated Access Management, JISC Presentation
PPT
Project Management The State of the Art
PDF
"Benefits management: a core theme in management research and education?" con...
PPT
Stakeholder Management
Business Intelligence Analysis - The key to organisational and business success
Analyzing Project Failure Modes: Lessons learnt from the field
Escape Analysis Paralysis
Where Business Analysis ends
Federated Access Management, JISC Presentation
Project Management The State of the Art
"Benefits management: a core theme in management research and education?" con...
Stakeholder Management

What's hot (20)

PDF
Building a bullet proof business case
PDF
"Benefits management: a core theme in management research and education?" con...
PPT
Overcome barriers to good req mgmt
PPTX
IT Business Value
PDF
Stevens MSIS - New Student Orientation
PPT
Sacred PM Practices
PDF
8 steps to Successful Accounts System Selection - Xledger Whitepaper
PDF
IT Service Management (ITSM) Model for Business & IT Alignement
PPT
Business Driven Technology Considerations
PDF
Regulatory Instability, BPM Technology, and BPM Skill Configurations
PPT
Select collaboration platform
PPT
IT Governance Concept
PPTX
Select and Implement a Next Generation Endpoint Protection Solution
PPTX
Spa - Systemic Project Alignment
PPTX
Optimize Change Management
PDF
Causal Insight in Technology & Innovation Benefits Forecasting & Realization
PPTX
Best Practices in Software Vendor Selection
PDF
I'm a Chief Experience Officer - Giarte
PDF
A Data-driven Maturity Model for Modernized, Automated, and Transformed IT
Building a bullet proof business case
"Benefits management: a core theme in management research and education?" con...
Overcome barriers to good req mgmt
IT Business Value
Stevens MSIS - New Student Orientation
Sacred PM Practices
8 steps to Successful Accounts System Selection - Xledger Whitepaper
IT Service Management (ITSM) Model for Business & IT Alignement
Business Driven Technology Considerations
Regulatory Instability, BPM Technology, and BPM Skill Configurations
Select collaboration platform
IT Governance Concept
Select and Implement a Next Generation Endpoint Protection Solution
Spa - Systemic Project Alignment
Optimize Change Management
Causal Insight in Technology & Innovation Benefits Forecasting & Realization
Best Practices in Software Vendor Selection
I'm a Chief Experience Officer - Giarte
A Data-driven Maturity Model for Modernized, Automated, and Transformed IT
Ad

Similar to Back to the Future (20)

PPTX
Data Center Transformation Program Planning and Design
PPTX
The Future of Oilsands Projects – Productivity Improvement & the Role o...
PDF
IT Optimization: Navigation Fiscal Austerity
PPTX
How to Achieve Measurable Benefits Through Project and Organizational Change
PPT
World Bank & IDB Workshop PBCs Finance and Risk - Thornton Wyatt 2015
PPTX
2014Q1-0127_USAW_CONF_Weitz_When Outsourcing Stops Making Sense
PPTX
2014-01-27_Weitz_Outsourcing
PDF
Benefits Management in Health and Care part 1: Identify and map target benefits
PDF
Enterprise Project and Portfolio Management: Managing the Revolution
 
DOCX
Post 1Participative Budgetary Process serves several benefit.docx
PDF
Transformation of legacy landscape in the insurance world
PPTX
Missing the Iceberg – avoiding project failure through killing or redefining ...
PDF
Why projects fail avoiding the classic pitfalls
PDF
Trillium Software Building the Business Case for Data Quality
PDF
Chaucer Quarterly Review Issue 2 EN
DOC
Comprehensive Data Governance Program
PDF
Predictors of Project Failure
PPT
Why Do So Many Software Projects Fail?
PPT
Asis Roy on "IT Reaches The Root And Changes Lives" at PM Conference India 2009
PPT
ch03-Design Project.ppt
Data Center Transformation Program Planning and Design
The Future of Oilsands Projects – Productivity Improvement & the Role o...
IT Optimization: Navigation Fiscal Austerity
How to Achieve Measurable Benefits Through Project and Organizational Change
World Bank & IDB Workshop PBCs Finance and Risk - Thornton Wyatt 2015
2014Q1-0127_USAW_CONF_Weitz_When Outsourcing Stops Making Sense
2014-01-27_Weitz_Outsourcing
Benefits Management in Health and Care part 1: Identify and map target benefits
Enterprise Project and Portfolio Management: Managing the Revolution
 
Post 1Participative Budgetary Process serves several benefit.docx
Transformation of legacy landscape in the insurance world
Missing the Iceberg – avoiding project failure through killing or redefining ...
Why projects fail avoiding the classic pitfalls
Trillium Software Building the Business Case for Data Quality
Chaucer Quarterly Review Issue 2 EN
Comprehensive Data Governance Program
Predictors of Project Failure
Why Do So Many Software Projects Fail?
Asis Roy on "IT Reaches The Root And Changes Lives" at PM Conference India 2009
ch03-Design Project.ppt
Ad

Recently uploaded (20)

PDF
sbt 2.0: go big (Scala Days 2025 edition)
PPTX
AI IN MARKETING- PRESENTED BY ANWAR KABIR 1st June 2025.pptx
PDF
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
PPT
Geologic Time for studying geology for geologist
PDF
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
PPTX
Module 1 Introduction to Web Programming .pptx
PPTX
Build Your First AI Agent with UiPath.pptx
DOCX
Basics of Cloud Computing - Cloud Ecosystem
PPTX
Configure Apache Mutual Authentication
PDF
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
PPTX
Custom Battery Pack Design Considerations for Performance and Safety
PDF
Improvisation in detection of pomegranate leaf disease using transfer learni...
PDF
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
PDF
Accessing-Finance-in-Jordan-MENA 2024 2025.pdf
PDF
Enhancing plagiarism detection using data pre-processing and machine learning...
PDF
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PDF
Taming the Chaos: How to Turn Unstructured Data into Decisions
PPTX
Training Program for knowledge in solar cell and solar industry
PPTX
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
sbt 2.0: go big (Scala Days 2025 edition)
AI IN MARKETING- PRESENTED BY ANWAR KABIR 1st June 2025.pptx
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
Geologic Time for studying geology for geologist
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
Module 1 Introduction to Web Programming .pptx
Build Your First AI Agent with UiPath.pptx
Basics of Cloud Computing - Cloud Ecosystem
Configure Apache Mutual Authentication
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
Custom Battery Pack Design Considerations for Performance and Safety
Improvisation in detection of pomegranate leaf disease using transfer learni...
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
Accessing-Finance-in-Jordan-MENA 2024 2025.pdf
Enhancing plagiarism detection using data pre-processing and machine learning...
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
Taming the Chaos: How to Turn Unstructured Data into Decisions
Training Program for knowledge in solar cell and solar industry
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx

Back to the Future

  • 1. Project Failure Modes: Lessons from the Field Roger Layton MD, NIRO Project Management (Pty) Ltd MD, Roger Layton Associates (Pty) Ltd
  • 2. Basic Premises Failure Avoidance it is possible to avoid failure completely or to minimise the impact at the earliest time but this requires comprehensive understanding of all possible types and modes of failure as well as best practice approaches to deal with issues and threats to success Learning from Other’s Mistakes What can we learn from large-scale failures that can help to avoid future failures Can we all learn from the lessons of a few disasters? Improving our Understanding of Failure We need to focus more on the understanding of failure than on success We will encounter the potential for failure every day
  • 3. What is Project Failure? Analysis of Google search on “Project Failure” identifies almost exclusively IT Project Failure! Many good case studies reported – but virtually NO companies (customers) or suppliers prepared to comment on their own failures Need to distinguish levels and modes of failure…
  • 4. Defining “Failure” The inability of the project to deliver the intended benefits to the identified stakeholders However – Failure is relative – there are many levels of failure from complete failure to mild failure, and each should be seen in context
  • 5. Projects and Complexity A project is a complex arrangement of time, costs, resources, scope, benefits, risks, issues, quality and structures Failure is very easy : any one part or link can cause failure – there are millions of way to fail Success is very difficult : there is only ONE way to succeed – the correct balance of the project elements
  • 6. Levels of Failure Complete Failure Cancelled before completion Failure after implementation so serious that have to roll-back to previous version or manual alternative Organisation is significantly worse off than before, and may be at risk of bankruptcy Serious Failure Continues into operation, but does not achieve full benefits May be less effective and efficient than existing system More costs than benefits and significant loss of brand value Medium Failure Some benefits received, but not all Many tolerances overrun Major fixes required to recover Mild Failure Largely meets benefits but some of the tolerances exceeded (time, cost, quality, benefits, risks, knowledge transfer, …)
  • 7. If it ain’t broke, don’t fix it! How often are organisations forced into the conservative position of not starting new projects because of a fear of failure (CYA) At the same time they deny themselves the opportunities and benefits that may emerge from new projects and products. Without new IT and business projects, organisations will over time become more ineffective, more inefficient and eventually will become extinct.
  • 8. If it ain’t broke yet, then break it! How often are organisations placed into a worse position by having tried to develop and install a new system and failed. We rely on IT systems more and more in our world. When large systems fail to be delivered, or fail after deployed, they can impact on the lives of thousands or millions of people.
  • 9. Managing Change All programmes and projects are a reaction to the need for change – driven by business strategy and policy Programmes deliver the changes and the benefits by producing new products, processes and services Projects will create these products
  • 10. Change Strategy Conservative Evolutionary If it ain’t broke, don’t fix it If it ain’t broke yet, then break it Do nothing… Risk of stagnation and extinction Lose competitive advantage Lose efficiency and effectiveness OR Sit back and watch competitors fail! Risk of high costs, not meeting deadlines and not receiving any benefits Being in a worse position than before with nothing to show Bad publicity and brand damage Legal actions We are in trouble if we do, and in trouble if we don’t Do ALL large IT projects have to endure the high risk of failure?
  • 11. Examples from the Field Source : Information Week, 13/16 Oct 2006, Paul McDougall “ in most cases overly complex IT makeovers are doomed to fail because their success depends upon too many unpredictable variables falling nicely into place” “ Some elements of success include :- Meticulous business case analysis Sound strategies for change management Workable back-up plans if the big one happens ”
  • 12. Selection of Field Examples Only using documented examples as have appeared in press No local examples cited Specific elements of failure extracted to serve as lessons learned
  • 13. Example 1 : MacDonalds 2001 : Intranet to connect 30,000 outlets with real-time information $170 million written off Early termination when estimated costs of completion reached $1 billion Decided that money could be better used PROBLEM : scope too broad – no possible way to construct it MODE OF FAILURE: Business Case failure TO THEIR CREDIT : Decided to stop before spending any more!
  • 14. Example 2 : US IRS GOAL : Upgrade the fraud-detection system Switched off old system PROBLEM: System did not work – could not be deployed – and old system already switched off COSTS : Estimated losses of $318 million in lost revenue/undetected fraud MODE OF FAILURE: Many – classified as “maintenance upgrade” instead of new system
  • 15. Example 3 : IRS infrastructure 8 year project to revise infrastructure Personnel retiring and lack of expertise Failure to deploy meant rebooting the old system for 2007 tax season Costs to Date : $8 billion MODE OF FAILURE: Many – too large a project – too long a timeframe – solutions out of date before deployed – loss of skills
  • 16. Example 4 : Neilsen Media Research Viewer stats in TV industry Complete rewrite of the system Wanted to get finished within one year 8 years on still no new system Costs and time overrun MODE OF FAILURE : Unrealistic schedules – always overdue and rushing – quality second to time, costs get lost
  • 17. Example 5 : UK NHS Rewrite of complete national health system More than 12 vendors – no compatibility in systems – squabbling among vendors Users inadequately consulted Contractors get no money until system delivered One large contractor has pulled out at loss of $450 million Costs to date = $10 billion overrun Major vendor (iSoft) under threat of bankruptcy
  • 18. Example 5 / contd MODES OF FAILURE : many Government contracting policy – try to reduce risk by spreading work among vendors Government tender policies – splitting specifications from implementation over different organisations Job too large – biting off too much
  • 19. Analysis of Failures Need a formal method for analysis of failures so that we do not have to learn same lessons over and over again Need a means of reporting failure and disclosure so that maximum benefits are gained for the future Need to ensure that organisations accountable for their work and cannot simply hide details in order to protect reputations HOWEVER : Analysis of Failure is itself Complex
  • 20. Analysis of Failure/2 Historical Research = What Happened? Many histories – many viewpoints Can we get to the truth or are all interpretations naturally biased Is there such a thing as an independent analysis? Analysis can only be successful if there is a well-documented project
  • 21. Risks that can induce Failure Organisation Failure to constitute a Project Board properly Lack of involvement from corporate management Lack of involvement from customer Lack of involvement from user Wrong people selected to assist Responsibilities not explicit Some key responsibilities not allocated
  • 22. Risks that can induce Failure/2 Communication Lack of reporting structure Lack of sufficient information from decision-making Lack of usage of the information as reported – get the information but not acted on People who receive reports do not know what they are supposed to do with them – think that someone else is acting on them
  • 23. Other Risks that can induce Failure Specification + Scope Management Business Case Management + Realised Benefits Quality Control Change Control + Issue Management Risk Analysis + Risk Management Configuration Control User Involvement Incompetence of Personnel Unsuitable Technology
  • 24. Recommendations Recommend that all projects be divided into smaller units – easier to manage – impact of failure is reduced = DIVIDE AND CONQUER High-level Programme Management takes the long-term view – identifies evolving technologies and decides on appropriate solution structures
  • 25. Recommendations/2 Need a Project Management Method that be used throughout the organisations Common Language for Projects E.g. what is an issue, what is a risk, what does “quality” imply, what is a “tolerance” Simple method that is easy to apply Method that can be used for early detection of failure modes