Construction Equipment and Plant Management
COTM 4202
General
Definition
 It is the number of units and the
size of equipment that would
permit the constructor to
accomplish the activity with a
duration resulting in the lowest
cost.
 Estimating and planning involves
the judicious selection of
equipment, the careful scheduling
of time and resources, and the
accurate determination of expected
system output and cost.
31 July 2021 2
COTM 4202
 Haul unit horsepower
 Haul road rolling resistance
 Haul road grades
 Haul unit loaded and empty weight
 Haul unit transmission characteristics
 Haul unit loading time
 Haul unit travel time
 Haul unit delay time
 Altitude of the project site
31 July 2021
COTM 4202 3
 Total power that an engine is capable of
generating is expressed as its horsepower.
 Available horsepower is power that is available
to perform work after taking into account losses
and consumption in other machine functions.
 Rimpull is defined as the tractive force between
the driving wheels and the surface on which
they travel.( V is velocity in mph)
31 July 2021
COTM 4202 4
31 July 2021
COTM 4202 5
Power generated by engine
Drawbar Pull
Rolling Resistance
Rimpull
 Rolling resistance is resistance offered to movement of
materials on a plain surface; often expressed in pounds
per ton of materials.
 Rolling Resistance depends upon:
31 July 2021
COTM 4202 6
31 July 2021
COTM 4202 7
31 July 2021
COTM 4202 8
 The force-opposing movement of a machine up a
frictionless slope is grade resistance.
 The effect of gravitational force in aiding movement of a
vehicle down a slope is grade assistance.
F= 20 lbs/ G% per Ton
 The cycle capacity C of a piece of equipment is
defined as the number of output units per cycle
of operation under standard work conditions.
 The standard production rate R of a piece of
construction equipment is defined as the
number of output units per unit time.
 The cycle time T refers to units of time per cycle
of operation.
31 July 2021
COTM 4202 9
 Time to load a mover for load shifting will
determine loads that can be transferred.
Longer loading time lesser will be
productivity.
 To is loading time
 Te is cycle time for loader/excavator
 Ch is capacity of a hauler (dump truck)
 Ce loading rate/capacity of loader
31 July 2021
COTM 4202 10
 It is time for moving load from production site to
disposal site. Longer time will reduce productivity.
 To determine the productivity of a hauler,
› Let: D be the distance from source to a dump site, S
be the average speed of the hauler, Tt be the travel
time for the round trip to the dump site, To be the
loading time, Td be the dumping time plus other
delays.
 Then the travel time for the round trip is given by:
31 July 2021
COTM 4202 11
 Human and machine system suffer from
inherent delays due to reaction time and
capacity, say Td.
31 July 2021
COTM 4202 12
 For a given dumping time Td, the total cycle
time Th of the hauler is the sum of loading
time, travel time and damping time given by:
31 July 2021
COTM 4202 13
 Optimum number of haul units (N) is
determined by:
 NB: Rounding down will maximize haul unit
productivity.
31 July 2021
COTM 4202 14
 An 16 cubic meter dump truck has a loading
time of 3 min, a travel time of 7 min, and the
dumping and delay times of 5 min. Calculate
the cycle time of the hauler and optimum
number of hauling units.
31 July 2021
COTM 4202 15
 The daily standard production rate Pe of an
excavator is is given by:
 He is the operating hours per day
 Ce is the cycle capacity (in units of volume) of the
excavator
 Te is the cycle time (in hours) of the excavator
31 July 2021
COTM 4202 16
 The daily standard production rate Ph of a
hauler is given by:
 Rh is standard production rate
 Hh is the number of operating hours per day
31 July 2021
COTM 4202 17
 A 1.5 cubic meter front-end loader is going to load
dump trucks with a capacity of 9.0 cubic meter. The
loader takes 0.4 min to fill and load one bucket. The
travel time in the haul is 4.0 min. Dump and delay
times are 2.5 min combined. Calculate:
 The loading time,
 The cycle time of hauler,
 Number of trucks,
 The hourly production rate of haul units, and
 The hourly production of loader
31 July 2021
COTM 4202 18
 A power shovel with a dipper of one cubic
meter capacity has a standard operating
cycle time of 30 seconds. Find the daily
standard production rate of the shovel. Ce
= 1 cu. mtr., Te = 30 sec. and He = 8 hours.
31 July 2021
COTM 4202 19
 A dump truck with a capacity of 6 cubic meter is
used to dispose of excavated materials at a
dump site 4 km away. The average speed of the
dump truck is 30 mph and the dumping time is
30 seconds. Find the daily standard production
rate of the truck. If a fleet of dump trucks of 9
cubic meter capacity is used to dispose of the
excavated materials for 8 hours per day,
determine the number of trucks needed daily.
31 July 2021
COTM 4202 20
 Material properties have a direct effect on the ease or
difficulty of handling the material, on the selection of
equipment, and on equipment production rates.
 Quantities are often measured in volume units.
 Volume of material under different conditions varies
appreciably.
31 July 2021
COTM 4202 21
31 July 2021
COTM 4202 22
 Bank: Material in its natural state. Also called in-
place or in-situ. Measurement: BCM (Bank
Cubic Meter)
 Lose: material that has been excavated or
loaded. Measurement: LCM (Lose Cubic Meter)
 Compacted: Material after compaction:
Measurement: CCM (Compacted Cubic Meter)
Swell
Factor
Shrinkage
Factor
 The swell factor is the ratio of the loose dry
weight per unit volume to the bank dry weight per
unit volume.
Loose dry unit weight
Swell Factor (w) = _____________________
Bank dry unit weight
Swell% = ( 1/w – 1 )x100
 The shrinkage factor is the ratio of the compacted dry
weight per unit volume to the bank dry weight per unit
volume:
Compacted dry unit weight
Shrinkage Factor = _________________________
Bank dry unit weight
Shrinkage % = ( SrF – 1 )x100
31 July 2021
COTM 4202 23
31 July 2021
COTM 4202 24
 Let w denote the swell factor of the soil
 wPe denote the daily volume of loose
excavated materials.
 Then the approximate number of haulers
required to dispose of the excavated
materials is given by:
31 July 2021
COTM 4202 25
 Equipment productivities at job sites are influenced
by actual work conditions and a variety of
inefficiencies and work stoppages.
 Let F1, F2, ..., Fn, denote factors that lower
productivity, each of which is smaller than 1,
 Then the actual equipment productivity R' at the job
site can be related to the standard production
rate R as follows:
31 July 2021
COTM 4202 26
 The actual cycle time T' at the job site is
related to the standard cycle time T as:
31 July 2021
COTM 4202 27
 A power shovel with a dipper of 1.2 cubic meter
capacity has a standard production rate of 960
cubic meter for an 8-hour day. 4min is consumed to
fill and load. Determine the job site productivity and
the actual cycle time of this shovel under the work
conditions at the site that affects its productivity as
shown below:
 Work Conditions at the Site Factors
Bulk composition 0.954
Soil properties and water content 0.983
Equipment idle time for worker breaks 0.8
Management efficiency 0.7
31 July 2021
COTM 4202 28
 A dump truck with a capacity of 6 cubic meter is used to
dispose of excavated materials. The distance from the
dump site is 4km and the average speed of the dump
truck is 30 kph. The job site productivity of the power
shovel per day is 504 cubic meter, which will be
modified by a swell factor of 1.1. The only factors
affecting the job site productivity of the dump truck in
addition to those affecting the power shovel are 0.80 for
equipment idle time and 0.70 for management
efficiency. Determine the job site productivity of the
dump truck. If a fleet of such trucks is used to haul the
excavated material, find the number of trucks needed
daily.
31 July 2021
COTM 4202 29
 A front-end loader loads a fleet of dump trucks (capacity
18 loose cubic meter each), which haul the earth to a fill
where it is compacted with a shrinkage factor of 10%.
The earth has a percent swell of 20%. The job requires
a volume of 18,000 compacted cubic meter. Distance
between quarry and project site is 5miles connected
with dirt track.
 How many hours will be required to excavate and haul
the material to the fill.
31 July 2021
COTM 4202 30
THANK YOU!
31 July 2021
COTM 4202
31

More Related Content

PPTX
Use of Integrated loader dumper over Shovel dumper combination
PPTX
Analysing shovel dumper productivity for coal mine
PPT
Transport & digging capacity calculation
PDF
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
PDF
Sachpazis: Strip Foundation Analysis and Design example (EN1997-1:2004)
PPTX
Horizontal Wind Turbine
PDF
Sachpazis pile analysis & design, in accordance with en 1997 1-2004
PPTX
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Use of Integrated loader dumper over Shovel dumper combination
Analysing shovel dumper productivity for coal mine
Transport & digging capacity calculation
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Sachpazis: Strip Foundation Analysis and Design example (EN1997-1:2004)
Horizontal Wind Turbine
Sachpazis pile analysis & design, in accordance with en 1997 1-2004
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

What's hot (12)

PDF
Sachpazis_CHS Column base plate to EC3 1993-1 with NA CEN
PDF
92795289 building-data
PDF
Sachpazis: Sloped rear face retaining wall example
PPTX
The productivity of lhd in underground coal mines
PDF
Masonry Wall Panel Analysis & Design, In accordance with EN1996-1-1:2005
PDF
Sachpazis: Wind Loading Analysis & Design for a Hipped Roof Example According...
PDF
Sachpazis Steel Member Analysis & Design (EN1993 1-1 2005)
PDF
Sachpazis" Analysis of Geogrid Reinforced Earth Slope Stability & Capacity
PDF
Sachpazis reinforced masonry retaining wall analysis & design, in accordance ...
PPTX
Gtl hi lite - A Case on Simenggaris and Bengara PSC - Indonesia
PDF
Sachpazis_Pocket reinforced masonry retaining wall analysis exampleEN1997-1-2004
PDF
Sachpazis gabion retaining wall analysis & design bs8002-1994
Sachpazis_CHS Column base plate to EC3 1993-1 with NA CEN
92795289 building-data
Sachpazis: Sloped rear face retaining wall example
The productivity of lhd in underground coal mines
Masonry Wall Panel Analysis & Design, In accordance with EN1996-1-1:2005
Sachpazis: Wind Loading Analysis & Design for a Hipped Roof Example According...
Sachpazis Steel Member Analysis & Design (EN1993 1-1 2005)
Sachpazis" Analysis of Geogrid Reinforced Earth Slope Stability & Capacity
Sachpazis reinforced masonry retaining wall analysis & design, in accordance ...
Gtl hi lite - A Case on Simenggaris and Bengara PSC - Indonesia
Sachpazis_Pocket reinforced masonry retaining wall analysis exampleEN1997-1-2004
Sachpazis gabion retaining wall analysis & design bs8002-1994
Ad

More from Delhi Technological University (20)

PPT
Chapter 6- Contract Management
PPT
Chapter 5- Contract Management
PPT
Chapter 4- Contract Management
PPT
Chapter 3- Contract Management
PPT
Chapter 2- Contract Management
PPT
Chapter 1- Procurement management
PPT
Chapter 3- Construction Law
PPT
Chapter 2- Construction Law
PPT
Chapter 1-Construction Law
PPT
Chapter 5- Lecture
PPT
Chapter 4- Lecture
PPT
Chapter 2- Lecture
PPT
Chapter 1- Lecture
PDF
Construction equipment management chapter 5
PDF
Construction equipment management chapter 4
PDF
Construction equipment management chapter 3
PDF
Construction equipment management chapter 2
PDF
Construction equipment management chapter 1pdf
PDF
Chapter 5 [compatibility mode]
Chapter 6- Contract Management
Chapter 5- Contract Management
Chapter 4- Contract Management
Chapter 3- Contract Management
Chapter 2- Contract Management
Chapter 1- Procurement management
Chapter 3- Construction Law
Chapter 2- Construction Law
Chapter 1-Construction Law
Chapter 5- Lecture
Chapter 4- Lecture
Chapter 2- Lecture
Chapter 1- Lecture
Construction equipment management chapter 5
Construction equipment management chapter 4
Construction equipment management chapter 3
Construction equipment management chapter 2
Construction equipment management chapter 1pdf
Chapter 5 [compatibility mode]
Ad

Recently uploaded (20)

PDF
IAE-V2500 Engine Airbus Family A319/320
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PPTX
Research Writing, Mechanical Engineering
PPTX
Unit IImachinemachinetoolopeartions.pptx
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
PDF
THE PEDAGOGICAL NEXUS IN TEACHING ELECTRICITY CONCEPTS IN THE GRADE 9 NATURAL...
PPT
Basics Of Pump types, Details, and working principles.
PDF
electrical machines course file-anna university
PPTX
Software-Development-Life-Cycle-SDLC.pptx
PPTX
chapter 1.pptx dotnet technology introduction
PPTX
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
PDF
Module 1 part 1.pdf engineering notes s7
PPTX
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
PPTX
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
PDF
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
DOCX
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
PDF
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
PDF
25AF1191PC303 MODULE-1 CHAIN SURVEYING SEMESTER III SURVEYING
PDF
Using Technology to Foster Innovative Teaching Practices (www.kiu.ac.ug)
IAE-V2500 Engine Airbus Family A319/320
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
Research Writing, Mechanical Engineering
Unit IImachinemachinetoolopeartions.pptx
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
THE PEDAGOGICAL NEXUS IN TEACHING ELECTRICITY CONCEPTS IN THE GRADE 9 NATURAL...
Basics Of Pump types, Details, and working principles.
electrical machines course file-anna university
Software-Development-Life-Cycle-SDLC.pptx
chapter 1.pptx dotnet technology introduction
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
Module 1 part 1.pdf engineering notes s7
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
25AF1191PC303 MODULE-1 CHAIN SURVEYING SEMESTER III SURVEYING
Using Technology to Foster Innovative Teaching Practices (www.kiu.ac.ug)

Chapter 3- Lecture

  • 2. General Definition  It is the number of units and the size of equipment that would permit the constructor to accomplish the activity with a duration resulting in the lowest cost.  Estimating and planning involves the judicious selection of equipment, the careful scheduling of time and resources, and the accurate determination of expected system output and cost. 31 July 2021 2 COTM 4202
  • 3.  Haul unit horsepower  Haul road rolling resistance  Haul road grades  Haul unit loaded and empty weight  Haul unit transmission characteristics  Haul unit loading time  Haul unit travel time  Haul unit delay time  Altitude of the project site 31 July 2021 COTM 4202 3
  • 4.  Total power that an engine is capable of generating is expressed as its horsepower.  Available horsepower is power that is available to perform work after taking into account losses and consumption in other machine functions.  Rimpull is defined as the tractive force between the driving wheels and the surface on which they travel.( V is velocity in mph) 31 July 2021 COTM 4202 4
  • 5. 31 July 2021 COTM 4202 5 Power generated by engine Drawbar Pull Rolling Resistance Rimpull
  • 6.  Rolling resistance is resistance offered to movement of materials on a plain surface; often expressed in pounds per ton of materials.  Rolling Resistance depends upon: 31 July 2021 COTM 4202 6
  • 8. 31 July 2021 COTM 4202 8  The force-opposing movement of a machine up a frictionless slope is grade resistance.  The effect of gravitational force in aiding movement of a vehicle down a slope is grade assistance. F= 20 lbs/ G% per Ton
  • 9.  The cycle capacity C of a piece of equipment is defined as the number of output units per cycle of operation under standard work conditions.  The standard production rate R of a piece of construction equipment is defined as the number of output units per unit time.  The cycle time T refers to units of time per cycle of operation. 31 July 2021 COTM 4202 9
  • 10.  Time to load a mover for load shifting will determine loads that can be transferred. Longer loading time lesser will be productivity.  To is loading time  Te is cycle time for loader/excavator  Ch is capacity of a hauler (dump truck)  Ce loading rate/capacity of loader 31 July 2021 COTM 4202 10
  • 11.  It is time for moving load from production site to disposal site. Longer time will reduce productivity.  To determine the productivity of a hauler, › Let: D be the distance from source to a dump site, S be the average speed of the hauler, Tt be the travel time for the round trip to the dump site, To be the loading time, Td be the dumping time plus other delays.  Then the travel time for the round trip is given by: 31 July 2021 COTM 4202 11
  • 12.  Human and machine system suffer from inherent delays due to reaction time and capacity, say Td. 31 July 2021 COTM 4202 12
  • 13.  For a given dumping time Td, the total cycle time Th of the hauler is the sum of loading time, travel time and damping time given by: 31 July 2021 COTM 4202 13
  • 14.  Optimum number of haul units (N) is determined by:  NB: Rounding down will maximize haul unit productivity. 31 July 2021 COTM 4202 14
  • 15.  An 16 cubic meter dump truck has a loading time of 3 min, a travel time of 7 min, and the dumping and delay times of 5 min. Calculate the cycle time of the hauler and optimum number of hauling units. 31 July 2021 COTM 4202 15
  • 16.  The daily standard production rate Pe of an excavator is is given by:  He is the operating hours per day  Ce is the cycle capacity (in units of volume) of the excavator  Te is the cycle time (in hours) of the excavator 31 July 2021 COTM 4202 16
  • 17.  The daily standard production rate Ph of a hauler is given by:  Rh is standard production rate  Hh is the number of operating hours per day 31 July 2021 COTM 4202 17
  • 18.  A 1.5 cubic meter front-end loader is going to load dump trucks with a capacity of 9.0 cubic meter. The loader takes 0.4 min to fill and load one bucket. The travel time in the haul is 4.0 min. Dump and delay times are 2.5 min combined. Calculate:  The loading time,  The cycle time of hauler,  Number of trucks,  The hourly production rate of haul units, and  The hourly production of loader 31 July 2021 COTM 4202 18
  • 19.  A power shovel with a dipper of one cubic meter capacity has a standard operating cycle time of 30 seconds. Find the daily standard production rate of the shovel. Ce = 1 cu. mtr., Te = 30 sec. and He = 8 hours. 31 July 2021 COTM 4202 19
  • 20.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials at a dump site 4 km away. The average speed of the dump truck is 30 mph and the dumping time is 30 seconds. Find the daily standard production rate of the truck. If a fleet of dump trucks of 9 cubic meter capacity is used to dispose of the excavated materials for 8 hours per day, determine the number of trucks needed daily. 31 July 2021 COTM 4202 20
  • 21.  Material properties have a direct effect on the ease or difficulty of handling the material, on the selection of equipment, and on equipment production rates.  Quantities are often measured in volume units.  Volume of material under different conditions varies appreciably. 31 July 2021 COTM 4202 21
  • 22. 31 July 2021 COTM 4202 22  Bank: Material in its natural state. Also called in- place or in-situ. Measurement: BCM (Bank Cubic Meter)  Lose: material that has been excavated or loaded. Measurement: LCM (Lose Cubic Meter)  Compacted: Material after compaction: Measurement: CCM (Compacted Cubic Meter)
  • 23. Swell Factor Shrinkage Factor  The swell factor is the ratio of the loose dry weight per unit volume to the bank dry weight per unit volume. Loose dry unit weight Swell Factor (w) = _____________________ Bank dry unit weight Swell% = ( 1/w – 1 )x100  The shrinkage factor is the ratio of the compacted dry weight per unit volume to the bank dry weight per unit volume: Compacted dry unit weight Shrinkage Factor = _________________________ Bank dry unit weight Shrinkage % = ( SrF – 1 )x100 31 July 2021 COTM 4202 23
  • 24. 31 July 2021 COTM 4202 24
  • 25.  Let w denote the swell factor of the soil  wPe denote the daily volume of loose excavated materials.  Then the approximate number of haulers required to dispose of the excavated materials is given by: 31 July 2021 COTM 4202 25
  • 26.  Equipment productivities at job sites are influenced by actual work conditions and a variety of inefficiencies and work stoppages.  Let F1, F2, ..., Fn, denote factors that lower productivity, each of which is smaller than 1,  Then the actual equipment productivity R' at the job site can be related to the standard production rate R as follows: 31 July 2021 COTM 4202 26
  • 27.  The actual cycle time T' at the job site is related to the standard cycle time T as: 31 July 2021 COTM 4202 27
  • 28.  A power shovel with a dipper of 1.2 cubic meter capacity has a standard production rate of 960 cubic meter for an 8-hour day. 4min is consumed to fill and load. Determine the job site productivity and the actual cycle time of this shovel under the work conditions at the site that affects its productivity as shown below:  Work Conditions at the Site Factors Bulk composition 0.954 Soil properties and water content 0.983 Equipment idle time for worker breaks 0.8 Management efficiency 0.7 31 July 2021 COTM 4202 28
  • 29.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials. The distance from the dump site is 4km and the average speed of the dump truck is 30 kph. The job site productivity of the power shovel per day is 504 cubic meter, which will be modified by a swell factor of 1.1. The only factors affecting the job site productivity of the dump truck in addition to those affecting the power shovel are 0.80 for equipment idle time and 0.70 for management efficiency. Determine the job site productivity of the dump truck. If a fleet of such trucks is used to haul the excavated material, find the number of trucks needed daily. 31 July 2021 COTM 4202 29
  • 30.  A front-end loader loads a fleet of dump trucks (capacity 18 loose cubic meter each), which haul the earth to a fill where it is compacted with a shrinkage factor of 10%. The earth has a percent swell of 20%. The job requires a volume of 18,000 compacted cubic meter. Distance between quarry and project site is 5miles connected with dirt track.  How many hours will be required to excavate and haul the material to the fill. 31 July 2021 COTM 4202 30