PRE-COMMISSIONING &
      COMMISSIONING

             A discussion on
             Pre-commissioning /
             Commissioning &
             Start Up of Projects




1
Contents

       Objective
       Common work at process plant at pipe
        line
       Definition of Mechanical Completion
       Pre-Commissioning Definition and
        Procedure

2
Contents(Continued)

       Activities (Piping & vessels, Mechanical,
        Electrical, Instrumentation, Operations)
       Check Sheets
       Punch Listing
       Completion Activities



3
Objectives


       Start-up and hand-over of the completed

        plant to the Client.

       To support client in operation of plant



                               .
4
COMMISSIONING
                                    & START-UP




MECHANICAL
COMPLETION
                                                    SYSTEM /   OPERATION
Inclusive of                        PLANT
                    COMMISSIONING                   PACKAGE    STAFF
Pre-commissioning                   START-UP
                                                    HANDOVER   TRAINING
Activities




                                                                           5
Commissioning Works
                       At Process Plants
        PIPING / VESSEL                                       ELECT / INSTRUM
•Flushing/Blowing                                      •Preliminary Check
•Chemical Cleaning                                     •Calibration
•Reinstatement                                         •Circuitry Check
•Gross leak with N2                                    •Continuity Check
•Drying                                                •Loop Test
•Inerting                                              • Energization (Power Up)
•Hydrocarbon In                                        •Performance Tests

                                MANAGEMENT
                          •Systems Breakdown
                          •Preparation of Procedures
                          •Loop Folder
                          •Circuit Folder
                          •Test Packs
                                                            CONTROL SYSTEM
    ROTATING EQUIPMENT                                 •SCADA / PCS SAT
•Alignment                                             •Fire & Gas System
•Belt Tensioning                                       •Safety Shutdown Sys.
•Motor Run in Test                                     •Alarm Set-Up & Test
•Vibration Test                                        •Simulation Test

                                                                                   6
Commissioning Works
                  At Pipe Lines
      PRECOMMISSIONING       SPECIALIZED PIPELINE CLEANING
•Cleaning                    •Dewaxing
•Flooding                    •Descaling
•Hydro testing               •De-oiling
•Dewatering & Drying         •Pit cleaning
•Flushing                    •Chemical cleaning
•Nitrogen Inserting          •Combined cleaning methods




     ASSOCIATED SERVICES           PIPELINE INSPECTION
•Temporary pipeline repair   •Geometry inspection
•On-site supervision         •Metal loss inspection
•Cathodic protection         •Crack detection
•Hot tapping & stoppling     •Leak detection and location
•Flow assurance Etc.         •Profile monitoring and mapping

                                                               7
Definition of Mechanical Completion
        & Construction Completion

       Mechanical Completion: A series of
        activities that MUST be completed prior to
        the commencement of Commissioning and
        Start-up of a Utility System or Main Process
        Unit.
       Mechanical Completion ALSO includes
        ALL pre-commissioning activities.

8
Pre-Commissioning Overview

       Process: Confirmation of Loops
        according to P& ID’s
       Vessels: Internal Inspection & Box up
       Piping: Hydro testing, reinstatement &
        verification of main gaskets.
       Stationary Equipment: Tightening and
        Final Box Up.
       Rotary Equipment: Leveling, Rotation,
9       Alignment & lubrications
Pre-Commissioning Activities –
                    Piping & Vessels

        Field checks as per isometrics and P&ID’s

        Verification of hydro testing

        Verification of flushing , blowing & drying

        Internal inspection of equipment as
         required

10
Pre-Commissioning Activities –
           Piping & Vessels(Continued)

        Verification of Internals
        Re-instatement of all flanges, control
         value, orifices, Psv’s and steam traps.
        Verification of blinds / spades installation
         and / or removal
        Box up: Pre-commissioned and closed



11
Pre-Commissioning Activities –
     Mechanical Discipline

        Verification of coupling and belt
         alignment

        Pumps / compressor checks

        Bearing lubrications

        Inspection / checking of filters & strainers

12
Pre-Commissioning Activities –
     Electrical Discipline

      MCC & UPS installation
      Field electrical installation
       – Cable Meggering (Continuity)
       – Termination of wiring; end devices
         to JB’s & MCC
       – Termination & Glanding according
         to area classification.

13
Pre-Commissioning Activities –
     Electrical Discipline(Continued)


        Motor installation

         –   Resistance maggering

         –   Rotation confirmation

         –   No load test run

14
Pre-Commissioning Activities -
                Instrumentation

        Instrument installation checks
        PSV calibration
        Calibration of transmitters and switches
        Loop checking of device end to PLC
        Function testing of PLC & ESD systems


15
Pre-Commissioning Check Sheets

        Vessel & Piping Check Sheets

        Mechanical Check Sheets

        Electrical Check Sheets

        Instrumentation Check Sheets


16      Operation / Process Check Sheets
Punch Listing

        Punch Lists are created and sorted as per disciplines
          – Piping and Vessels
          – Mechanical
          – Electrical
          – Instrumentation
          – Operations
        Punch Lists are categorized on a priority basis
          – Category “A”; MUST be completed prior to
             Commissioning
          – Category “B”; MUST be completed prior to Start-up
          – Category “C”; Signifies end of job
        Construction Contractor MUST have a coordinated
         management plan of Punch Listing including categorizing
         of punch list items
17
Completion Activities

        Flushing Blowing Certificates
        Box Up Certificate
        Mechanical Completion Certificate for
         each Utility and Process Unit
        Handover Certificate


18
COMMISSIONING

        Definition

        Utility Description

        Commissioning Activities

        Check Sheets

        Commissioning / Start Up Procedure
19
Systems Description

     Commissioning of The Following Systems
      Air Compression System

        MCC & Plant Lighting System
        UPS, PLC & Plant ESD System
        Fire Water System
        Fire & Gas Detection System


20
Systems Description

        Instrument Air Package
        Inert Gas Package
        Fuel Gas System
        Closed Drain & Waste Water Systems
        Condensate Transfer System
        Process Units; Reactor

21
Commissioning Check Sheets

        Commissioning check sheets are given in
         the Commissioning Protocol.




22
START-UP OF PROCESS UNITS

        Utilities in Service
        Introduction of Raw material (Vacuum Residue
         Feed)
        Introduction of Process Air & Steam
        Production of required grades of products
        Maintaining required proportion of off gases as
         per specs
        Achievement of required steam temperature
        Obtaining steam temperature compatible to
         system steam temperature.

23
Issues for Discussion.


        Less re-work SS304, 304L

        Carbon filter back flow

        Go for the standard packages

        15 KM pipeline

24
THANK YOU



25

More Related Content

PDF
World Class Manufacturing:Plant Start Up and Commissioning Procedure
PDF
Precommisioning and commissioning updated
PDF
Precommissioning and Commissioning
PDF
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PPTX
Commissioning of Offshore Installations
DOCX
Mechanical completion
PPS
Mechanical Completions
PDF
Process Plant Start Up and Commissioning
World Class Manufacturing:Plant Start Up and Commissioning Procedure
Precommisioning and commissioning updated
Precommissioning and Commissioning
PetroSync - Pre-Commissioning, Commissioning and Start-Up
Commissioning of Offshore Installations
Mechanical completion
Mechanical Completions
Process Plant Start Up and Commissioning

What's hot (20)

PDF
Static equipment in oil and gas industry
PDF
Oil & Gas Engineering
DOC
Commissioning Supervisor New
PDF
110921 commissioning of offshore installations
DOCX
495265750-Hydro-Test-Procedure.docx
DOC
Pr 1159 - commissioning and start-up procedure
DOCX
CV Oil and Gas Field Operator Nishanth P Joy
PDF
Karthik Resume
DOCX
Instrument Technician
DOCX
Cv Piping Engineer
PDF
Erection guidelinesfor500mw boilerpressureparts
PPTX
Process Related, Mechanical and Piping Workshop by Technip
PDF
Mechanical completion
DOC
AJITHKUMAR -Lead Production Operator
PPTX
Piping Hydrostatic Test / Hydrotesting
PDF
GAS TURBINE MAJOR INSPECTION
DOC
CV of Pradip Saha_CEng MIGEM Senior Process Engineer 2015
PPT
Pre commissioning steam turbines load trial
PPT
Hydrotest
Static equipment in oil and gas industry
Oil & Gas Engineering
Commissioning Supervisor New
110921 commissioning of offshore installations
495265750-Hydro-Test-Procedure.docx
Pr 1159 - commissioning and start-up procedure
CV Oil and Gas Field Operator Nishanth P Joy
Karthik Resume
Instrument Technician
Cv Piping Engineer
Erection guidelinesfor500mw boilerpressureparts
Process Related, Mechanical and Piping Workshop by Technip
Mechanical completion
AJITHKUMAR -Lead Production Operator
Piping Hydrostatic Test / Hydrotesting
GAS TURBINE MAJOR INSPECTION
CV of Pradip Saha_CEng MIGEM Senior Process Engineer 2015
Pre commissioning steam turbines load trial
Hydrotest
Ad

Viewers also liked (9)

PPTX
Petrolium and gas processing
PPTX
Hydrocarbon preeti bhatt
PPTX
Commissioning Plan Robert Thelander, Svenska kraftnät
PPTX
Hydrocarbons
PPTX
Hydrocarbons
PDF
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
PPTX
Power Point On Hydrocarbon
PPTX
The Future of Leadership Development
PDF
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
Petrolium and gas processing
Hydrocarbon preeti bhatt
Commissioning Plan Robert Thelander, Svenska kraftnät
Hydrocarbons
Hydrocarbons
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Power Point On Hydrocarbon
The Future of Leadership Development
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
Ad

Similar to Commissioning & Interface With Engineering (20)

PPTX
PEMBAHASAN RENCANA PCSU - SCHEDULE MANPOWER DLL.pptx
PDF
369051174-Basic-of-Commissioning.pdf
PPTX
Episode 22 : PROJECT EXECUTION
DOC
Capability initial flow control
PDF
Mind map the_9_key_elements_video_05_pre-commissioning
PDF
PDF
Episode 34 : Project Execution Part (5)
DOC
Cv of nilesh rk
DOC
Bogdan tudor cv
PDF
NewSTS Brochure
PPT
Aims presentation on Western Region NACE Conference at Victoria 2013
PPT
Bogdan Mircea Tomescu Presentation
PDF
Pre commissioning and Commissioning Safety.pdf
PPTX
Presentation1
PPTX
FUNDAMENTAL COMMISSIONING AND START-UP_23112024.pptx
DOCX
PDF
commissioning.pdf
DOCX
Piping System Internal Cleaning criteria.docx
DOCX
SENTHIL PANDIAN CV
DOC
ICS ENGINEER CV WITH IMAGE (doc)
PEMBAHASAN RENCANA PCSU - SCHEDULE MANPOWER DLL.pptx
369051174-Basic-of-Commissioning.pdf
Episode 22 : PROJECT EXECUTION
Capability initial flow control
Mind map the_9_key_elements_video_05_pre-commissioning
Episode 34 : Project Execution Part (5)
Cv of nilesh rk
Bogdan tudor cv
NewSTS Brochure
Aims presentation on Western Region NACE Conference at Victoria 2013
Bogdan Mircea Tomescu Presentation
Pre commissioning and Commissioning Safety.pdf
Presentation1
FUNDAMENTAL COMMISSIONING AND START-UP_23112024.pptx
commissioning.pdf
Piping System Internal Cleaning criteria.docx
SENTHIL PANDIAN CV
ICS ENGINEER CV WITH IMAGE (doc)

Commissioning & Interface With Engineering

  • 1. PRE-COMMISSIONING & COMMISSIONING A discussion on Pre-commissioning / Commissioning & Start Up of Projects 1
  • 2. Contents  Objective  Common work at process plant at pipe line  Definition of Mechanical Completion  Pre-Commissioning Definition and Procedure 2
  • 3. Contents(Continued)  Activities (Piping & vessels, Mechanical, Electrical, Instrumentation, Operations)  Check Sheets  Punch Listing  Completion Activities 3
  • 4. Objectives  Start-up and hand-over of the completed plant to the Client.  To support client in operation of plant . 4
  • 5. COMMISSIONING & START-UP MECHANICAL COMPLETION SYSTEM / OPERATION Inclusive of PLANT COMMISSIONING PACKAGE STAFF Pre-commissioning START-UP HANDOVER TRAINING Activities 5
  • 6. Commissioning Works At Process Plants PIPING / VESSEL ELECT / INSTRUM •Flushing/Blowing •Preliminary Check •Chemical Cleaning •Calibration •Reinstatement •Circuitry Check •Gross leak with N2 •Continuity Check •Drying •Loop Test •Inerting • Energization (Power Up) •Hydrocarbon In •Performance Tests MANAGEMENT •Systems Breakdown •Preparation of Procedures •Loop Folder •Circuit Folder •Test Packs CONTROL SYSTEM ROTATING EQUIPMENT •SCADA / PCS SAT •Alignment •Fire & Gas System •Belt Tensioning •Safety Shutdown Sys. •Motor Run in Test •Alarm Set-Up & Test •Vibration Test •Simulation Test 6
  • 7. Commissioning Works At Pipe Lines PRECOMMISSIONING SPECIALIZED PIPELINE CLEANING •Cleaning •Dewaxing •Flooding •Descaling •Hydro testing •De-oiling •Dewatering & Drying •Pit cleaning •Flushing •Chemical cleaning •Nitrogen Inserting •Combined cleaning methods ASSOCIATED SERVICES PIPELINE INSPECTION •Temporary pipeline repair •Geometry inspection •On-site supervision •Metal loss inspection •Cathodic protection •Crack detection •Hot tapping & stoppling •Leak detection and location •Flow assurance Etc. •Profile monitoring and mapping 7
  • 8. Definition of Mechanical Completion & Construction Completion  Mechanical Completion: A series of activities that MUST be completed prior to the commencement of Commissioning and Start-up of a Utility System or Main Process Unit.  Mechanical Completion ALSO includes ALL pre-commissioning activities. 8
  • 9. Pre-Commissioning Overview  Process: Confirmation of Loops according to P& ID’s  Vessels: Internal Inspection & Box up  Piping: Hydro testing, reinstatement & verification of main gaskets.  Stationary Equipment: Tightening and Final Box Up.  Rotary Equipment: Leveling, Rotation, 9 Alignment & lubrications
  • 10. Pre-Commissioning Activities – Piping & Vessels  Field checks as per isometrics and P&ID’s  Verification of hydro testing  Verification of flushing , blowing & drying  Internal inspection of equipment as required 10
  • 11. Pre-Commissioning Activities – Piping & Vessels(Continued)  Verification of Internals  Re-instatement of all flanges, control value, orifices, Psv’s and steam traps.  Verification of blinds / spades installation and / or removal  Box up: Pre-commissioned and closed 11
  • 12. Pre-Commissioning Activities – Mechanical Discipline  Verification of coupling and belt alignment  Pumps / compressor checks  Bearing lubrications  Inspection / checking of filters & strainers 12
  • 13. Pre-Commissioning Activities – Electrical Discipline  MCC & UPS installation  Field electrical installation – Cable Meggering (Continuity) – Termination of wiring; end devices to JB’s & MCC – Termination & Glanding according to area classification. 13
  • 14. Pre-Commissioning Activities – Electrical Discipline(Continued)  Motor installation – Resistance maggering – Rotation confirmation – No load test run 14
  • 15. Pre-Commissioning Activities - Instrumentation  Instrument installation checks  PSV calibration  Calibration of transmitters and switches  Loop checking of device end to PLC  Function testing of PLC & ESD systems 15
  • 16. Pre-Commissioning Check Sheets  Vessel & Piping Check Sheets  Mechanical Check Sheets  Electrical Check Sheets  Instrumentation Check Sheets 16  Operation / Process Check Sheets
  • 17. Punch Listing  Punch Lists are created and sorted as per disciplines – Piping and Vessels – Mechanical – Electrical – Instrumentation – Operations  Punch Lists are categorized on a priority basis – Category “A”; MUST be completed prior to Commissioning – Category “B”; MUST be completed prior to Start-up – Category “C”; Signifies end of job  Construction Contractor MUST have a coordinated management plan of Punch Listing including categorizing of punch list items 17
  • 18. Completion Activities  Flushing Blowing Certificates  Box Up Certificate  Mechanical Completion Certificate for each Utility and Process Unit  Handover Certificate 18
  • 19. COMMISSIONING  Definition  Utility Description  Commissioning Activities  Check Sheets  Commissioning / Start Up Procedure 19
  • 20. Systems Description Commissioning of The Following Systems  Air Compression System  MCC & Plant Lighting System  UPS, PLC & Plant ESD System  Fire Water System  Fire & Gas Detection System 20
  • 21. Systems Description  Instrument Air Package  Inert Gas Package  Fuel Gas System  Closed Drain & Waste Water Systems  Condensate Transfer System  Process Units; Reactor 21
  • 22. Commissioning Check Sheets  Commissioning check sheets are given in the Commissioning Protocol. 22
  • 23. START-UP OF PROCESS UNITS  Utilities in Service  Introduction of Raw material (Vacuum Residue Feed)  Introduction of Process Air & Steam  Production of required grades of products  Maintaining required proportion of off gases as per specs  Achievement of required steam temperature  Obtaining steam temperature compatible to system steam temperature. 23
  • 24. Issues for Discussion.  Less re-work SS304, 304L  Carbon filter back flow  Go for the standard packages  15 KM pipeline 24