CONSTRUCTION AND DESIGN OF
MULTISTOREY BUILDING
AT
UNITECH LTD
SUBMITTED BY: UNDER THE GUINDANCE OF
ABHIMANYU PARIDA RAJIV GUPTA
1040241 FACULTY COORDINATOR
construction and design of multistorey building by abhimanyu parida.ppt
Projects Undertaken
1. Construction of residential building (escape)
1.1 Excavation, Layout and Foundation
1.2 Column layout, shuttering and casting
1.3 Slab, Beam shuttering and casting
1.4 Important Components
2. Introduction to bonded slab post tensioning
2.1 Post tensioning
2.2 benefits
2.3 Tendons and stressing
Projects Undertaken
3. Design of building component
3.1 Formwork design
3.2 Staircase design
3.3 Deep Beams
3.4 Slabs
construction and design of multistorey building by abhimanyu parida.ppt
Excavation, Layout and Foundation
 Excavation is a process of making trenches by digging up
of earth for the construction of foundations and
basements.
 Excavation level at escape site is 219.825 mm
 Excavation is done by the JCB on the hourly basis
 After the excavation the surface is leveled called surface
dressing
 Layout is done on the PCC poured over leveled surface.
 Column and foundation (raft ) steel is then laid as per
drawings.
Points to take care:-
 layout should be checked properly.
 Check any difference between architectural and structural
drawings regarding location of column.
 After excavation check the stability of temporary structures built
near the excavated ground.
 Before laying raft reinforcement, shuttering wall which is mainly
brick wall should be built and should be filled with soil on other
side.
 Check the direction of chair bars in the raft
EXCAVATION
LAYOUT
RAFT FOUNDATION
COULMN CASTING
 On the raft the column layout is done.
 Layout for starter.
 The column ties and link bars are provided as per column
reinforcement drawings and general specifications.
 Displacement of main bars should be provided with L bar
 The plumb of formwork should be checked.
 Height of cast should be calculated accurately.
 Avoid caps as far as possible.
LAYOUT , PEDESTAL & STARTER
LINKS & TIES
PLUMB & FORMWORK, CASTING,CURING
SLAB, BEAM SHUTTERING & CASTING
 beam bottom is first laid on the column and then slab formwork
is laid
 After the reinforcement, the slab is checked for steel as per
drawings and level required.
 A camber of 5 mm in provided in the center of slab.
 Casting of slab should be discontinue at l/3 from the support.
SLAB STAGES
IMPORTANT COMPONENTS
 Key in column
 Water bar
 Binding materials
 Expansion joint
KEY IN COLUMN
 since the height of column is very large,
hence it is not possible to cast the column at
one time, to cast the column later the key is
made at the junction so that the proper bond
between the old concrete and new concrete is
formed.
KEY IN COLUMN
EXPANSION JOINT
 Since concrete is subjected to volume change. Provision must
be made to cater for the volume change by way of joint to
relieve the stresses produced.
 Expansion joint is function of length
 Buildings longer than 45 m are generally provided with one or
more expansion joints.
 Material used as expansion joint material is armour board
whose thickness is 25 mm.
EXPANSION JOINT
 Expansion joint
material, size is 25 mm
 Expansion joint in
building
WATER BAR
 Water bar is provided in the retaining wall o
that the moisture can’t move from the soil to
the joint. Water bar is basically provided at
the constructions joints of retaining wall of two
different towers
WATER BAR
BINDING MATERIALS
 Since the thermal expansion of concrete is different from that of
masonry. The interface between the concrete and the masonry is
liable to crack. To avoid this crack the chicken wire mesh is used to
avoid the crack and also provides the better grip for Masonry with
concrete.
 Similarly when the drainage pipes are laid along with the outer wall
then again the connection between the pipe and the wall has
different coefficient of temperature change hence they are joint to
the concrete by lead keys.
 In the toilets and kitchen sunken portion the joints in any case are
packed by water proof and non shrinkable material.
BINDING MATERIALS
 Chicken wire mesh between
brick masonry and concrete
 Connection of pipes with
concrete
 Chicken wire mesh in
conduits through concrete
WATER PROOFING
 Water proofing has remained as an unsolved complex problem
 Use of plasticizers, super plasticizers, air-entraining agents
helps in reducing the permeability of concrete by reducing the
requirement of mixing water, hence can be also be regarded as
waterproof material.
 Some of approved water-proofing compound by the company
are:- pidilite, cico, fosroe, baushimine, unitile.
 Water-proofing cement paint:- super snoweem
WATER PROOFING
 Water proofing in sunken
portion of kitchen and
bathroom
 WP in sunken portion at
ground level
 WP in retaining wall
WATER PROOFING IN GARDEN AREA
 For water proofing in garden area the soil is first leveled and
then rammed to achieve the maximum density
 The PCC is then laid down mixed with tape Crete (a water
proofing compound)
 After PCC the plaster of fibrous material is done.
 the bituminous sheets are laid by heating it with the welder. On
those sheets the drainage pipes are laid down with suitable
slope and these pipes are covered with geo-fabric sheets.
 Again the plaster is done. On the plaster the 40 mm aggregates
are laid.
 On the aggregate the geo-fabric sheets are laid down on which
the sand is placed & on the sand the soil ,along with fertilizers,
is placed on which the gardening is done for the non tower area.
WATER PROOFING IN GARDEN AREA
 Sandy soil
 PCC mixed with tape
Crete (water proof
compound)
 Texas (bitumen) sheet
 Drainage pipe
 40 mm aggregate
 Geo-fabric sheet
 Sand
construction and design of multistorey building by abhimanyu parida.ppt
INTRODUCTION/BENEFITS
 Post-tensioning is a method of reinforcing (strengthening)
concrete or other materials with high-strength steel strands or
bars, typically referred to as tendons
 allows longer clear spans, thinner slabs
 lower overall building height for the same floor-to-floor height.
 allows a high degree of flexibility in the column layout, span
lengths and ramp configurations
POST TENSIONING
PLACEMENT OF TENDONS
 Positioning and fixing of casting and block-outs to the edge formwork
or construction joint formwork
 The support bars shall be prepared in advance.
 Lay tendons according to tendon layout in accordance with the
drawings.
 Fix tendons to correct profiles with support bars and chairs and the
tendons are made with provisions for grouting using grout using grout
vents and grout hoses
 Prepare installation report for every installation as per the enclosed
format.
 tolerance of tendon profiles is recommended as follows:
 **vertical: + 5 mm (at lowest and highest points)
 Horizontal: + 100 mm
construction and design of multistorey building by abhimanyu parida.ppt
LOADS ON FALSEWORK
Loads on Falsework are any combinations of
the following:
 Dead loads,
 Imposed loads,
 Environmental loads,
 Incidental loads during erection and
operation, and
 Lateral pressure.
DIFFERENT LOAD DATA
 Self load shall be determined by either actual measurement or in
accordance with IS 875 (Part I) the unit weight of wet concrete including
reinforcement shall be taken as 26 kN/m². However, in absence of the
data, load may be assumed as 500 N/M2 for the purpose of initial
calculations .
 Loads during constructional operation shall constitute the imposed
loads [see IS 875 (Part 2 ) Where allowance has only to be made for
access and inspection purposes, a loading of 750 N/m² should be
adequate
 The lateral pressure due to fresh concrete depends on the temperature
of concrete as placed, the rate of placing of concrete and the concrete
mix proportion
 Wind loads should be taken for design in accordance with IS 875 (Part
3 ) subject to a minimum horizontal load equal to 3 percent of the
vertical loads at critical level.
 Snow loads should be assumed in accordance with IS 875(4) . The
maximum density of ice may be assumed to be 900 kg/m³.
OUTPUT OF EXCEL SHEET
(DOFW)
construction and design of multistorey building by abhimanyu parida.ppt

More Related Content

DOC
Engineering constructionmethodsguidelinescbs(2)
PPT
PPT
Aim for quality in construction
PPTX
Column and Retaining Wall Analysis .pptx
PPTX
Lining in tunnels
PPTX
CONSTRUCTION and types of bonding MODULE final.pptx
PPTX
Construction of residential building summer training ppt
PDF
Re development works at east kidwai nagar, New Delhi
Engineering constructionmethodsguidelinescbs(2)
Aim for quality in construction
Column and Retaining Wall Analysis .pptx
Lining in tunnels
CONSTRUCTION and types of bonding MODULE final.pptx
Construction of residential building summer training ppt
Re development works at east kidwai nagar, New Delhi

Similar to construction and design of multistorey building by abhimanyu parida.ppt (20)

PDF
Building Construction II Report
PPTX
Ñnnnndkdkxkxkxkckckxkcllclclclclcoclclfkocvivi.pptx
PDF
3 Bedroom Duplex Sample Design Drawings Merged
PPTX
Sample copy of IT PPT.pptx
PPTX
Construction of Elevated Highway along Avinashi Road in Coimbatore City from ...
PPTX
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PDF
Building construction ii report (1)
PPTX
Building Construction powerpoint for diploma engineering students
PDF
Project Report - CECL
PDF
Chapter 4
PDF
CT 3 Group Assignment Presentation Slide
DOCX
building consturction training report at cpwd (MNIT)
PPTX
INTERNSHIP PPT THAT HELPS TO UNDERSTANDpptx
PPTX
BUILDING CONSTRUCTION PPT TO HELP THE ENGINEERSSpptx
PPTX
Sanchit
PPT
Industrial Training Report-(2012-13)
PPTX
kuku.pptx
PDF
PPTX
Practical field Training and Report submission
PPTX
Mat foundation
Building Construction II Report
Ñnnnndkdkxkxkxkckckxkcllclclclclcoclclfkocvivi.pptx
3 Bedroom Duplex Sample Design Drawings Merged
Sample copy of IT PPT.pptx
Construction of Elevated Highway along Avinashi Road in Coimbatore City from ...
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
Building construction ii report (1)
Building Construction powerpoint for diploma engineering students
Project Report - CECL
Chapter 4
CT 3 Group Assignment Presentation Slide
building consturction training report at cpwd (MNIT)
INTERNSHIP PPT THAT HELPS TO UNDERSTANDpptx
BUILDING CONSTRUCTION PPT TO HELP THE ENGINEERSSpptx
Sanchit
Industrial Training Report-(2012-13)
kuku.pptx
Practical field Training and Report submission
Mat foundation
Ad

More from DrMuhammadNawazKhan (20)

PPT
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
PPT
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
PPT
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
PPTX
PerfLL and Collective Bargaining.pptormance Management.ppt.pptx
PPT
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
PPTX
Lecture - III - referencing.Data Science.pptx
PPTX
Data Science Data Science Data Science.pptx
PPTX
Lecture 4.pptxsADSADSADadsadsadsDASDdsddasdasd
PPT
Lecture 6.pptsadadasdaDSADASasdadsdADSASDSADad
PPTX
Lecture - V - Article Parts and Title.pptx
PPTX
Lecture 3.pptxEthics, Social Responsibility, and Sustainability
PPTX
Lecture 2.pptxEthics, Social Responsibility, and Sustainability
PPT
MGT Lecture 3 Team Coheacsion updatad.ppt
PPTX
Comprehensive Strategic-Management Model
PPT
82146060-Employee-Retention.pptx82146060-Employee-Retention.pptx
PPTX
82146060-Employee-Retention.pptx82146060-Employee-Retention.pptx
PDF
Lecture 5 - Training and Develoment.pdfLecture 4 - Perfromance Management.pdf
PDF
Lecture 4 - Perfromance Management.pdfLecture 4 - Perfromance Management.pdf
PPTX
Lecture 3 - Job Analysis.pptx PhD - Model.pptx
PPTX
PhD - Model.pptx PhD - Model.pptxPhD - Model.pptx
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
PerfLL and Collective Bargaining.pptormance Management.ppt.pptx
LL and Collective Bargaining.pptLL and Collective Bargaining.ppt
Lecture - III - referencing.Data Science.pptx
Data Science Data Science Data Science.pptx
Lecture 4.pptxsADSADSADadsadsadsDASDdsddasdasd
Lecture 6.pptsadadasdaDSADASasdadsdADSASDSADad
Lecture - V - Article Parts and Title.pptx
Lecture 3.pptxEthics, Social Responsibility, and Sustainability
Lecture 2.pptxEthics, Social Responsibility, and Sustainability
MGT Lecture 3 Team Coheacsion updatad.ppt
Comprehensive Strategic-Management Model
82146060-Employee-Retention.pptx82146060-Employee-Retention.pptx
82146060-Employee-Retention.pptx82146060-Employee-Retention.pptx
Lecture 5 - Training and Develoment.pdfLecture 4 - Perfromance Management.pdf
Lecture 4 - Perfromance Management.pdfLecture 4 - Perfromance Management.pdf
Lecture 3 - Job Analysis.pptx PhD - Model.pptx
PhD - Model.pptx PhD - Model.pptxPhD - Model.pptx
Ad

Recently uploaded (20)

PDF
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
PPTX
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
DOCX
Handbook of entrepreneurship- Chapter 7- Types of business organisations
PDF
HQ #118 / 'Building Resilience While Climbing the Event Mountain
PDF
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
PPTX
Market and Demand Analysis.pptx for Management students
PDF
Value-based IP Management at Siemens: A Cross-Divisional Analysis
PPTX
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
PPTX
Chapter 2 strategic Presentation (6).pptx
PDF
Communication Tactics in Legal Contexts: Historical Case Studies (www.kiu.ac...
PPTX
CTG - Business Update 2Q2025 & 6M2025.pptx
PDF
Second Hand Fashion Call to Action March 2025
PDF
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
PDF
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
PDF
Business Communication for MBA Students.
PPTX
IMM marketing mix of four ps give fjcb jjb
PPTX
IMM.pptx marketing communication givguhfh thfyu
PPTX
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
PDF
Comments on Clouds that Assimilate Parts I&II.pdf
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
Understanding Procurement Strategies.pptx Your score increases as you pick a ...
Handbook of entrepreneurship- Chapter 7- Types of business organisations
HQ #118 / 'Building Resilience While Climbing the Event Mountain
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
Market and Demand Analysis.pptx for Management students
Value-based IP Management at Siemens: A Cross-Divisional Analysis
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
Chapter 2 strategic Presentation (6).pptx
Communication Tactics in Legal Contexts: Historical Case Studies (www.kiu.ac...
CTG - Business Update 2Q2025 & 6M2025.pptx
Second Hand Fashion Call to Action March 2025
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
Business Communication for MBA Students.
IMM marketing mix of four ps give fjcb jjb
IMM.pptx marketing communication givguhfh thfyu
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
Comments on Clouds that Assimilate Parts I&II.pdf
Hand book of Entrepreneurship 4 Chapters.docx

construction and design of multistorey building by abhimanyu parida.ppt

  • 1. CONSTRUCTION AND DESIGN OF MULTISTOREY BUILDING AT UNITECH LTD SUBMITTED BY: UNDER THE GUINDANCE OF ABHIMANYU PARIDA RAJIV GUPTA 1040241 FACULTY COORDINATOR
  • 3. Projects Undertaken 1. Construction of residential building (escape) 1.1 Excavation, Layout and Foundation 1.2 Column layout, shuttering and casting 1.3 Slab, Beam shuttering and casting 1.4 Important Components 2. Introduction to bonded slab post tensioning 2.1 Post tensioning 2.2 benefits 2.3 Tendons and stressing
  • 4. Projects Undertaken 3. Design of building component 3.1 Formwork design 3.2 Staircase design 3.3 Deep Beams 3.4 Slabs
  • 6. Excavation, Layout and Foundation  Excavation is a process of making trenches by digging up of earth for the construction of foundations and basements.  Excavation level at escape site is 219.825 mm  Excavation is done by the JCB on the hourly basis  After the excavation the surface is leveled called surface dressing  Layout is done on the PCC poured over leveled surface.  Column and foundation (raft ) steel is then laid as per drawings.
  • 7. Points to take care:-  layout should be checked properly.  Check any difference between architectural and structural drawings regarding location of column.  After excavation check the stability of temporary structures built near the excavated ground.  Before laying raft reinforcement, shuttering wall which is mainly brick wall should be built and should be filled with soil on other side.  Check the direction of chair bars in the raft
  • 11. COULMN CASTING  On the raft the column layout is done.  Layout for starter.  The column ties and link bars are provided as per column reinforcement drawings and general specifications.  Displacement of main bars should be provided with L bar  The plumb of formwork should be checked.  Height of cast should be calculated accurately.  Avoid caps as far as possible.
  • 12. LAYOUT , PEDESTAL & STARTER
  • 14. PLUMB & FORMWORK, CASTING,CURING
  • 15. SLAB, BEAM SHUTTERING & CASTING  beam bottom is first laid on the column and then slab formwork is laid  After the reinforcement, the slab is checked for steel as per drawings and level required.  A camber of 5 mm in provided in the center of slab.  Casting of slab should be discontinue at l/3 from the support.
  • 17. IMPORTANT COMPONENTS  Key in column  Water bar  Binding materials  Expansion joint
  • 18. KEY IN COLUMN  since the height of column is very large, hence it is not possible to cast the column at one time, to cast the column later the key is made at the junction so that the proper bond between the old concrete and new concrete is formed.
  • 20. EXPANSION JOINT  Since concrete is subjected to volume change. Provision must be made to cater for the volume change by way of joint to relieve the stresses produced.  Expansion joint is function of length  Buildings longer than 45 m are generally provided with one or more expansion joints.  Material used as expansion joint material is armour board whose thickness is 25 mm.
  • 21. EXPANSION JOINT  Expansion joint material, size is 25 mm  Expansion joint in building
  • 22. WATER BAR  Water bar is provided in the retaining wall o that the moisture can’t move from the soil to the joint. Water bar is basically provided at the constructions joints of retaining wall of two different towers
  • 24. BINDING MATERIALS  Since the thermal expansion of concrete is different from that of masonry. The interface between the concrete and the masonry is liable to crack. To avoid this crack the chicken wire mesh is used to avoid the crack and also provides the better grip for Masonry with concrete.  Similarly when the drainage pipes are laid along with the outer wall then again the connection between the pipe and the wall has different coefficient of temperature change hence they are joint to the concrete by lead keys.  In the toilets and kitchen sunken portion the joints in any case are packed by water proof and non shrinkable material.
  • 25. BINDING MATERIALS  Chicken wire mesh between brick masonry and concrete  Connection of pipes with concrete  Chicken wire mesh in conduits through concrete
  • 26. WATER PROOFING  Water proofing has remained as an unsolved complex problem  Use of plasticizers, super plasticizers, air-entraining agents helps in reducing the permeability of concrete by reducing the requirement of mixing water, hence can be also be regarded as waterproof material.  Some of approved water-proofing compound by the company are:- pidilite, cico, fosroe, baushimine, unitile.  Water-proofing cement paint:- super snoweem
  • 27. WATER PROOFING  Water proofing in sunken portion of kitchen and bathroom  WP in sunken portion at ground level  WP in retaining wall
  • 28. WATER PROOFING IN GARDEN AREA  For water proofing in garden area the soil is first leveled and then rammed to achieve the maximum density  The PCC is then laid down mixed with tape Crete (a water proofing compound)  After PCC the plaster of fibrous material is done.  the bituminous sheets are laid by heating it with the welder. On those sheets the drainage pipes are laid down with suitable slope and these pipes are covered with geo-fabric sheets.  Again the plaster is done. On the plaster the 40 mm aggregates are laid.  On the aggregate the geo-fabric sheets are laid down on which the sand is placed & on the sand the soil ,along with fertilizers, is placed on which the gardening is done for the non tower area.
  • 29. WATER PROOFING IN GARDEN AREA  Sandy soil  PCC mixed with tape Crete (water proof compound)  Texas (bitumen) sheet  Drainage pipe  40 mm aggregate  Geo-fabric sheet  Sand
  • 31. INTRODUCTION/BENEFITS  Post-tensioning is a method of reinforcing (strengthening) concrete or other materials with high-strength steel strands or bars, typically referred to as tendons  allows longer clear spans, thinner slabs  lower overall building height for the same floor-to-floor height.  allows a high degree of flexibility in the column layout, span lengths and ramp configurations
  • 33. PLACEMENT OF TENDONS  Positioning and fixing of casting and block-outs to the edge formwork or construction joint formwork  The support bars shall be prepared in advance.  Lay tendons according to tendon layout in accordance with the drawings.  Fix tendons to correct profiles with support bars and chairs and the tendons are made with provisions for grouting using grout using grout vents and grout hoses  Prepare installation report for every installation as per the enclosed format.  tolerance of tendon profiles is recommended as follows:  **vertical: + 5 mm (at lowest and highest points)  Horizontal: + 100 mm
  • 35. LOADS ON FALSEWORK Loads on Falsework are any combinations of the following:  Dead loads,  Imposed loads,  Environmental loads,  Incidental loads during erection and operation, and  Lateral pressure.
  • 36. DIFFERENT LOAD DATA  Self load shall be determined by either actual measurement or in accordance with IS 875 (Part I) the unit weight of wet concrete including reinforcement shall be taken as 26 kN/m². However, in absence of the data, load may be assumed as 500 N/M2 for the purpose of initial calculations .  Loads during constructional operation shall constitute the imposed loads [see IS 875 (Part 2 ) Where allowance has only to be made for access and inspection purposes, a loading of 750 N/m² should be adequate  The lateral pressure due to fresh concrete depends on the temperature of concrete as placed, the rate of placing of concrete and the concrete mix proportion  Wind loads should be taken for design in accordance with IS 875 (Part 3 ) subject to a minimum horizontal load equal to 3 percent of the vertical loads at critical level.  Snow loads should be assumed in accordance with IS 875(4) . The maximum density of ice may be assumed to be 900 kg/m³.
  • 37. OUTPUT OF EXCEL SHEET (DOFW)