Chapter 5:  Construction Process by Syed Burhanuddin Hilmi Syed Mohamad
Project Format The  construction industry is generally focused on the production of a single and unique end product. The product of construction industry is a facility that is usually unique in design and method of fabrication. It is a single ‘one-off’ item that is stylized in terms of its function, appearance and location.
Project Development Construction projects develop in a clearly sequential or linear fashion. The general steps involved are as follows: A need for a facility is identified by the owner. Initial feasibility and cost projections are developed. The decision to proceed with conceptual design is made, and a design professional is retained.
Project Development The conceptual design and scope of work are developed to include an approximate estimate of cost. The decision is made to proceed with the development of final design documents, which fully define the project for purposes of construction. Based on the final design documents, the project is advertised and proposals to include quotations for construction of the work are solicited.
Project Development Based on proposals received, a constructor is selected and a notice to the constructor to proceed with the work is given. The proposal and the acceptance of the proposal on the part of the owner constitute the formation of a contract for the work. The process of constructing the facility is initiated. Work is complete and the facility is available for acceptance and occupancy.
Project Development In complex projects, a period of testing decides if the facility operates as designed and planned. This period is typical of industrial projects and is referred to as project start-up. The facility operates and is maintained during a specified service life. The facility is disposed of if appropriate or maintained in perpetuity.
Process A process is defined as a system of operations in the design, development, and  production of something, such as a project. A process is a series of actions, changes, or operations that bring about an end result – cost, schedule, technical performance objectives. A process is that it is a course or passage of time in which something is created – an ongoing movement or progression. (Ireland & Iceland, 2002)
Construction Processes The process of purchase begins with a client who has need for a facility. The nature of risk is influenced by this process of purchasing construction. In construction, since the item purchased is to be produced, there are many complex issues which can lead to failure to complete the project in a functional and/or timely manner.
Managing the Project Life Cycle Cleland & King, 1983 Assist in transfer of project product. Transfer human and nonhuman resources to other organizations. Transfer or complete commitments. Terminate project. Reward personnel. Perform the work of the project (i.e. design, construction, production, site activation, testing, delivery, etc.). Define the project organization approach. Define projects target. Prepare the schedule for execution phase. Define and allocate tasks and resources. Build the project team. Determine that a project is needed. Establish goal. Estimate the resources that the organization is willing to commit. “ Sell” the organization on the need for a project approach. Make key personnel appointment. Phase 4 Termination Phase 3 Execution phase Phase 2 Planning phase Phase 1 Conceptual Phase
Construction Process The construction process may be subdivided into the stages considered below: Conceptual stage: the client identifies the need for the item of construction and appoints and briefs consultants who study the client’s requirement, propose an outline of the design and assess the feasibility of the project. Design stage: the concept of the project is further developed and production information and contract documentation prepared. Tenders are called.
Construction Process Construction stage: production programmes are prepared and construction carried out on site. Operation and maintenance stage: the completed building or works is maintained, repaired or altered as required over the course of its life.
Activities at Various Stages of a construction project Members of the design team develop brief, consider the technical and functional feasibility of the client’s intentions, make general proposals for the project including form, layout, height and floor area, Architect applies for outline planning approval. Outline proposals Client considers project requirements, acquires land, sets up project team, appoints and briefs architect/engineer. Inception Activities Substage
Activities at Various Stages of a construction project Design team prepares the full design of the project and all relevant production information and contract documentation. Architect applies for building plan approval. Detailed design Architect/Engineer finalises brief, and with other consultants, prepares sketch designs which are submitted to the client for approval. Scheme Design Activities Substage
Activities at Various Stages of a construction project Prepares a programme for the project and mobilises resources for construction on sie. Project planning Invites tenders. Quantity Surveyor evaluates the tenders and report to client. Recommends to Client. Client signs a contract with the successful bidder. Tender Activities Substage
Activities at Various Stages of a construction project Main Contractor and subcontractors transform the production information into a physical facility. Members of the design team supervise construction. Architect/engineer issues payment certificates periodically on the recommendation of the Quantity Surveyor. Site Meeting. On completion, Architect, applies for a temporary occupation license. Application for a final certificate. Site Operation Activities Substage
Activities at Various Stages of a construction project George Ofori, 1990 All faults becoming evident during the defects liability period are made good by the contractor. Quantity surveyor prepares the final account for the project. Clients arranges for the management and maintenance of the facility. Operation Activities Substage
On time and within budget A quality facility on time and within budget
Construction Process The construction process involves the translation of a client’s needs and intentions. Then prepare documentations; cost plan, BQ, Specifications, Drawings. Finally, the construction phase.
Construction Process Pre-Construction Activities Feasibility study Outline Conceptual Design Stage Preliminary Design Stage Design Development Stage (Working Drawing) Completion of Working Drawings
Activities During Construction Construction Supervision Preliminaries Demolition Excavation and foundation Concrete and brickwork Finishes M&E works External works
Activities During Construction Construction Activities Variation Order Progress Payment Certificate of Practical Completion (CPC) Certificate of Fitness (CF)
Site Preparation Site clearing Earthwork Setting Out & Levelling Hoarding  Dewatering systems Temporary buildings Access
Detail Process Decision of a client in order to invest or not. The client acquires a piece of land for project development. The client will engage professionals to prepare documentation including drawings, specifications, a form of contract, BQ. All about consultancy works.
Key Players The owner/Employer The designer/Estimator Architect/Planner C&S Engineers M&E Engineers QS The constructor Main Subcont.
Clients Initiator of the construction process. Will be financing the project. An employer May be the public and private sectors.
SUPPLIER CONTRACTOR MANPOWER AUTHORITIES FINANCIER CONSULTANTS CLIENT Project Management Consultant Planner Architect Engineers; C&S, M, E Quantity Surveyor Land Surveyor Interior Designer Landscape Architect Administration Site Management Site Worker Domestic Sub Contractor Nominated Sub Contractor Main Contractor Nominated Supplier Manufacturer Vendor Distributor Bank Finance Company Credit Corporation Leasing Company Federal State Local Private Sector Public Sector Parties Involved in the  Construction Industry
The process will be organised into the sequence of activities/works differ from one project to another.
Construction Site Management Work Programme The first stage, which is best commenced by referring to the initial draft programme submitted at tender stage. Includes time schedule for all major activities in the contract. Critical activities, early start time, early completion time, milestones. Sequence of works.
Project Planning and Control Objectives To arrange the activities appropriately To make a realistic time scheduling To make a resources estimation and planning To implement time and cost controlling To ease the contract administration
Planning What are we aiming for and why? In the execution of this function, the organization’s mission, objectives, goals, and strategies are determined.
Control Construction – monitored by Project Manager. Based on work programme – as planned vs. actual progress. IT  - Microsoft project & Primavera (sometime Excel). Cash Flow (Financial Progress) Inspection & Observation (Physical Progress).
WHY THERE HAS TO BE A PLAN? INTERNAL (STRATEGIC) OR EXTERNAL (CLIENT’S REQUEST) TO AVOID RISK TO TRACK PROGRESS TO MAKE CORRECTION
WHY SCHEDULE? To communicate the construction plan To establish production goal To monitor and measure progress To manage change
INTRODUCTION The task of monitoring and controlling help to determine the objectives are within reach Monitoring and control has to start at early stage of the project development since it has more impact on cost Focusing on monitoring and control at the construction stage since many acknowledge of its difficulty
MONITORING and CONTROL Monitoring is comparing the planned against actual Using software can easily be updated and preparation of reports are standardised Several methods used to monitor the work progress these include time weightage, cost weightage, man-days and quality Most common is using cost weightage
Progress Curves Table 3.4  Combination between S-Curves and Bar Charts Original Schedule Actual progress Cumulative progress (%) 100 0                     Dismantle Plant, Clean Up 12                     Curtain Grout 11                     Spillway Bridge 10                     Radial Gates 9                     Prestress 8                     Install Trash Racks 7                     Install Outlet Gates 6                     Dam Concrete 5                     Foundation Grouting 4                     Diversion Stage  3                     Foundation Excavation 2                     Mobilization 1 10 9 8 7 6 5 4 3 2 1     Month Description No.
Project Controlling Procedure - What performance measures should be selected? What data should be used to estimate the current value of each performance measure? How should raw data be collected, from which sources, and in what frequency? How should the data be analyzed to detect current and future deviations? How should the results of the analysis be reported, in what format, to whom, and how often? Figure 3.12  Project Controlling Procedure Project plan Project implementation Project control Project updating Measurement Of work performance
Project Controlling  Figure 3.13  Implementation of Project Controlling in Construction Project Implementation of  Project Controlling Construction Design Subcontract Procurement Project Site Main office
Elements of Project Controlling  Figure 3.14  Elements of Project Controlling Action Plan Budget Elements of  Project Controlling Tools Milestone Forecasting
Figure below presents a Gantt Chart generated by Microsoft Project.   Gantt Chart:   The Gantt chart (invented by Henry L. Gantt in 1900's) is a bar chart presentation showing a horizontal bar for each task,  the length of the bar representing the duration of the task.
Construct Bar Chart Layout? Time unit? Workdays or calendar days? Continuous or non-continuous…
Bar Charts Limitations Advantages Easy to prepare Easy to understand Good communication tool Disadvantages Do not show inter-relationship Difficult to documentation and manage project
Time Controlling  Factors causing delay in construction project Procurement of resources which is not on schedule Inappropriate work capacity Low productivity Ineffective project management There are some redesign and extra work to the project Bad communication among parties involved in project Inefficient decision making Force majeur, etc. Need an effective supervision
Suggestion of Practices Some of the practices can be incorporated in the monitoring and control process system these include: Daily monitoring Morning discussion with the foreman Afternoon discussion Discussion the resources requirement every forth nightly Using bonus system to improve productivity Using damages clause to control supplier and sub-contractor
The Planning & Scheduling Process IDENTIFY THE PROJECT ACTIVITIES EXTIMATE DURATION OF ACTIVITY DEVELOPED THE PROJECT PLAN SCHEDULE PROJECT ACTIVITIES REVIEW AND ANALYSE THE SCHEDULE OK? IMPLEMENT YES NO
Historical Background During world war 1, Henry L.Gantt develop a graphical technique of displaying bar type line upon specific time. The technique was known as Bar Chart. In 1956 E.I. du Pont de Nemours & Company developed network concept known as Critical Path Method Booz Allen & Hamilton develop Project Evaluation Review Technique (PERT) Scheduling software application are Primavera, Microsoft Project, Artemis, Timeline etc
Choice of Scheduling Method Factors that governed the choice of the  technique are: Familiarity on the technique to be used Type and size of project Purpose of scheduling
Familiarity on the technique to be used A planner should not engaged any technique which he has a limited knowledge  on it’s application Main objective of the schedule as a communication tool Important to have a schedule technique which is acceptable by all parties.
Type and Size of the Project Project with few but repetitive tasks –  Line of Balance Medium to Large Project –  (Critical Path Method) like Precedence Method or Arrow Diagram Small Project –  Gantt Chart or Bar Chart
Purpose & Important of Schedule Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage – all material cannot put in the site (confined space) Avoid delay of the work and activity. Minimize the cash flow – as min as possible such as order material stage by stage depend on the work needed. To guide fabricate (roofing, steel etc) Control human resources and machinery  To give confidence to the client especially when bidding process. To improve the efficiency of the operation through the efficient use of resources and cost control. Basic schedule for endorsement .
ACTIVITY DEFINED FIVE CHARACTERISTICS Must consume time Mostly consume resourse Have a defineable start and finish Measurable
ACTIVITY IDENTIFICATION THINGS TO BE REVIEWED Plans and specification Agreement Contract conditions BQ Other information
ACTIVITY IDENTIFICATION CRITERIA FOR BREAKING DOWN PROJECTS: WHAT? WHERE? WHO? WHEN? HOW?
ACTIVITY DETAIL DEPENDS ON THE FOLLOWING: >Purpose Complexity >Philosophy >Information >Responsibility >Effect of detail
ACTIVITY DESCRIPTIONS CONCISE AND CLEAR MAY USE SCOPE AND LOCATION ALWAYS HAVE THE SAME MEANING LEGIBLE AND UNDERSTANDABLE CONSISTENT USE STANDARD ABBREVIATION
WORK BREAKDOWN STRUCTURES (WBS) A PLANNING TOOL AND NOT A SCHEDULING METHOD BREAKS A PROJECT DOWN INTO GREATER DETAIL BY LEVEL ORGANISES WITHOUT SCHEDULING PROVIDES A FRAMEWORK FOR ORGANISING AND ORDERING ACTIVITIES
Work Sequence Stages of construction activity. Normally from site clearing until project handover. Logical sequence of activities. Needs an experience and knowledge during planning and scheduling process.
                        Jumlah Terkumpul (Dilaksana) 36 35 34 31 27 22 17 13 9 6 3 1 Jumlah Terkumpul (Dirancang) 1 1 3 4 5 5 4 4 3 3 2 1 Jumlah Mingguan                         36 Jumlah                                                 4 Kerja Bata                                                 4 Tuang Konkrit Tiang                                                 4 Pasang Tetulang Tiang                                                 4 Pasang Acuan Tiang                                                 4 Penambakan                                                 4 Tuang Konkrit Asas                                                 4 Pasang Tetulang Asas                                                 4 Korek Asas                                                 4 Bersih Tapak 12 11 10 9 8 7 6 5 4 3 2 1 MINGGU MASA AKTIVITI
2200 3 Finish HVAC 2400 2200 2 Finish plumbing 2300 2600 3 Internal paint 2200 2200 4 Internal finish carpentry 2100 2200 3 Ext paint 2000 2100, 2300 2 Cabinets 1900 1900, 2400, 2500 4 Finish drywall 1800 1800 4 Hang drywall 1700 1500 2 Ext finish carpentry 1600 20000 3 Ext siding 1500 1000, 1600, 2700 3 Shingles 1400 1000 3 Rough Electrical 1300 1300 3 Rough HVAC 1200 Successors Duration (days) Description Act. ID 2 Punch list 2800 2800 4 Grading and landscaping 2700 2800 3 Flooring 2600 2200 2 Finish electrical 2500
A SUCCESSFUL CONSTRUCTION: WITHIN BUDGET ON TIME MEETS OWNWER SPECIFIED NEEDS AND REQUIREMENTS WORK WITH FLEXIBILITY
Daniel W.Halpin (2006); Construction Management; Third Edition; John Wiley & Sons; USA. Andrew A. L. Tan (2004); Why Projects Fail? 1001 reasons; Venton Publishing (M) Sdn. Bhd.; Selangor, Malaysia.

More Related Content

PPTX
Construction phases
PPT
Lecture 1 introduction to construction procurement process.
PPTX
Stages In Construction
PPT
3. construction planning. construction project management
PPTX
Construction Project Management.
PDF
02 Construction Projects
PPTX
Building Construction
PPTX
Construction difficulties
Construction phases
Lecture 1 introduction to construction procurement process.
Stages In Construction
3. construction planning. construction project management
Construction Project Management.
02 Construction Projects
Building Construction
Construction difficulties

What's hot (20)

PPTX
Construction Project Management
PPTX
Construction Project Management
PPTX
Construction contract
DOCX
Traditional procurement method
PPT
Building approval.ppt
PDF
50451783 taking-off-quantity
PPTX
Construction planning & management
PPTX
Construction project management
PPTX
Construction planning - Construction Technology and Project Management
PDF
site visit report (final)
PPTX
Mooc smm substructure_2
DOCX
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
PDF
Construction Contract in Malaysia
PDF
Project Execution Plan for High Rise Building
PPTX
Stakeholder’s Involvement in Construction Industry
PPT
Construction contracts docuements_08092008
PPTX
Site Possession
PPTX
Construction Project Management ppt
DOCX
Procurement Methods
DOCX
Procurement Methods and their Application.
Construction Project Management
Construction Project Management
Construction contract
Traditional procurement method
Building approval.ppt
50451783 taking-off-quantity
Construction planning & management
Construction project management
Construction planning - Construction Technology and Project Management
site visit report (final)
Mooc smm substructure_2
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
Construction Contract in Malaysia
Project Execution Plan for High Rise Building
Stakeholder’s Involvement in Construction Industry
Construction contracts docuements_08092008
Site Possession
Construction Project Management ppt
Procurement Methods
Procurement Methods and their Application.
Ad

Viewers also liked (20)

PPT
Stages in Construction
PPT
Get Commercial Building Construction Company Auburn by TopRung LLC
DOCX
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
PPT
Arega Siyum D/r revised
PDF
Ranking of scientists in saudi institutions according to their gsc public pro...
PPTX
Stakeholder management In Construction Industry
PPTX
Lecture slides4; Construction Project Planning
PPTX
Project Monitoring and Control
PDF
Project Monitoring And Controlling
PPT
Project control
PDF
Determination of reservoir storage capacity
PPTX
Construction Project Management Class Project Presentation
PDF
Project Controlling and Project Monitoring
ZIP
Project Monitoring and Control
PPTX
Tender procedure slide
ODP
building material
PPTX
PPTX
Stages in Construction
Get Commercial Building Construction Company Auburn by TopRung LLC
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Arega Siyum D/r revised
Ranking of scientists in saudi institutions according to their gsc public pro...
Stakeholder management In Construction Industry
Lecture slides4; Construction Project Planning
Project Monitoring and Control
Project Monitoring And Controlling
Project control
Determination of reservoir storage capacity
Construction Project Management Class Project Presentation
Project Controlling and Project Monitoring
Project Monitoring and Control
Tender procedure slide
building material
Ad

Similar to Construction process (20)

PPTX
CEM unit -I ppt.pptx
PPT
ACH 216 Lecture 02 (Project Format)
PDF
Ch1 introduction
PPTX
Construction Engineering lecture 1.pptx civil engineering
DOCX
Construction management
PDF
Unit 1 basics of construction
PPTX
About cpm and it's basic use in various CTM_042352.pptx
PPTX
Construction project management
PPTX
Constructionprojectmanagement Amit Payal
PPTX
Advanced CM_04.09.2022.pptx
PDF
1 Introduction.pdf
PDF
mod1.pdf
PDF
The management of construction
PDF
Project management-130717112230-phpapp02
PDF
Project Management Notes 5
PDF
Software Project Management | An Overview of the Software Project Management
PDF
Construction Stages and Construction Teams
PPTX
Phases of a Project
PPTX
Construction PROJECT MANAGEMENT
CEM unit -I ppt.pptx
ACH 216 Lecture 02 (Project Format)
Ch1 introduction
Construction Engineering lecture 1.pptx civil engineering
Construction management
Unit 1 basics of construction
About cpm and it's basic use in various CTM_042352.pptx
Construction project management
Constructionprojectmanagement Amit Payal
Advanced CM_04.09.2022.pptx
1 Introduction.pdf
mod1.pdf
The management of construction
Project management-130717112230-phpapp02
Project Management Notes 5
Software Project Management | An Overview of the Software Project Management
Construction Stages and Construction Teams
Phases of a Project
Construction PROJECT MANAGEMENT

Recently uploaded (20)

PPTX
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
PDF
Value-based IP Management at Siemens: A Cross-Divisional Analysis
PDF
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
PDF
Business Communication for MBA Students.
PDF
Challenges of Managing International Schools (www.kiu. ac.ug)
PDF
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
DOCX
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
PDF
Middle East's Most Impactful Business Leaders to Follow in 2025
PDF
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
PPTX
IITM - FINAL Option - 01 - 12.08.25.pptx
PPTX
Market and Demand Analysis.pptx for Management students
PDF
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
PDF
Consumer Behavior in the Digital Age (www.kiu.ac.ug)
PDF
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
PDF
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
PPTX
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
PPTX
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PDF
Pink Cute Simple Group Project Presentation.pdf
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
interschool scomp.pptxzdkjhdjvdjvdjdhjhieij
Value-based IP Management at Siemens: A Cross-Divisional Analysis
Immigration Law and Communication: Challenges and Solutions {www.kiu.ac.ug)
Business Communication for MBA Students.
Challenges of Managing International Schools (www.kiu. ac.ug)
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
Middle East's Most Impactful Business Leaders to Follow in 2025
Highest-Paid CEO in 2025_ You Won’t Believe Who Tops the List.pdf
IITM - FINAL Option - 01 - 12.08.25.pptx
Market and Demand Analysis.pptx for Management students
Vinod Bhatt - Most Inspiring Supply Chain Leader in India 2025.pdf
Consumer Behavior in the Digital Age (www.kiu.ac.ug)
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
Engaging Stakeholders in Policy Discussions: A Legal Framework (www.kiu.ac.ug)
df0ee68f89e1a869be4bff9b80a7 business 79f0.pptx
33ABJFA6556B1ZP researhchzfrsdfasdfsadzd
Hand book of Entrepreneurship 4 Chapters.docx
Pink Cute Simple Group Project Presentation.pdf
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...

Construction process

  • 1. Chapter 5: Construction Process by Syed Burhanuddin Hilmi Syed Mohamad
  • 2. Project Format The construction industry is generally focused on the production of a single and unique end product. The product of construction industry is a facility that is usually unique in design and method of fabrication. It is a single ‘one-off’ item that is stylized in terms of its function, appearance and location.
  • 3. Project Development Construction projects develop in a clearly sequential or linear fashion. The general steps involved are as follows: A need for a facility is identified by the owner. Initial feasibility and cost projections are developed. The decision to proceed with conceptual design is made, and a design professional is retained.
  • 4. Project Development The conceptual design and scope of work are developed to include an approximate estimate of cost. The decision is made to proceed with the development of final design documents, which fully define the project for purposes of construction. Based on the final design documents, the project is advertised and proposals to include quotations for construction of the work are solicited.
  • 5. Project Development Based on proposals received, a constructor is selected and a notice to the constructor to proceed with the work is given. The proposal and the acceptance of the proposal on the part of the owner constitute the formation of a contract for the work. The process of constructing the facility is initiated. Work is complete and the facility is available for acceptance and occupancy.
  • 6. Project Development In complex projects, a period of testing decides if the facility operates as designed and planned. This period is typical of industrial projects and is referred to as project start-up. The facility operates and is maintained during a specified service life. The facility is disposed of if appropriate or maintained in perpetuity.
  • 7. Process A process is defined as a system of operations in the design, development, and production of something, such as a project. A process is a series of actions, changes, or operations that bring about an end result – cost, schedule, technical performance objectives. A process is that it is a course or passage of time in which something is created – an ongoing movement or progression. (Ireland & Iceland, 2002)
  • 8. Construction Processes The process of purchase begins with a client who has need for a facility. The nature of risk is influenced by this process of purchasing construction. In construction, since the item purchased is to be produced, there are many complex issues which can lead to failure to complete the project in a functional and/or timely manner.
  • 9. Managing the Project Life Cycle Cleland & King, 1983 Assist in transfer of project product. Transfer human and nonhuman resources to other organizations. Transfer or complete commitments. Terminate project. Reward personnel. Perform the work of the project (i.e. design, construction, production, site activation, testing, delivery, etc.). Define the project organization approach. Define projects target. Prepare the schedule for execution phase. Define and allocate tasks and resources. Build the project team. Determine that a project is needed. Establish goal. Estimate the resources that the organization is willing to commit. “ Sell” the organization on the need for a project approach. Make key personnel appointment. Phase 4 Termination Phase 3 Execution phase Phase 2 Planning phase Phase 1 Conceptual Phase
  • 10. Construction Process The construction process may be subdivided into the stages considered below: Conceptual stage: the client identifies the need for the item of construction and appoints and briefs consultants who study the client’s requirement, propose an outline of the design and assess the feasibility of the project. Design stage: the concept of the project is further developed and production information and contract documentation prepared. Tenders are called.
  • 11. Construction Process Construction stage: production programmes are prepared and construction carried out on site. Operation and maintenance stage: the completed building or works is maintained, repaired or altered as required over the course of its life.
  • 12. Activities at Various Stages of a construction project Members of the design team develop brief, consider the technical and functional feasibility of the client’s intentions, make general proposals for the project including form, layout, height and floor area, Architect applies for outline planning approval. Outline proposals Client considers project requirements, acquires land, sets up project team, appoints and briefs architect/engineer. Inception Activities Substage
  • 13. Activities at Various Stages of a construction project Design team prepares the full design of the project and all relevant production information and contract documentation. Architect applies for building plan approval. Detailed design Architect/Engineer finalises brief, and with other consultants, prepares sketch designs which are submitted to the client for approval. Scheme Design Activities Substage
  • 14. Activities at Various Stages of a construction project Prepares a programme for the project and mobilises resources for construction on sie. Project planning Invites tenders. Quantity Surveyor evaluates the tenders and report to client. Recommends to Client. Client signs a contract with the successful bidder. Tender Activities Substage
  • 15. Activities at Various Stages of a construction project Main Contractor and subcontractors transform the production information into a physical facility. Members of the design team supervise construction. Architect/engineer issues payment certificates periodically on the recommendation of the Quantity Surveyor. Site Meeting. On completion, Architect, applies for a temporary occupation license. Application for a final certificate. Site Operation Activities Substage
  • 16. Activities at Various Stages of a construction project George Ofori, 1990 All faults becoming evident during the defects liability period are made good by the contractor. Quantity surveyor prepares the final account for the project. Clients arranges for the management and maintenance of the facility. Operation Activities Substage
  • 17. On time and within budget A quality facility on time and within budget
  • 18. Construction Process The construction process involves the translation of a client’s needs and intentions. Then prepare documentations; cost plan, BQ, Specifications, Drawings. Finally, the construction phase.
  • 19. Construction Process Pre-Construction Activities Feasibility study Outline Conceptual Design Stage Preliminary Design Stage Design Development Stage (Working Drawing) Completion of Working Drawings
  • 20. Activities During Construction Construction Supervision Preliminaries Demolition Excavation and foundation Concrete and brickwork Finishes M&E works External works
  • 21. Activities During Construction Construction Activities Variation Order Progress Payment Certificate of Practical Completion (CPC) Certificate of Fitness (CF)
  • 22. Site Preparation Site clearing Earthwork Setting Out & Levelling Hoarding Dewatering systems Temporary buildings Access
  • 23. Detail Process Decision of a client in order to invest or not. The client acquires a piece of land for project development. The client will engage professionals to prepare documentation including drawings, specifications, a form of contract, BQ. All about consultancy works.
  • 24. Key Players The owner/Employer The designer/Estimator Architect/Planner C&S Engineers M&E Engineers QS The constructor Main Subcont.
  • 25. Clients Initiator of the construction process. Will be financing the project. An employer May be the public and private sectors.
  • 26. SUPPLIER CONTRACTOR MANPOWER AUTHORITIES FINANCIER CONSULTANTS CLIENT Project Management Consultant Planner Architect Engineers; C&S, M, E Quantity Surveyor Land Surveyor Interior Designer Landscape Architect Administration Site Management Site Worker Domestic Sub Contractor Nominated Sub Contractor Main Contractor Nominated Supplier Manufacturer Vendor Distributor Bank Finance Company Credit Corporation Leasing Company Federal State Local Private Sector Public Sector Parties Involved in the Construction Industry
  • 27. The process will be organised into the sequence of activities/works differ from one project to another.
  • 28. Construction Site Management Work Programme The first stage, which is best commenced by referring to the initial draft programme submitted at tender stage. Includes time schedule for all major activities in the contract. Critical activities, early start time, early completion time, milestones. Sequence of works.
  • 29. Project Planning and Control Objectives To arrange the activities appropriately To make a realistic time scheduling To make a resources estimation and planning To implement time and cost controlling To ease the contract administration
  • 30. Planning What are we aiming for and why? In the execution of this function, the organization’s mission, objectives, goals, and strategies are determined.
  • 31. Control Construction – monitored by Project Manager. Based on work programme – as planned vs. actual progress. IT - Microsoft project & Primavera (sometime Excel). Cash Flow (Financial Progress) Inspection & Observation (Physical Progress).
  • 32. WHY THERE HAS TO BE A PLAN? INTERNAL (STRATEGIC) OR EXTERNAL (CLIENT’S REQUEST) TO AVOID RISK TO TRACK PROGRESS TO MAKE CORRECTION
  • 33. WHY SCHEDULE? To communicate the construction plan To establish production goal To monitor and measure progress To manage change
  • 34. INTRODUCTION The task of monitoring and controlling help to determine the objectives are within reach Monitoring and control has to start at early stage of the project development since it has more impact on cost Focusing on monitoring and control at the construction stage since many acknowledge of its difficulty
  • 35. MONITORING and CONTROL Monitoring is comparing the planned against actual Using software can easily be updated and preparation of reports are standardised Several methods used to monitor the work progress these include time weightage, cost weightage, man-days and quality Most common is using cost weightage
  • 36. Progress Curves Table 3.4 Combination between S-Curves and Bar Charts Original Schedule Actual progress Cumulative progress (%) 100 0                     Dismantle Plant, Clean Up 12                     Curtain Grout 11                     Spillway Bridge 10                     Radial Gates 9                     Prestress 8                     Install Trash Racks 7                     Install Outlet Gates 6                     Dam Concrete 5                     Foundation Grouting 4                     Diversion Stage 3                     Foundation Excavation 2                     Mobilization 1 10 9 8 7 6 5 4 3 2 1     Month Description No.
  • 37. Project Controlling Procedure - What performance measures should be selected? What data should be used to estimate the current value of each performance measure? How should raw data be collected, from which sources, and in what frequency? How should the data be analyzed to detect current and future deviations? How should the results of the analysis be reported, in what format, to whom, and how often? Figure 3.12 Project Controlling Procedure Project plan Project implementation Project control Project updating Measurement Of work performance
  • 38. Project Controlling Figure 3.13 Implementation of Project Controlling in Construction Project Implementation of Project Controlling Construction Design Subcontract Procurement Project Site Main office
  • 39. Elements of Project Controlling Figure 3.14 Elements of Project Controlling Action Plan Budget Elements of Project Controlling Tools Milestone Forecasting
  • 40. Figure below presents a Gantt Chart generated by Microsoft Project. Gantt Chart: The Gantt chart (invented by Henry L. Gantt in 1900's) is a bar chart presentation showing a horizontal bar for each task, the length of the bar representing the duration of the task.
  • 41. Construct Bar Chart Layout? Time unit? Workdays or calendar days? Continuous or non-continuous…
  • 42. Bar Charts Limitations Advantages Easy to prepare Easy to understand Good communication tool Disadvantages Do not show inter-relationship Difficult to documentation and manage project
  • 43. Time Controlling Factors causing delay in construction project Procurement of resources which is not on schedule Inappropriate work capacity Low productivity Ineffective project management There are some redesign and extra work to the project Bad communication among parties involved in project Inefficient decision making Force majeur, etc. Need an effective supervision
  • 44. Suggestion of Practices Some of the practices can be incorporated in the monitoring and control process system these include: Daily monitoring Morning discussion with the foreman Afternoon discussion Discussion the resources requirement every forth nightly Using bonus system to improve productivity Using damages clause to control supplier and sub-contractor
  • 45. The Planning & Scheduling Process IDENTIFY THE PROJECT ACTIVITIES EXTIMATE DURATION OF ACTIVITY DEVELOPED THE PROJECT PLAN SCHEDULE PROJECT ACTIVITIES REVIEW AND ANALYSE THE SCHEDULE OK? IMPLEMENT YES NO
  • 46. Historical Background During world war 1, Henry L.Gantt develop a graphical technique of displaying bar type line upon specific time. The technique was known as Bar Chart. In 1956 E.I. du Pont de Nemours & Company developed network concept known as Critical Path Method Booz Allen & Hamilton develop Project Evaluation Review Technique (PERT) Scheduling software application are Primavera, Microsoft Project, Artemis, Timeline etc
  • 47. Choice of Scheduling Method Factors that governed the choice of the technique are: Familiarity on the technique to be used Type and size of project Purpose of scheduling
  • 48. Familiarity on the technique to be used A planner should not engaged any technique which he has a limited knowledge on it’s application Main objective of the schedule as a communication tool Important to have a schedule technique which is acceptable by all parties.
  • 49. Type and Size of the Project Project with few but repetitive tasks – Line of Balance Medium to Large Project – (Critical Path Method) like Precedence Method or Arrow Diagram Small Project – Gantt Chart or Bar Chart
  • 50. Purpose & Important of Schedule Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage – all material cannot put in the site (confined space) Avoid delay of the work and activity. Minimize the cash flow – as min as possible such as order material stage by stage depend on the work needed. To guide fabricate (roofing, steel etc) Control human resources and machinery To give confidence to the client especially when bidding process. To improve the efficiency of the operation through the efficient use of resources and cost control. Basic schedule for endorsement .
  • 51. ACTIVITY DEFINED FIVE CHARACTERISTICS Must consume time Mostly consume resourse Have a defineable start and finish Measurable
  • 52. ACTIVITY IDENTIFICATION THINGS TO BE REVIEWED Plans and specification Agreement Contract conditions BQ Other information
  • 53. ACTIVITY IDENTIFICATION CRITERIA FOR BREAKING DOWN PROJECTS: WHAT? WHERE? WHO? WHEN? HOW?
  • 54. ACTIVITY DETAIL DEPENDS ON THE FOLLOWING: >Purpose Complexity >Philosophy >Information >Responsibility >Effect of detail
  • 55. ACTIVITY DESCRIPTIONS CONCISE AND CLEAR MAY USE SCOPE AND LOCATION ALWAYS HAVE THE SAME MEANING LEGIBLE AND UNDERSTANDABLE CONSISTENT USE STANDARD ABBREVIATION
  • 56. WORK BREAKDOWN STRUCTURES (WBS) A PLANNING TOOL AND NOT A SCHEDULING METHOD BREAKS A PROJECT DOWN INTO GREATER DETAIL BY LEVEL ORGANISES WITHOUT SCHEDULING PROVIDES A FRAMEWORK FOR ORGANISING AND ORDERING ACTIVITIES
  • 57. Work Sequence Stages of construction activity. Normally from site clearing until project handover. Logical sequence of activities. Needs an experience and knowledge during planning and scheduling process.
  • 58.                         Jumlah Terkumpul (Dilaksana) 36 35 34 31 27 22 17 13 9 6 3 1 Jumlah Terkumpul (Dirancang) 1 1 3 4 5 5 4 4 3 3 2 1 Jumlah Mingguan                         36 Jumlah                                                 4 Kerja Bata                                                 4 Tuang Konkrit Tiang                                                 4 Pasang Tetulang Tiang                                                 4 Pasang Acuan Tiang                                                 4 Penambakan                                                 4 Tuang Konkrit Asas                                                 4 Pasang Tetulang Asas                                                 4 Korek Asas                                                 4 Bersih Tapak 12 11 10 9 8 7 6 5 4 3 2 1 MINGGU MASA AKTIVITI
  • 59. 2200 3 Finish HVAC 2400 2200 2 Finish plumbing 2300 2600 3 Internal paint 2200 2200 4 Internal finish carpentry 2100 2200 3 Ext paint 2000 2100, 2300 2 Cabinets 1900 1900, 2400, 2500 4 Finish drywall 1800 1800 4 Hang drywall 1700 1500 2 Ext finish carpentry 1600 20000 3 Ext siding 1500 1000, 1600, 2700 3 Shingles 1400 1000 3 Rough Electrical 1300 1300 3 Rough HVAC 1200 Successors Duration (days) Description Act. ID 2 Punch list 2800 2800 4 Grading and landscaping 2700 2800 3 Flooring 2600 2200 2 Finish electrical 2500
  • 60. A SUCCESSFUL CONSTRUCTION: WITHIN BUDGET ON TIME MEETS OWNWER SPECIFIED NEEDS AND REQUIREMENTS WORK WITH FLEXIBILITY
  • 61. Daniel W.Halpin (2006); Construction Management; Third Edition; John Wiley & Sons; USA. Andrew A. L. Tan (2004); Why Projects Fail? 1001 reasons; Venton Publishing (M) Sdn. Bhd.; Selangor, Malaysia.