BUILDING CONSTRUCTION AND MATERIALS
BY:-
PROF. SAGAR R. RAUT
ASST. PROFESSOR
CIVIL ENGINEERING DEPARTMENT
JAGADAMBHA COLLEGE OF ENGINEERING AND TECHNOLOGY,
YAVATMAL
What is Formwork?
o It should be capable of carrying all imposed dead and
live loads apart from its own weight.
o Formwork is a mould including all supporting
structures, used to shape and support the concrete until it
attains sufficient strength to carry its own weight.
Formwork is commonly made of
o Steel
o Timber
TIMBER FORMWORK
STEEL FORMWORK
 Formwork has been in use since the beginning of
concrete construction.
 New materials such as steel, plastics and fibreglass
are used in formwork.
 Greater attention is being given to the design,
fabrication, erection and Stripping of formwork
 Formwork is designed according to The IS
standards for formwork.
Qualities of Formwork
 It should be water tight.
 It should be strong.
 It can be reusable.
 Its contact surface should be uniform.
 It should be according to the size of member.
• In order to successfully carry out its function,
formwork must achieve a balance of following
requirements:
• Containment
• Strength
• Resistance To Leakage
• Accuracy
• Ease of Handling
• Finish and Reuse Potential
• Access For Concrete
• Economy
Requirements of Formwork
• Containment: formwork must be capable of shaping and
supporting the fluid concrete until it cures.
• Strength: formwork must be capable of safely withstanding
without distortion or danger the dead weight of the fluid
concrete is placed on it, labour weight, equipment weight and
any environmental loadings.
Requirements of Formwork
• Ease of Handling: form panels and units should be designed
so that their maximum size does not exceed that which can be
easily handled by hand or mechanical means.
– In addition all formwork must also be designed and
constructed to include facilities for adjustments, levelling,
easing and striking without damage to the form work or
concrete.
Requirements of Formwork
• Economy: all the formwork is very expensive. On average about
25% of the total cost of any finished concrete unit or element can be
attributed to its formwork; of this just over 40% can be taken for
material for formwork and 60% for labour.
– The formwork designer must therefore not only consider the
maximum number of times that any form can be reused, but also
produce a design that will minimize the time taken for erection
and striking.
Requirements of Formwork
Requirements of formwork:
 Material should be cheap and re usable,
 It should be practically water proof, so that it should not absorb
water from concrete,
 Swelling and shrinkage should be minimum,
 Strong enough to with stand all external loads,
 Deflection should be minimum,
 Surface should be smooth, and afford easy striping,
 Light in weight, so that easy to transfer,
 Joints should be stiff, so that lateral deformation and leak is minimum
.
Major objectives considered in
formwork:
 Quality
 Safety
Economy
 Quality:
Forms must be designed and built with sufficient stiffness
and accuracy so that the size, shape, position, and finish of
the cast concrete are maintained.
Safety:
Forms must be built sufficient strength and factor of
safety so that they have the capable of all supporting loads.
 Economy:
Forms must be built efficiently, minimizing time and
cost.
Major objectives considered in formwork:
a) Assembly and erection .
b) Concrete placement.
c) Stripping and dismantling.
Three stages in the process :
Formwork detail for different structural
members
In concrete construction formwork is commonly
provided for the following structural members.
o Wall
o Column
o Slabs & Beams
o Stairs
o Chimneys
o Water tanks
o Cooling Towers
Formwork for Wall
 It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
 After completing one side of formwork reinforcement is
provided at the place then the second side formwork is
provided.
Fig. formwork for wall
Formwork for Column
• It consists of the following
– Side & End Planks
– Yoke
– Nut & Bolts
• Two end & two side planks
are joined by the yokes and
bolts.
Formwork for columns
• It consists of
– Sole plates
– Wedges
– Props
– Head tree
– Planks
– Batten
– Ledgers
• Beam formwork rests on head tree
• Slab form work rests on battens and joists
• If prop height are more than 8’ provide horizontal
braces.
• Formwork for Slabs & beams:
Formwork, by prof. sagar raut
Lintel or Beam Formwork:
• FORMWORK FOR SLAB:
• FORMWORK FOR STAIRS:
• It consists of
– Vertical & inclined
posts
– Inclined members
-- Wooden Planks or
sheeting
– Stringer
– Riser Planks
• FORMWORK FOR STAIRS:
• FORMWORK FOR SPIRAL STAIRS :
• Removal of formwork:
Time of formwork removal depends on the following
factors
1. Type of Cement
Rapid hardening cements require lesser time as compared
to OPC (Ordinary Portland Cement)
2. Ratio of concrete mix
Rich ratio concrete gain strength earlier as compared to
weak ratio concrete.
3. Weather condition
Hydration process accelerates in hot weather conditions as
compared to cold and humid weather conditions..
Time of Removal of formwork:
• First free end's support
should be removed.
• And then from right to left
it should be proceed.
• If we are removing from
the mid span then it will
act as a prop cantilever.
Cantilever slab
• In simply supported
we have to remove the
support from the mid
span to the ends.
• To meet the design
behavior.
Simply supported slab
• Maintenance of formwork:`
• Due to continuous use wooden planks & steel plates
surfaces become uneven and require maintenance.
• For wooden formwork use cardboard or plastic fiber
board. Bolt hole places must also be repaired.
• For steel formwork plates must be leveled by mallet and
loose corners must be welded.
• Cost of formwork
For normal works cost of formwork is about 20%-30% of the
concrete cost.
For special works cost of formwork is about 50%-60% of the
concrete cost.
Formwork cost is controlled by the following factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges.
• Advantages of steel form work:
 It can be used for a no. of times.
 It is non absorbent.
 Smooth finish surface obtained.
 No shrinkage of formwork occurs.
 Easy to use.
 Its volume is less
 Its strength is more.
• LOADS ON FORMWORK:
• Dead load
 Self weight of formwork
 Pressure and loads from fresh concrete
 Reinforcement
• Imposed load
 Construction workers
 Stacking of materials
• Horizontal loads
• Environmental loads
 Accidental loads
 Wind loads
• References
• R.C.C Design by B. C.Punmia
Thank you
THANK
YOU

More Related Content

PPTX
Formwork in civil engineering
PPTX
Form-work in construction
PPT
2.7 BRIDGE LAUNCHING.ppt
PPT
Formwork
PPTX
6. FORMWORK (ACE) 2160601 GTU
PDF
Maintenance and repair strategies
PPTX
Chapter 1 repair stratergies
Formwork in civil engineering
Form-work in construction
2.7 BRIDGE LAUNCHING.ppt
Formwork
6. FORMWORK (ACE) 2160601 GTU
Maintenance and repair strategies
Chapter 1 repair stratergies

What's hot (20)

PPT
blockwork
PPTX
Formwork
PPTX
Seismic retrofitting techniques of rcc
PPTX
FORMWORK.pptx
PDF
Shear walls
PPTX
Earthquake damages
PPTX
Formwork
PDF
Prestressed concrete
PPTX
Materials and Techniques For Repair
PPT
Chimney one go
PPT
Failures In Masonry Structures Lec 1
PDF
Formwork Design-Introduction.pdf
PPTX
Brick Masonry
PPTX
Jacketing (RR&S)
PPT
Brick masonary
PPT
Formwork
PPTX
Types of formwork
PPTX
Formwork Presentation for Construction Technology
PPTX
REPAIRS AND REHABILITATION OF STRUCTURES
PDF
blockwork
Formwork
Seismic retrofitting techniques of rcc
FORMWORK.pptx
Shear walls
Earthquake damages
Formwork
Prestressed concrete
Materials and Techniques For Repair
Chimney one go
Failures In Masonry Structures Lec 1
Formwork Design-Introduction.pdf
Brick Masonry
Jacketing (RR&S)
Brick masonary
Formwork
Types of formwork
Formwork Presentation for Construction Technology
REPAIRS AND REHABILITATION OF STRUCTURES
Ad

Similar to Formwork, by prof. sagar raut (20)

PPTX
Formwork
PPTX
Formwork
PPTX
Formwork
PPTX
formwork as per IS Code Slip and moving formwork..pptx
PPTX
PPTX
FormWork
PDF
Farmwork shuttering
PDF
formwork Bco (1) final.pdf
PPTX
Chapter 5 formwork
PPTX
Formwork construction in structures
DOC
Gurme santoshkumar
PPTX
Introduction and types of Form Work in civil engineering
PDF
Form Work
PPT
formwork-Building different structural memebers
PPTX
Steel formwork
PDF
types of formwork.pdf
PPTX
chapter 3_ Fresh Concrete Pressure on Formwork.pptx
PDF
All you need to know about Construction Formwork
Formwork
Formwork
Formwork
formwork as per IS Code Slip and moving formwork..pptx
FormWork
Farmwork shuttering
formwork Bco (1) final.pdf
Chapter 5 formwork
Formwork construction in structures
Gurme santoshkumar
Introduction and types of Form Work in civil engineering
Form Work
formwork-Building different structural memebers
Steel formwork
types of formwork.pdf
chapter 3_ Fresh Concrete Pressure on Formwork.pptx
All you need to know about Construction Formwork
Ad

More from SAGAR RAUT (6)

PPTX
Canal MASONRY WORK
PPTX
Painting and colouring
PPTX
Lintels and arches
PPTX
Door and windows, by Prof. Sagar Raut
PPT
Spillways & energy dissipator
PPTX
Canal irrigation
Canal MASONRY WORK
Painting and colouring
Lintels and arches
Door and windows, by Prof. Sagar Raut
Spillways & energy dissipator
Canal irrigation

Recently uploaded (20)

PPTX
Solar energy pdf of gitam songa hemant k
PDF
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
PPTX
CS6006 - CLOUD COMPUTING - Module - 1.pptx
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PPTX
Micro1New.ppt.pptx the main themes if micro
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PDF
Computer System Architecture 3rd Edition-M Morris Mano.pdf
PDF
Present and Future of Systems Engineering: Air Combat Systems
PPTX
Cisco Network Behaviour dibuywvdsvdtdstydsdsa
PDF
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PPTX
CT Generations and Image Reconstruction methods
PPTX
Principal presentation for NAAC (1).pptx
PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PPT
Programmable Logic Controller PLC and Industrial Automation
PPTX
MAD Unit - 3 User Interface and Data Management (Diploma IT)
PDF
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
PDF
Unit1 - AIML Chapter 1 concept and ethics
PPTX
chapter 1.pptx dotnet technology introduction
Solar energy pdf of gitam songa hemant k
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
CS6006 - CLOUD COMPUTING - Module - 1.pptx
August -2025_Top10 Read_Articles_ijait.pdf
Environmental studies, Moudle 3-Environmental Pollution.pptx
Micro1New.ppt.pptx the main themes if micro
20250617 - IR - Global Guide for HR - 51 pages.pdf
Computer System Architecture 3rd Edition-M Morris Mano.pdf
Present and Future of Systems Engineering: Air Combat Systems
Cisco Network Behaviour dibuywvdsvdtdstydsdsa
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
CT Generations and Image Reconstruction methods
Principal presentation for NAAC (1).pptx
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
Programmable Logic Controller PLC and Industrial Automation
MAD Unit - 3 User Interface and Data Management (Diploma IT)
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
Unit1 - AIML Chapter 1 concept and ethics
chapter 1.pptx dotnet technology introduction

Formwork, by prof. sagar raut

  • 1. BUILDING CONSTRUCTION AND MATERIALS BY:- PROF. SAGAR R. RAUT ASST. PROFESSOR CIVIL ENGINEERING DEPARTMENT JAGADAMBHA COLLEGE OF ENGINEERING AND TECHNOLOGY, YAVATMAL
  • 2. What is Formwork? o It should be capable of carrying all imposed dead and live loads apart from its own weight. o Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. Formwork is commonly made of o Steel o Timber
  • 5.  Formwork has been in use since the beginning of concrete construction.  New materials such as steel, plastics and fibreglass are used in formwork.  Greater attention is being given to the design, fabrication, erection and Stripping of formwork  Formwork is designed according to The IS standards for formwork.
  • 6. Qualities of Formwork  It should be water tight.  It should be strong.  It can be reusable.  Its contact surface should be uniform.  It should be according to the size of member.
  • 7. • In order to successfully carry out its function, formwork must achieve a balance of following requirements: • Containment • Strength • Resistance To Leakage • Accuracy • Ease of Handling • Finish and Reuse Potential • Access For Concrete • Economy Requirements of Formwork
  • 8. • Containment: formwork must be capable of shaping and supporting the fluid concrete until it cures. • Strength: formwork must be capable of safely withstanding without distortion or danger the dead weight of the fluid concrete is placed on it, labour weight, equipment weight and any environmental loadings. Requirements of Formwork
  • 9. • Ease of Handling: form panels and units should be designed so that their maximum size does not exceed that which can be easily handled by hand or mechanical means. – In addition all formwork must also be designed and constructed to include facilities for adjustments, levelling, easing and striking without damage to the form work or concrete. Requirements of Formwork
  • 10. • Economy: all the formwork is very expensive. On average about 25% of the total cost of any finished concrete unit or element can be attributed to its formwork; of this just over 40% can be taken for material for formwork and 60% for labour. – The formwork designer must therefore not only consider the maximum number of times that any form can be reused, but also produce a design that will minimize the time taken for erection and striking. Requirements of Formwork
  • 11. Requirements of formwork:  Material should be cheap and re usable,  It should be practically water proof, so that it should not absorb water from concrete,  Swelling and shrinkage should be minimum,  Strong enough to with stand all external loads,  Deflection should be minimum,  Surface should be smooth, and afford easy striping,  Light in weight, so that easy to transfer,  Joints should be stiff, so that lateral deformation and leak is minimum .
  • 12. Major objectives considered in formwork:  Quality  Safety Economy
  • 13.  Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained. Safety: Forms must be built sufficient strength and factor of safety so that they have the capable of all supporting loads.  Economy: Forms must be built efficiently, minimizing time and cost. Major objectives considered in formwork:
  • 14. a) Assembly and erection . b) Concrete placement. c) Stripping and dismantling. Three stages in the process :
  • 15. Formwork detail for different structural members In concrete construction formwork is commonly provided for the following structural members. o Wall o Column o Slabs & Beams o Stairs o Chimneys o Water tanks o Cooling Towers
  • 16. Formwork for Wall  It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges  After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 18. Formwork for Column • It consists of the following – Side & End Planks – Yoke – Nut & Bolts • Two end & two side planks are joined by the yokes and bolts.
  • 20. • It consists of – Sole plates – Wedges – Props – Head tree – Planks – Batten – Ledgers • Beam formwork rests on head tree • Slab form work rests on battens and joists • If prop height are more than 8’ provide horizontal braces. • Formwork for Slabs & beams:
  • 22. Lintel or Beam Formwork:
  • 24. • FORMWORK FOR STAIRS: • It consists of – Vertical & inclined posts – Inclined members -- Wooden Planks or sheeting – Stringer – Riser Planks
  • 25. • FORMWORK FOR STAIRS:
  • 26. • FORMWORK FOR SPIRAL STAIRS :
  • 27. • Removal of formwork: Time of formwork removal depends on the following factors 1. Type of Cement Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) 2. Ratio of concrete mix Rich ratio concrete gain strength earlier as compared to weak ratio concrete. 3. Weather condition Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions..
  • 28. Time of Removal of formwork:
  • 29. • First free end's support should be removed. • And then from right to left it should be proceed. • If we are removing from the mid span then it will act as a prop cantilever. Cantilever slab
  • 30. • In simply supported we have to remove the support from the mid span to the ends. • To meet the design behavior. Simply supported slab
  • 31. • Maintenance of formwork:` • Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. • For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. • For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 32. • Cost of formwork For normal works cost of formwork is about 20%-30% of the concrete cost. For special works cost of formwork is about 50%-60% of the concrete cost. Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges.
  • 33. • Advantages of steel form work:  It can be used for a no. of times.  It is non absorbent.  Smooth finish surface obtained.  No shrinkage of formwork occurs.  Easy to use.  Its volume is less  Its strength is more.
  • 34. • LOADS ON FORMWORK: • Dead load  Self weight of formwork  Pressure and loads from fresh concrete  Reinforcement • Imposed load  Construction workers  Stacking of materials • Horizontal loads • Environmental loads  Accidental loads  Wind loads
  • 35. • References • R.C.C Design by B. C.Punmia