PILE LOAD TEST
Load Test on Piles – Methods of Pile Load Test
Prepared By: Dharmendra Singh
 Load tests on piles are conducted on completion of 28 days after casting
of piles.
 Two types of tests namely initial and routine tests, for each type of
loading viz. vertical, horizontal (lateral) pull out, are performed on piles.
 Initial Load Tests on Piles
• This test is performed to confirm the design load calculations and to
provide guidelines for setting up the limits of acceptance for routine
tests. It also gives an idea of the suitability of the piling system. Initial
Test on piles are to be carried out at one or more locations depending
on the number of piles required.
•
Load applied for the initial (cyclic) load test is 2.5 times the safe
carrying capacity of the pile. Loading for Initial Tests is conducted as
per Appendix ‘A’ Clause 6.3 of IS-2911 Part IV.
 Routine Load Tests on Piles
• Selection of piles for the Routine Test is done based on number of piles required
subject to maximum of ½% of total number of piles required. The number of
tests may be increased to 2% depending on the nature / type of structure. The
test load applied is 1½ times the safe carrying capacity of the pile.
• he Maintained load method as described in Clause 6.2 of IS-2911 (Part IV) – 1985
shall be followed for loading for the Routine Tests.
• This test will be performed for the following purposes:
• a) To ensure the safe load capacity of piles
• b) Detection of any unusual performance contrary to the findings of the Initial
Test.
• The tests shall be performed at the cut-off level only. A detailed report for the test
result is prepared.
 Vertical Load Tests on Piles
• This test will be carried out as stipulated in IS-2911 (Part IV)
1995.
 Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable.
The reinforcement shall be cut and head levelled with Plaster of Paris. A bearing plate with a
hole shall be placed on the head for the jack to rest.
 Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor
piles (if required) shall be placed at a center to center distance of 3 times the pile diameter
subject to a minimum distance of 2 M.
 Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm
sensitivity shall be used. They shall be positioned at equal distance around the piles on datum
bars resting on immovable supports at a distance of 3D (min. of 1.5 m) where D is the diameter
of pile or circumscribing circle for non-circular piles.
 Application of load- It shall be applied as specified depending on the type of test (routine /
initial). Each load shall be maintained till the rate of displacement of the pile top is either 0.1
mm in the first 30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The
next increment in the load shall be applied on achieving the aforesaid criterion.
The test load shall be maintained for 24 hours.
 Initial Tests– The safe load on a single pile shall be the least of the following:
(i) 2/3rd of the final load at which the total displacement attains a value of 12 mm unless
otherwise required in a given case on the basis of nature and type of structure in which
case, the safe load should be corresponding to the stated total displacement permissible.
(ii) 50% of the final load at which the total displacement equals 10% of the pile diameter in
case of uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles.
Routine Tests – Acceptance
The maximum settlement at test load should not exceed 12 mm.
 Lateral Load Tests on Piles
 The jack should be placed horizontally, between two piles. The load on the jack shall be the
same on both the piles. The load will be applied in increments of 20% of the estimated safe
load and at the cut off level. The load will be increased after the rate of displacement is
nearer to 0.1 mm per 30 minutes.
 If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall measure
the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm apart
vertically, shall be set up and the lateral displacement of the cut-off level calculated by similar
triangles.
 The safe load on the pile shall be the least of the following:
a) 50% of the final load at which the total displacement increases to 12 mm.
b) Final load at which the total displacement corresponds to 5 mm.
*Thank You*

More Related Content

PPTX
Pile load test
PPTX
Intellectual Property Rights
PPT
Dynamic pile testing
PPTX
Introduction to Concrete
PPTX
Geosynthetics
PPSX
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
PPTX
Pile foundation
PDF
Astm d4541 standard pull off test for coatings
Pile load test
Intellectual Property Rights
Dynamic pile testing
Introduction to Concrete
Geosynthetics
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Pile foundation
Astm d4541 standard pull off test for coatings

What's hot (20)

PPTX
Plate load test and its interpretations
PPTX
Plate load test ppt
PPTX
Plate load test
PPTX
Index properties
PPTX
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
PPTX
Standard Penetration Test
PPT
Bearing capacity of soil final
PPTX
Standard penetration test (spt)
PPTX
Shape tests of aggregate
PPTX
Box culvert
PPTX
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
PPT
Compressive strength in concrete test
PPTX
Field control of compaction and compaction Equipment
PDF
Rcc box culvert methodology and designs including computer method
PPTX
Earth pressure
PPSX
Design of singly reinforced.
PPTX
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
PPTX
Rcc design by working stress method
PPTX
Design of floor slab
PPTX
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Plate load test and its interpretations
Plate load test ppt
Plate load test
Index properties
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Standard Penetration Test
Bearing capacity of soil final
Standard penetration test (spt)
Shape tests of aggregate
Box culvert
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Compressive strength in concrete test
Field control of compaction and compaction Equipment
Rcc box culvert methodology and designs including computer method
Earth pressure
Design of singly reinforced.
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Rcc design by working stress method
Design of floor slab
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Ad

Similar to Pile load test ppt (20)

PPT
METHOD AND ASSESSMENT FOR LOAD TEST.ppt
PPTX
ASTM E 09(COMPRESSION TEST)
PPTX
Unit II: Design of Static Equipment Foundations
PPTX
PILE LOAD TEST-abhishek.pptx
PDF
Astm d2938 unconfined compressive strength
PDF
publication_1580218342.pdf
PDF
178749411 astm-d-1633-00-standard-methods-for-compressive-strength-of-molded-...
PDF
A triaxial test is a laboratory procedure
DOCX
4-pile foundation.docx pile foundation.docx
PDF
D1004.pdf
PPTX
California bearingratio test
PPTX
Compression_Flexural_and_Tensile_tests.pptx
DOCX
Tri axial test
PPTX
DETERMINATION OF UNCONFINED COMPRESSIVE STRENGTH OF SOIL
PPTX
PILE FOUNDATION.pptx
PPTX
Vicker test
METHOD AND ASSESSMENT FOR LOAD TEST.ppt
ASTM E 09(COMPRESSION TEST)
Unit II: Design of Static Equipment Foundations
PILE LOAD TEST-abhishek.pptx
Astm d2938 unconfined compressive strength
publication_1580218342.pdf
178749411 astm-d-1633-00-standard-methods-for-compressive-strength-of-molded-...
A triaxial test is a laboratory procedure
4-pile foundation.docx pile foundation.docx
D1004.pdf
California bearingratio test
Compression_Flexural_and_Tensile_tests.pptx
Tri axial test
DETERMINATION OF UNCONFINED COMPRESSIVE STRENGTH OF SOIL
PILE FOUNDATION.pptx
Vicker test
Ad

Recently uploaded (20)

PPTX
CT Generations and Image Reconstruction methods
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PPTX
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
PDF
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
PDF
Cryptography and Network Security-Module-I.pdf
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PDF
Mechanics of materials week 2 rajeshwari
PPTX
CS6006 - CLOUD COMPUTING - Module - 1.pptx
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PDF
Computer System Architecture 3rd Edition-M Morris Mano.pdf
PDF
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
PDF
Micro 4 New.ppt.pdf a servay of cells and microorganism
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PPTX
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
PPTX
MAD Unit - 3 User Interface and Data Management (Diploma IT)
PDF
Beginners-Guide-to-Artificial-Intelligence.pdf
PDF
Research on ultrasonic sensor for TTU.pdf
PDF
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
PPTX
Cisco Network Behaviour dibuywvdsvdtdstydsdsa
PDF
Designing Fault-Tolerant Architectures for Resilient Oracle Cloud ERP and HCM...
CT Generations and Image Reconstruction methods
Environmental studies, Moudle 3-Environmental Pollution.pptx
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
Unit I -OPERATING SYSTEMS_SRM_KATTANKULATHUR.pptx.pdf
Cryptography and Network Security-Module-I.pdf
20250617 - IR - Global Guide for HR - 51 pages.pdf
Mechanics of materials week 2 rajeshwari
CS6006 - CLOUD COMPUTING - Module - 1.pptx
Environmental studies, Moudle 3-Environmental Pollution.pptx
Computer System Architecture 3rd Edition-M Morris Mano.pdf
[jvmmeetup] next-gen integration with apache camel and quarkus.pdf
Micro 4 New.ppt.pdf a servay of cells and microorganism
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
MAD Unit - 3 User Interface and Data Management (Diploma IT)
Beginners-Guide-to-Artificial-Intelligence.pdf
Research on ultrasonic sensor for TTU.pdf
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
Cisco Network Behaviour dibuywvdsvdtdstydsdsa
Designing Fault-Tolerant Architectures for Resilient Oracle Cloud ERP and HCM...

Pile load test ppt

  • 1. PILE LOAD TEST Load Test on Piles – Methods of Pile Load Test Prepared By: Dharmendra Singh
  • 2.  Load tests on piles are conducted on completion of 28 days after casting of piles.  Two types of tests namely initial and routine tests, for each type of loading viz. vertical, horizontal (lateral) pull out, are performed on piles.
  • 3.  Initial Load Tests on Piles • This test is performed to confirm the design load calculations and to provide guidelines for setting up the limits of acceptance for routine tests. It also gives an idea of the suitability of the piling system. Initial Test on piles are to be carried out at one or more locations depending on the number of piles required. • Load applied for the initial (cyclic) load test is 2.5 times the safe carrying capacity of the pile. Loading for Initial Tests is conducted as per Appendix ‘A’ Clause 6.3 of IS-2911 Part IV.
  • 4.  Routine Load Tests on Piles • Selection of piles for the Routine Test is done based on number of piles required subject to maximum of ½% of total number of piles required. The number of tests may be increased to 2% depending on the nature / type of structure. The test load applied is 1½ times the safe carrying capacity of the pile. • he Maintained load method as described in Clause 6.2 of IS-2911 (Part IV) – 1985 shall be followed for loading for the Routine Tests. • This test will be performed for the following purposes: • a) To ensure the safe load capacity of piles • b) Detection of any unusual performance contrary to the findings of the Initial Test. • The tests shall be performed at the cut-off level only. A detailed report for the test result is prepared.
  • 5.  Vertical Load Tests on Piles • This test will be carried out as stipulated in IS-2911 (Part IV) 1995.
  • 6.  Pile Head – The pile head shall be chipped off till sound concrete is met wherever applicable. The reinforcement shall be cut and head levelled with Plaster of Paris. A bearing plate with a hole shall be placed on the head for the jack to rest.  Reaction- Kentledge shall be suitably designed to get the desired reaction on the piles. Anchor piles (if required) shall be placed at a center to center distance of 3 times the pile diameter subject to a minimum distance of 2 M.  Settlement- 2 dial gauges for a single pile and 4 dial gauges for a group of piles with 0.01 mm sensitivity shall be used. They shall be positioned at equal distance around the piles on datum bars resting on immovable supports at a distance of 3D (min. of 1.5 m) where D is the diameter of pile or circumscribing circle for non-circular piles.  Application of load- It shall be applied as specified depending on the type of test (routine / initial). Each load shall be maintained till the rate of displacement of the pile top is either 0.1 mm in the first 30 minutes or 0.2 mm in the first one hour or 2 hours whichever occurs first. The next increment in the load shall be applied on achieving the aforesaid criterion.
  • 7. The test load shall be maintained for 24 hours.  Initial Tests– The safe load on a single pile shall be the least of the following: (i) 2/3rd of the final load at which the total displacement attains a value of 12 mm unless otherwise required in a given case on the basis of nature and type of structure in which case, the safe load should be corresponding to the stated total displacement permissible. (ii) 50% of the final load at which the total displacement equals 10% of the pile diameter in case of uniform diameter piles or 7.5% of the bulb diameter in case of under reamed piles. Routine Tests – Acceptance The maximum settlement at test load should not exceed 12 mm.
  • 8.  Lateral Load Tests on Piles
  • 9.  The jack should be placed horizontally, between two piles. The load on the jack shall be the same on both the piles. The load will be applied in increments of 20% of the estimated safe load and at the cut off level. The load will be increased after the rate of displacement is nearer to 0.1 mm per 30 minutes.  If the cut-off level is approachable, one dial gauge exactly at the cut-off level shall measure the displacement. In case the cut-off level is not approachable, 2 dial gauges 30 cm apart vertically, shall be set up and the lateral displacement of the cut-off level calculated by similar triangles.  The safe load on the pile shall be the least of the following: a) 50% of the final load at which the total displacement increases to 12 mm. b) Final load at which the total displacement corresponds to 5 mm.