Case # 1: A Day of the Life   Group: D Keshani Malindi Chanaka Reeza Fazily
Overview of the Case Study   Rachel is one of project managers in an information systems project  Case study mainly discussed the way a project manager allocates her time to spend one day in her life  20 sec
Q1: How effectively do you think Rachel spent her day?
45 sec   Characteristics of a project  Examples from the case study Project is a complex, non routine, one time effort that is limited by time, budget, resources and performance specifications and its implemented to meet the customer requirements  Review project reports and prepare for the weekly status meeting  - 25 min Discuss the project with her superiors – 20 min Participate in the progress review meeting – 45 min Identify and respond to the issues arise in the project –  20 min
25 sec Characteristics of a non project  Examples from the case study Non project is ordinary daily work that requires doing the same work repetitively. Socializing and catching up with personal news – 10 min Reviewing the day’s schedule  - 15 min
25 sec   Characteristics of a quasi project  Examples from the case study No specific task is defined  Specific time limit has not been provided Likely to arise in temporary situations  Performance schedules and budgets have been implied . Updating boss on key events of the day
40 sec
Final Decision…….. Efficiency =  Direct project related work  * 100 Total spend time =  340  * 100 515 = 66.02% Rachel is an efficient project manager for some extent.  She has an efficiency of 66.02% of the project. She has only spend her time on non-project activities are 23.30%.  30 sec
Q2: What does the case tell you about what it is like to be a project manager?
Project Manager Provides Direction, Coordination and Integration to the Project Team   Solve out the problems and direct the team members for the solution Discuss with the team members when ever got an issue and get their ideas too  Keeping Project status meetings, small discussions to coordinate and ingrate  30 sec
Organization Planning Great relationship with individuals and Organizational Structure Friendly relationship with other managers, team members and individuals  Coordinates her boss and Updates every thing to her boss Maintains great integration with other managers when solves an issue  Ex:  Integration with senior marketing manager  30 sec
Improving the projects success rate with better leadership   “ The project leadership is shaping a team of diverse individuals a force that produce an effective output/measurable project results.” (Dr. Karen McGraw ) Leading courageously Influencing others  Act with resilience   1 min
1 min   Essential Leadership skills  Examples from the case  Leading courageously –  being important and challenging others to make tough choices  Frequently interacts with her project team, identifies the issues and response to those effectively. E.g. meeting Mary Influencing others  - As a good leader project manager must be able to provide convincing responses to the ideas and  suggestions and gain the support from the stakeholders.  request John to investigate the problem immediately. she decides to get equipments for the project through express delivery quite earlier than they planned. Act with resilience- He/she must concern on the project goals and should not give up the project at any cost. When Rachel recognized that the client’s managers request for additional features that were not included in the scope of project she tries to identify the root causes and take possible steps to solve the issue without giving up the project
Managing the overall schedule to ensure work is assigned and completed on time and within budget - She has been helping Victoria on her project as it was behind the projected time. Identifying, tracking, managing and resolving project issues - She attended meeting in order to find out the project issue and try to fix them. - Also she has found out that several clients are requesting features that are not on the project, and she said her team members she will get on this issue right away.  1 min
Project managers has a huge responsibility and authority over a project. This was clear in the case when Rachel had to deal with client firm’s additional requests where she has to manage performance of the extended requirements, time and cost to finish the project successfully. Man in between One good example is where Rachel going and talking to the purchasing agent assigned to her  project, on getting necessary equipments  to the project site earlier than planned. Also where she walks down to the marketing managers office to clarify on the problem they came up with.  1 min
Reference  Projectsmart.co.uk,2001,  Improving Project Success Rates with Better Leadership  [online accessed date 21 st  Feb 2010]URL: Leadershiphttp://www.projectsmart.co.uk/improving-project-success-rates-with-better-leadership.html
THANK YOU!!!!!!!!!!

A Day of the Life of a Project Manager

  • 1.
    Case # 1:A Day of the Life Group: D Keshani Malindi Chanaka Reeza Fazily
  • 2.
    Overview of theCase Study Rachel is one of project managers in an information systems project Case study mainly discussed the way a project manager allocates her time to spend one day in her life 20 sec
  • 3.
    Q1: How effectivelydo you think Rachel spent her day?
  • 4.
    45 sec Characteristics of a project Examples from the case study Project is a complex, non routine, one time effort that is limited by time, budget, resources and performance specifications and its implemented to meet the customer requirements Review project reports and prepare for the weekly status meeting - 25 min Discuss the project with her superiors – 20 min Participate in the progress review meeting – 45 min Identify and respond to the issues arise in the project – 20 min
  • 5.
    25 sec Characteristicsof a non project Examples from the case study Non project is ordinary daily work that requires doing the same work repetitively. Socializing and catching up with personal news – 10 min Reviewing the day’s schedule - 15 min
  • 6.
    25 sec Characteristics of a quasi project Examples from the case study No specific task is defined Specific time limit has not been provided Likely to arise in temporary situations Performance schedules and budgets have been implied . Updating boss on key events of the day
  • 7.
  • 8.
    Final Decision…….. Efficiency= Direct project related work * 100 Total spend time = 340 * 100 515 = 66.02% Rachel is an efficient project manager for some extent. She has an efficiency of 66.02% of the project. She has only spend her time on non-project activities are 23.30%. 30 sec
  • 9.
    Q2: What doesthe case tell you about what it is like to be a project manager?
  • 10.
    Project Manager ProvidesDirection, Coordination and Integration to the Project Team Solve out the problems and direct the team members for the solution Discuss with the team members when ever got an issue and get their ideas too Keeping Project status meetings, small discussions to coordinate and ingrate 30 sec
  • 11.
    Organization Planning Greatrelationship with individuals and Organizational Structure Friendly relationship with other managers, team members and individuals Coordinates her boss and Updates every thing to her boss Maintains great integration with other managers when solves an issue Ex: Integration with senior marketing manager 30 sec
  • 12.
    Improving the projectssuccess rate with better leadership “ The project leadership is shaping a team of diverse individuals a force that produce an effective output/measurable project results.” (Dr. Karen McGraw ) Leading courageously Influencing others Act with resilience 1 min
  • 13.
    1 min Essential Leadership skills Examples from the case Leading courageously – being important and challenging others to make tough choices Frequently interacts with her project team, identifies the issues and response to those effectively. E.g. meeting Mary Influencing others - As a good leader project manager must be able to provide convincing responses to the ideas and suggestions and gain the support from the stakeholders. request John to investigate the problem immediately. she decides to get equipments for the project through express delivery quite earlier than they planned. Act with resilience- He/she must concern on the project goals and should not give up the project at any cost. When Rachel recognized that the client’s managers request for additional features that were not included in the scope of project she tries to identify the root causes and take possible steps to solve the issue without giving up the project
  • 14.
    Managing the overallschedule to ensure work is assigned and completed on time and within budget - She has been helping Victoria on her project as it was behind the projected time. Identifying, tracking, managing and resolving project issues - She attended meeting in order to find out the project issue and try to fix them. - Also she has found out that several clients are requesting features that are not on the project, and she said her team members she will get on this issue right away. 1 min
  • 15.
    Project managers hasa huge responsibility and authority over a project. This was clear in the case when Rachel had to deal with client firm’s additional requests where she has to manage performance of the extended requirements, time and cost to finish the project successfully. Man in between One good example is where Rachel going and talking to the purchasing agent assigned to her project, on getting necessary equipments to the project site earlier than planned. Also where she walks down to the marketing managers office to clarify on the problem they came up with. 1 min
  • 16.
    Reference Projectsmart.co.uk,2001, Improving Project Success Rates with Better Leadership [online accessed date 21 st Feb 2010]URL: Leadershiphttp://www.projectsmart.co.uk/improving-project-success-rates-with-better-leadership.html