Chapter 7 Push and Pull  Production Control Systems MRP  and  JIT
Push and Pull Control Systems A Push System (MRP) initiates production in anticipation of future demand Incorporates forecasts of future demand A Pull System initiates production as a reaction to present demand (JIT) Initiates production as a reaction of … demand
Difference between MRP and JIT MRP: Determine lot sizes based on future demand forecasts JIT Reduce lot sizes to eliminate waste and unnecessary buildups of inventory
MRP Basics Production Plan M aster  P roduction  S chedule (MPS) MRP system Job shop Schedule At the heart of the production plan are the  demand forecasts of end items End item: Components Raw materials Figure 7-1
Schematic of the  Productive System Fig. 7-1
Production Plan MPS : specification of the exact amounts and timing of production of each of the end items MRP  is the means by which MPS is broken down into a detailed schedule of production for each component that comprises an end item MRP results are translated into specific  shop floor schedules
Data sources for determining the MPS Firm customer orders Forecasts of future demand by item Safety stock requirements Seasonal plans Internal orders from other parts of the organization
Success of MRP Integrity and timeliness of the data The information system that supports MRP receives input from: Production Marketing And Finance Departments A smooth flow of information among these three functional areas is a key ingredient to a  successful production planning system
Major phases of the control system Phase 1: Gathering and coordinating of the information require to develop the MPS Phase 2: Determination of planned order releases using MRP Phase 3: Development of detailed shop floor schedules and resource requirements from the MRP planned order releases
The Three Major Control  Phases of the Productive System Fig. 7-2
Explosion Calculus Bill of Material (BOM) explosion Set of rules by which  gross requirements  at one level of  the product structure  are translated into a production schedule at that level and requirements at lower levels At the heart of the MRP system is the product structure  (figure 7-3): The method is best illustrated with an example:
Typical Product Structure  Diagram Fig. 7-3
Trumpet and Subassemblies Fig. 7-4
Product Structure Diagram  for Harmon Trumpet Fig. 7-5
Indented BOM 1 Trumpet 1 Bell assembly 1 Valve assembly 3 slide assemblies 3 valves
38 76 14 45 112 26 12 32 42 42 Net demand Expect 23 in inventory at the end of week 7 9 6 12 Scheduled Receipts Returns 38 76 14 45 112 26 21 38 42 77 Demand 17 16 15 14 13 12 11 10 9 8 Week
MRP calculations for Bell assembly 38 76 14 45 112 26 12 32 42 42 Planned order release (lot for lot) 38 76 14 45 112 26 12 32 42 42 Time-phased Net Reqts 38 76 14 45 112 26 12 32 42 42 Lead time Net Reqts 38 76 14 45 112 26 12 32 42 42 Gross Reqts 17 16 15 14 13 12 11 10 9 8 7 6 Week
MRP calculations for the valves 30 60 186 On-hand Inv. 96 Scheduled Receipts 114 228 42 135 336 78 36 66 Planned order release (lot for lot) 114 228 42 135 336 78 36 66 Time-phased Net Reqts 114 228 42 135 336 78 36 66 0 0 Net Reqts 114 228 42 135 336 78 36 96 126 126 Gross Reqts 13 12 11 10 9 8 7 6 5 4 3 2 Week
Incorporating the lot-sizing algorithms into the explosion calculus ___________________________________________ Week   4  5  6  7  8  9  10   11  12 13 Time-phased  42  42   32  12  26  112  45   14  76 38 Net Reqts _____________________________________________________________________________ Valve casing assembly
Starting in week 4 C(1)=132 C(2)=[132+0.6(42)]/2=78.6 C(3)=[132+0.6(42+2(32))]/3=65.2 C(4)=[132+0.6(42+2(32)+3(12))]/4=54.3 C(5)=[132+0.6(42+2(32)+3(12)+4(26))]/5=55.92      y 4 = 42+42+32+12=128 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts . 13 12 11 10 9 8 7 6 5 4 Week
Starting in week 8: C(1)=132 C(2)=[132+0.6(112)]/2=99.6 C(3)=[112+0.6(112+2(45))]/3=84.4 C(4)=[112+0.6(112+2(45)+3(14))]/4=69.6 C(5)=[112+0.6(112+2(45)+3(14)+4(76))]/5=92.16    y 8 = 26+112+45+14=197 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts. 13 12 11 10 9 8 7 6 5 4 Week
Starting in week 12: C(1)=132 C(2)=[132+0.6(38)]/2=77.4    y 12 = 76+38=114 Week 4  5  6   7  8   9  10  11   12   13 Pon  128   0  0   0  197   0   0  0   114   0 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts. 13 12 11 10 9 8 7 6 5 4 Week
Part Period Balancing Set the order horizon = the number of periods that most closely matches the total  holding cost  with the  set up cost  over that period
Order horizon   total holding cost 1 0 2 0.6(42)=25.2 3 0.6(42+2(32))=64.8 4 0.6(42+2(32)+3(12))=86.4 5 0.6(42+2(32)+3(12)+4(26))=148.8  > 132   Since 148.8 is closer to 132 than 86.4 the order horizon is 5 periods  _________________________________________________________  1 0 2 0.6(45)=27=27 3 0.6(45+2(14))=43.8 4 0.6(45+2(14)+3(76))=180.6  > 132   Since 121.2 is closer to 132 than 151.2 the order horizon is 3 periods _________________________________________________________ 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts . 13 12 11 10 9 8 7 6 5 4 Week
MRP calculations for valve casing Inv Del Ord Net Reqt 0 38 0 14 59 171 0 12 44 86 128 42 4 12 0 114 0 0 0 197 0 0 0 128 0 114 0 0 0 197 0 0 0 38 76 14 45 112 26 32 42 38 76 14 45 112 26 12 32 42 42 17 16 15 14 13 12 11 10 9 8 7 6 5
Cost comparison Silver-Meal Setup cost  = 3(132)  = $396 Holding cost = 0.6(424) = $254.40 Total cost  =  $650.40 Lot-for-lot Setup cost  = 132(10) =  $1,320 Holding cost = 0 Total cost  =  $1,320
Lower level of valve casing (valves) SM Orders  198 0  0  0  495   0  0  0  342   0  0  0  0 Time-Phased Net Reqts OH inv Receipts Gross Rqts. 0 0 0 0 342 0 0 0 495 0 0 0 198 1 0 342 0 0 0 495 0 0 0 198 0 96 96 96 0 186 96 0 342 0 0 0 591 0 0 0 384 13 12 11 10 9 8 7 6 5 4 3 2
Lot-sizing with capacity constraints r = (20,40,100,35,80,75,25) c = (60,60,60,60,60,60,60) Checking for feasibility: r 1  = 20  c 1 =60 r 1  +r 2  = 60  c 1  +c 2  = 120 r 1  +r 2  +r 3  = 160  c 1  +c 2  +c 3  = 180 r 1  +r 2  +r 3  +r 4  = 195    c 1  +c 2  +c 3  +c 4  = 240 r 1  +r 2  +r 3  +r 4  +r 5  = 275  c 1  +c 2  +c 3  +c 4  +c 5  = 300 r 1  +r 2  +r 3  +r 4  +r 5  +r 6  = 350    c 1  +c 2  +c 3  +c 4  +c 5  +c 6  = 360 r 1  +r 2  +r 3  +r 4  +r 5  +r 6  +r 7  = 375  c 1  +c 2  +c 3  +c 4  +c 5  +c 6  +c 7  = 420 Feasibility test is satisfied
Lot shifting technique r = (20,40, 100 ,35,80,75,25) r’ = ( 40 , 60 , 60 ,35,80,75,25) c = (60,60,60,60,60,60,60) _______________________________________ r’ = ( 40 , 60 , 60 ,35,80,75,25) r’ = ( 40 , 60 , 60 , 55 , 60 ,75,25) r’ = ( 50 , 60 , 60 , 60,60,60 ,25)
The improvement step K=450 and h =2 r = (100,  79,  230, 105,  3, 10,  99, 126,40) c = (120, 200, 200, 400, 300, 50, 120, 50, 30) 0 0 0 0 272 295 0 91 20 Excess capacity 30 50 120 50 28 105 200 109 100 y 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 r’
Calculations of the improvement step 0 0 0 0 272 295 0 91 20 Excess capacity 242 192 30 50 120 50 28 105 200 109 100 y 0 0 58 108 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
Calculations continued 0 0 0 0 192 295 0 91 20 Excess capacity 142 0 0 120 50 108 105 200 109 100 y 0 158 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
0 0 0 0 142 295 0 91 20 Excess capacity 300 137 0 0 120 0 158 105 200 109 100 y 0 263 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
0 0 0 0 300 137 0 91 20 Excess capacity 0 0 120 0 0 263 200 109 100 y 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
Cost comparison Initial solution Holding cost = 2 (0+30+0+0+25+65+86+10)=432 Set up cost = 9 x 450 = 4,050 Total Cost = 432 + 4,050 =  4,482 Improved solution Holding cost = 2 (0+30+0+158+155+145+166+40+0) = 2 x 694 = 1,388 Set up cost = 5 x 450 = 2,250 Total cost = 1,388 + 2,250 =  3,638

More Related Content

PPTX
Production Planning & Control
PPT
material requirement planning
PPTX
Pull Vs. Push Production
PDF
What is master production schedule
PPTX
Production planning, routing, scheduling, Activating, Monitoring
PPTX
Lean Manufacturing Tools
PPT
Lean manufacturing
Production Planning & Control
material requirement planning
Pull Vs. Push Production
What is master production schedule
Production planning, routing, scheduling, Activating, Monitoring
Lean Manufacturing Tools
Lean manufacturing

What's hot (20)

PPT
PPTX
Production capacity – planning and control
PPT
Operation scheduling
PPTX
Production planning control ppt
PPT
CAPACITY PLANNING
PPTX
Production Planning
PPT
Lean presentation ppt
PPTX
Line balancing
PPT
Production Planning and Control
PPTX
Material Requirement Planning (mrp)
PPT
Production Planning and Control
PPT
Cellular Manufacturing
PPTX
PPTX
Inventory management
 
PPT
Material requirement planning presentation
PPTX
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PPTX
types of production system
PPTX
Aggregate planning
PPT
Capacity planning
Production capacity – planning and control
Operation scheduling
Production planning control ppt
CAPACITY PLANNING
Production Planning
Lean presentation ppt
Line balancing
Production Planning and Control
Material Requirement Planning (mrp)
Production Planning and Control
Cellular Manufacturing
Inventory management
 
Material requirement planning presentation
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
types of production system
Aggregate planning
Capacity planning
Ad

Viewers also liked (11)

PPT
Master production schedule
DOCX
Push and pull -strategy
PPT
Master Scheduling
PPT
PPTX
small and effective ppt on master production schedule
PPTX
Master scheduling
PPTX
Push vs pull Advantages & Disadvantages
DOCX
Capacity Planning
PDF
Push & Pull
PPSX
Aggregate planning
PDF
Job shop scheduling
Master production schedule
Push and pull -strategy
Master Scheduling
small and effective ppt on master production schedule
Master scheduling
Push vs pull Advantages & Disadvantages
Capacity Planning
Push & Pull
Aggregate planning
Job shop scheduling
Ad

Similar to Push And Pull Production Systems Chap7 Ppt) (20)

PPT
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
PPTX
Control charts
PPTX
Log11 uitwerking opdrachten
PPT
Rancangan Acak Lengkap; Rancangan Acak Lengkap
PDF
Forecasting Assignment Help
DOCX
Arna Friend Controls II Final
PPTX
SQL Tuning 101 - Sep 2013
PDF
Gravity water supply design illustration using SW software
PPTX
Production & operarions management review
PPTX
Production & Operarions Management Compre Review
PPTX
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
PDF
Capacity Requirements Planning, Industrial Engineering
PDF
New Clustering-based Forecasting Method for Disaggregated End-consumer Electr...
PDF
Mq9 nsw 5 3 answers
PPT
Computer Arithmetic and Organization presentation
PPTX
Industrial plant optimization in reduced dimensional spaces
PDF
Writing Sample
PPTX
Design of experiment methodology
PPTX
Roll grinding Six Sigma project
PPTX
SSN Project Presentation March 2015
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
Control charts
Log11 uitwerking opdrachten
Rancangan Acak Lengkap; Rancangan Acak Lengkap
Forecasting Assignment Help
Arna Friend Controls II Final
SQL Tuning 101 - Sep 2013
Gravity water supply design illustration using SW software
Production & operarions management review
Production & Operarions Management Compre Review
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
Capacity Requirements Planning, Industrial Engineering
New Clustering-based Forecasting Method for Disaggregated End-consumer Electr...
Mq9 nsw 5 3 answers
Computer Arithmetic and Organization presentation
Industrial plant optimization in reduced dimensional spaces
Writing Sample
Design of experiment methodology
Roll grinding Six Sigma project
SSN Project Presentation March 2015

More from 3abooodi (20)

PPT
Winters Method
PDF
PPT
Value Of Information
PPT
Trend Based + Reg And Holtns
PPT
Supply Chain Integration
PPT
Single Facility Lot Size Model Elsp
PDF
Set Covering
PPT
Newsboy
PDF
Multi Echelon Inventories
PDF
Delayed Differantiation
PDF
Maximum Covering
PPT
Introduction To Scm
PPT
Delayed Product Differentiation
PPT
Forecasting
PPT
Inventory Control
PPT
Continuous Review Inventory System
PPT
An Integrated Location Inventory Model
PPT
Aggregate Production Planning
PPT
Vmi1
PPT
Role Of Robots
Winters Method
Value Of Information
Trend Based + Reg And Holtns
Supply Chain Integration
Single Facility Lot Size Model Elsp
Set Covering
Newsboy
Multi Echelon Inventories
Delayed Differantiation
Maximum Covering
Introduction To Scm
Delayed Product Differentiation
Forecasting
Inventory Control
Continuous Review Inventory System
An Integrated Location Inventory Model
Aggregate Production Planning
Vmi1
Role Of Robots

Recently uploaded (20)

PDF
sustainability-14-14877-v2.pddhzftheheeeee
PDF
sbt 2.0: go big (Scala Days 2025 edition)
PDF
4 layer Arch & Reference Arch of IoT.pdf
PDF
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
PPTX
MuleSoft-Compete-Deck for midddleware integrations
PPT
Galois Field Theory of Risk: A Perspective, Protocol, and Mathematical Backgr...
PDF
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
PDF
Taming the Chaos: How to Turn Unstructured Data into Decisions
PPTX
Microsoft User Copilot Training Slide Deck
PPTX
Training Program for knowledge in solar cell and solar industry
PPTX
AI-driven Assurance Across Your End-to-end Network With ThousandEyes
PDF
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
PDF
Co-training pseudo-labeling for text classification with support vector machi...
DOCX
Basics of Cloud Computing - Cloud Ecosystem
PPTX
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
PDF
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
PDF
Advancing precision in air quality forecasting through machine learning integ...
PDF
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf
PDF
Improvisation in detection of pomegranate leaf disease using transfer learni...
PDF
The influence of sentiment analysis in enhancing early warning system model f...
sustainability-14-14877-v2.pddhzftheheeeee
sbt 2.0: go big (Scala Days 2025 edition)
4 layer Arch & Reference Arch of IoT.pdf
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
MuleSoft-Compete-Deck for midddleware integrations
Galois Field Theory of Risk: A Perspective, Protocol, and Mathematical Backgr...
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
Taming the Chaos: How to Turn Unstructured Data into Decisions
Microsoft User Copilot Training Slide Deck
Training Program for knowledge in solar cell and solar industry
AI-driven Assurance Across Your End-to-end Network With ThousandEyes
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
Co-training pseudo-labeling for text classification with support vector machi...
Basics of Cloud Computing - Cloud Ecosystem
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
Advancing precision in air quality forecasting through machine learning integ...
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf
Improvisation in detection of pomegranate leaf disease using transfer learni...
The influence of sentiment analysis in enhancing early warning system model f...

Push And Pull Production Systems Chap7 Ppt)

  • 1. Chapter 7 Push and Pull Production Control Systems MRP and JIT
  • 2. Push and Pull Control Systems A Push System (MRP) initiates production in anticipation of future demand Incorporates forecasts of future demand A Pull System initiates production as a reaction to present demand (JIT) Initiates production as a reaction of … demand
  • 3. Difference between MRP and JIT MRP: Determine lot sizes based on future demand forecasts JIT Reduce lot sizes to eliminate waste and unnecessary buildups of inventory
  • 4. MRP Basics Production Plan M aster P roduction S chedule (MPS) MRP system Job shop Schedule At the heart of the production plan are the demand forecasts of end items End item: Components Raw materials Figure 7-1
  • 5. Schematic of the Productive System Fig. 7-1
  • 6. Production Plan MPS : specification of the exact amounts and timing of production of each of the end items MRP is the means by which MPS is broken down into a detailed schedule of production for each component that comprises an end item MRP results are translated into specific shop floor schedules
  • 7. Data sources for determining the MPS Firm customer orders Forecasts of future demand by item Safety stock requirements Seasonal plans Internal orders from other parts of the organization
  • 8. Success of MRP Integrity and timeliness of the data The information system that supports MRP receives input from: Production Marketing And Finance Departments A smooth flow of information among these three functional areas is a key ingredient to a successful production planning system
  • 9. Major phases of the control system Phase 1: Gathering and coordinating of the information require to develop the MPS Phase 2: Determination of planned order releases using MRP Phase 3: Development of detailed shop floor schedules and resource requirements from the MRP planned order releases
  • 10. The Three Major Control Phases of the Productive System Fig. 7-2
  • 11. Explosion Calculus Bill of Material (BOM) explosion Set of rules by which gross requirements at one level of the product structure are translated into a production schedule at that level and requirements at lower levels At the heart of the MRP system is the product structure (figure 7-3): The method is best illustrated with an example:
  • 12. Typical Product Structure Diagram Fig. 7-3
  • 14. Product Structure Diagram for Harmon Trumpet Fig. 7-5
  • 15. Indented BOM 1 Trumpet 1 Bell assembly 1 Valve assembly 3 slide assemblies 3 valves
  • 16. 38 76 14 45 112 26 12 32 42 42 Net demand Expect 23 in inventory at the end of week 7 9 6 12 Scheduled Receipts Returns 38 76 14 45 112 26 21 38 42 77 Demand 17 16 15 14 13 12 11 10 9 8 Week
  • 17. MRP calculations for Bell assembly 38 76 14 45 112 26 12 32 42 42 Planned order release (lot for lot) 38 76 14 45 112 26 12 32 42 42 Time-phased Net Reqts 38 76 14 45 112 26 12 32 42 42 Lead time Net Reqts 38 76 14 45 112 26 12 32 42 42 Gross Reqts 17 16 15 14 13 12 11 10 9 8 7 6 Week
  • 18. MRP calculations for the valves 30 60 186 On-hand Inv. 96 Scheduled Receipts 114 228 42 135 336 78 36 66 Planned order release (lot for lot) 114 228 42 135 336 78 36 66 Time-phased Net Reqts 114 228 42 135 336 78 36 66 0 0 Net Reqts 114 228 42 135 336 78 36 96 126 126 Gross Reqts 13 12 11 10 9 8 7 6 5 4 3 2 Week
  • 19. Incorporating the lot-sizing algorithms into the explosion calculus ___________________________________________ Week 4 5 6 7 8 9 10 11 12 13 Time-phased 42 42 32 12 26 112 45 14 76 38 Net Reqts _____________________________________________________________________________ Valve casing assembly
  • 20. Starting in week 4 C(1)=132 C(2)=[132+0.6(42)]/2=78.6 C(3)=[132+0.6(42+2(32))]/3=65.2 C(4)=[132+0.6(42+2(32)+3(12))]/4=54.3 C(5)=[132+0.6(42+2(32)+3(12)+4(26))]/5=55.92  y 4 = 42+42+32+12=128 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts . 13 12 11 10 9 8 7 6 5 4 Week
  • 21. Starting in week 8: C(1)=132 C(2)=[132+0.6(112)]/2=99.6 C(3)=[112+0.6(112+2(45))]/3=84.4 C(4)=[112+0.6(112+2(45)+3(14))]/4=69.6 C(5)=[112+0.6(112+2(45)+3(14)+4(76))]/5=92.16  y 8 = 26+112+45+14=197 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts. 13 12 11 10 9 8 7 6 5 4 Week
  • 22. Starting in week 12: C(1)=132 C(2)=[132+0.6(38)]/2=77.4  y 12 = 76+38=114 Week 4 5 6 7 8 9 10 11 12 13 Pon 128 0 0 0 197 0 0 0 114 0 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts. 13 12 11 10 9 8 7 6 5 4 Week
  • 23. Part Period Balancing Set the order horizon = the number of periods that most closely matches the total holding cost with the set up cost over that period
  • 24. Order horizon total holding cost 1 0 2 0.6(42)=25.2 3 0.6(42+2(32))=64.8 4 0.6(42+2(32)+3(12))=86.4 5 0.6(42+2(32)+3(12)+4(26))=148.8 > 132 Since 148.8 is closer to 132 than 86.4 the order horizon is 5 periods _________________________________________________________ 1 0 2 0.6(45)=27=27 3 0.6(45+2(14))=43.8 4 0.6(45+2(14)+3(76))=180.6 > 132 Since 121.2 is closer to 132 than 151.2 the order horizon is 3 periods _________________________________________________________ 38 76 14 45 112 26 12 32 42 42 Time-phased net reqts . 13 12 11 10 9 8 7 6 5 4 Week
  • 25. MRP calculations for valve casing Inv Del Ord Net Reqt 0 38 0 14 59 171 0 12 44 86 128 42 4 12 0 114 0 0 0 197 0 0 0 128 0 114 0 0 0 197 0 0 0 38 76 14 45 112 26 32 42 38 76 14 45 112 26 12 32 42 42 17 16 15 14 13 12 11 10 9 8 7 6 5
  • 26. Cost comparison Silver-Meal Setup cost = 3(132) = $396 Holding cost = 0.6(424) = $254.40 Total cost = $650.40 Lot-for-lot Setup cost = 132(10) = $1,320 Holding cost = 0 Total cost = $1,320
  • 27. Lower level of valve casing (valves) SM Orders 198 0 0 0 495 0 0 0 342 0 0 0 0 Time-Phased Net Reqts OH inv Receipts Gross Rqts. 0 0 0 0 342 0 0 0 495 0 0 0 198 1 0 342 0 0 0 495 0 0 0 198 0 96 96 96 0 186 96 0 342 0 0 0 591 0 0 0 384 13 12 11 10 9 8 7 6 5 4 3 2
  • 28. Lot-sizing with capacity constraints r = (20,40,100,35,80,75,25) c = (60,60,60,60,60,60,60) Checking for feasibility: r 1 = 20 c 1 =60 r 1 +r 2 = 60 c 1 +c 2 = 120 r 1 +r 2 +r 3 = 160 c 1 +c 2 +c 3 = 180 r 1 +r 2 +r 3 +r 4 = 195 c 1 +c 2 +c 3 +c 4 = 240 r 1 +r 2 +r 3 +r 4 +r 5 = 275 c 1 +c 2 +c 3 +c 4 +c 5 = 300 r 1 +r 2 +r 3 +r 4 +r 5 +r 6 = 350 c 1 +c 2 +c 3 +c 4 +c 5 +c 6 = 360 r 1 +r 2 +r 3 +r 4 +r 5 +r 6 +r 7 = 375 c 1 +c 2 +c 3 +c 4 +c 5 +c 6 +c 7 = 420 Feasibility test is satisfied
  • 29. Lot shifting technique r = (20,40, 100 ,35,80,75,25) r’ = ( 40 , 60 , 60 ,35,80,75,25) c = (60,60,60,60,60,60,60) _______________________________________ r’ = ( 40 , 60 , 60 ,35,80,75,25) r’ = ( 40 , 60 , 60 , 55 , 60 ,75,25) r’ = ( 50 , 60 , 60 , 60,60,60 ,25)
  • 30. The improvement step K=450 and h =2 r = (100, 79, 230, 105, 3, 10, 99, 126,40) c = (120, 200, 200, 400, 300, 50, 120, 50, 30) 0 0 0 0 272 295 0 91 20 Excess capacity 30 50 120 50 28 105 200 109 100 y 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 r’
  • 31. Calculations of the improvement step 0 0 0 0 272 295 0 91 20 Excess capacity 242 192 30 50 120 50 28 105 200 109 100 y 0 0 58 108 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
  • 32. Calculations continued 0 0 0 0 192 295 0 91 20 Excess capacity 142 0 0 120 50 108 105 200 109 100 y 0 158 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
  • 33. 0 0 0 0 142 295 0 91 20 Excess capacity 300 137 0 0 120 0 158 105 200 109 100 y 0 263 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
  • 34. 0 0 0 0 300 137 0 91 20 Excess capacity 0 0 120 0 0 263 200 109 100 y 30 50 120 50 300 400 200 200 120 c 30 50 120 50 28 105 200 109 100 r’ 9 8 7 6 5 4 3 2 1 Period
  • 35. Cost comparison Initial solution Holding cost = 2 (0+30+0+0+25+65+86+10)=432 Set up cost = 9 x 450 = 4,050 Total Cost = 432 + 4,050 = 4,482 Improved solution Holding cost = 2 (0+30+0+158+155+145+166+40+0) = 2 x 694 = 1,388 Set up cost = 5 x 450 = 2,250 Total cost = 1,388 + 2,250 = 3,638