1
Recommended Risk Allocation of Taiwan Offshore Wind Projects For Taiwan Financial Institution
ITEM PARTY BEARING RISK DISCUSSION
A. Financing/Energy Revenues
1. Failure to make debt service payments to:
a. higher than anticipated operating and maintenance
expense
Party B Under normal operating conditions
b. insufficient revenues Party B Party B unless loss of revenues due to
fault of Party A
c. bankruptcy/insolvency/walkway Party B
d. changes in interest rates Party B Any possibility to adjust tariff ?
e. improper cash flow/mismanagement Party B Party B unless event due to fault of
Party A
f. facility shutdown or limited operation (Curtailment) Party B Party B in accordance with PPA
g. changes in foreign exchange Party B
2. Insufficient Revenues from Energy Sales because:
a. The energy is in a form not usable by the market
due to:
i. improper design Party B Guaranteed
ii. improper operation Party B Guaranteed
iii. change in energy market requirements Party A
	NOTE:	
1. Party	A	(甲方)means	the	governmental	entities	either	on	behalf	of	Taiwan	government	to	grant	the	concession	of	Taiwan	offshore	wind	projects	or	
Taiwan	Power	Corp	(Taipower).	
2. Party	B	(乙方)means	project	sponsors
2
b. The energy market is unable to accept all or a portion
of the energy projected due to:
i. market shutdown Party A
ii. market energy demand reduction Party A
iii. failure of energy transportation mechanism Party A
iv. change in law Party A
v. breach of contract by either party Party B/Party A Breaching party
vi. uncontrollable circumstances Party A
vii. market walkaway/bankruptcy/ insolvency Party A
viii. Taipower walkaway/bankruptcy/insolvency
c. The energy revenues are lower due to:
i. lower than anticipated unit energy prices Party A
ii. wind resource variability Party B
iii. Facility non-performance Party B Guaranteed
3
ITEM PARTY BEARING RISK DISCUSSION
B. Design/Construction/Testing
1. Construction Behind Schedule due to delays caused by:
a. labor strikes Party B For strikes of employees under control
of the Contractor
b. uncontrollable circumstances Party A To the degree not covered by
insurance
c. unforeseen site conditions Party A
d. Contractor/Party B mismanagement Party B
e. failure to secure construction permits Party B
f. suspension of work by the Party B Party B
g. failure to receive equipment on schedule Party B
2. Construction cost overruns caused by:
a. higher than anticipated inflation -
i. Fixed price
ii. Escalation price
Party B
Party A
Adjustment of Tariff
b. construction delays Party B
c. change in law requiring additional equipment or
design changes
Party A Extent of needed change and cost
negotiated
d. Contractor error in design and/or construction Party B
e. Party B initiated changes Party B
f. uncontrollable circumstances Party A Extent of needed change and cost
negotiated
4
3. The Facility cannot demonstrate anticipated
performance levels during acceptance testing due to:
a. defective technology which will not meet guarantees Party B
b. errors in design Party B
c. improper construction Party B
d. wind resource variability Party B
4. The Facility cannot meet environmental regulations and
EIA due to:
a. failure of plant to perform as anticipated Party B
b. change in law Party A Extent of needed change and cost
negotiated
5. The Facility is not completed due to:
a. cost overruns with insufficient additional funds
available for completion
Party B
b. Taipower/Party A/walkaway/bankruptcy/insolvency Party A Cost liability negotiated
c. Contractor/walkaway/bankruptcy/insolvency Party B
d. defective technology which will not meet guarantees Party B
5
C. Operation and Maintenance
1. Equipment failure caused by:
a. defective equipment which cannot meet guarantees Party B
b. legal/court injunction Party B/Party A Party causing the injunction is
responsible
c. revocation of permits Party B Party B unless due to action or
inaction of Party A
d. design errors and omissions Party B
e. poor construction Party B
f. improper operation and/or maintenance Party B
g. damaged caused by wind resource variability Party B/Party A Party A responsible for bringing
acceptable waste only
h. uncontrollable circumstances Party A Extent of needed change and cost
negotiated
2. Excessive downtime caused by:
a. equipment failure Party B
b. uncontrollable circumstances Party B/Party A Extent of needed change and cost
negotiated
c. labor strikes Party B For strikes of employees under the
control of the Contractor
d. improper operation and/or management Party B
e. wind resource variability Party B Service fee and lost energy revenues
paid
6
3. Operation and maintenance costs are higher than
anticipated due to:
a. equipment failure Party B
b. uncontrollable circumstances Party A Extent of needed change and cost
negotiated
c. poor labor productivity Party B
d. change in law Party A Extent of needed change and cost
negotiated
e. estimating error Party B
f. higher insurance costs Party B
g. higher inflation rate Party A Adjustment to tariff
h. wind resource variability Party B
i. increase of backup capacity Party A
j. increase of backup capacity cost Party A
k. increased balancing cost Party A
l. cost of necessary reinforcement of transmission and
distribution network
Party A
4. Facility cannot meet environmental regulations and EIA
due to:
a. equipment failure Party B
b. change in law/permit requirements Party A Extent of needed change and cost
negotiated
5. Permanent Facility shutdown caused by:
a. Inability to pay operating expenses Party B/Party A depending on reason for inability
7
b. revocation of operating permit Party B/Party A depending on reason for revocation
c. Taipower/Party A/walkaway/bankruptcy/ insolvency Party A
d. Contractor/walkaway/bankruptcy/ insolvency Party B
e. wind resource variability Party B
f. technology failure Party B
g. change in law Party A
h. uncontrollable circumstances Party A
6. The wind resource varies from the assumed design
criteria due to:
a. error in estimating wind resource Party B
b. adverse weather conditions Party B

More Related Content

PDF
Green Hydrogen Financial Model Toolkit LCOH
PDF
SunBurn Test Presentation
PDF
Green Hydrogen Financial Model Toolkit
PPTX
Unit 7
PPT
Conditions of CPWD contract in INDIA
PDF
Commonwealth of Virginia Virginia Information Technologies ...
PDF
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
PDF
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Green Hydrogen Financial Model Toolkit LCOH
SunBurn Test Presentation
Green Hydrogen Financial Model Toolkit
Unit 7
Conditions of CPWD contract in INDIA
Commonwealth of Virginia Virginia Information Technologies ...
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a

Similar to Risk allocation for offshore wind (8)

PPTX
Claims and insolvencies (1)
PPTX
Contractors EoT Claims - Draft Presentation - 10.04.2025.pptx
PPTX
Contracts & Claims Management Workshop (Session-1)
PPTX
KDC11- Anand Rohatgi, Synergy Consulting
PPTX
Contractors EoT Claims - Draft Presentation - 09.04.2025.pptx
PPTX
5M CHANGE TRAINING in manufacturing .pptx
PPT
Part 1 administrative portion
PDF
REC mechanism
Claims and insolvencies (1)
Contractors EoT Claims - Draft Presentation - 10.04.2025.pptx
Contracts & Claims Management Workshop (Session-1)
KDC11- Anand Rohatgi, Synergy Consulting
Contractors EoT Claims - Draft Presentation - 09.04.2025.pptx
5M CHANGE TRAINING in manufacturing .pptx
Part 1 administrative portion
REC mechanism
Ad

Recently uploaded (20)

PPTX
Group Presentation Development Econ and Envi..pptx
PPTX
Machine Learning (ML) is a branch of Artificial Intelligence (AI)
PPTX
Very useful ppt for your banking assignments Banking.pptx
PPTX
INDIAN FINANCIAL SYSTEM (Financial institutions, Financial Markets & Services)
PDF
NewBase 22 August 2025 Energy News issue - 1818 by Khaled Al Awadi_compresse...
PDF
01 KEY PROVISIONS on NGPA and PROFESSIONALIZATION.pdf
PDF
Call cute girls 😀 Delhi, call now pls cute girls delhi call🔙
PDF
epic-retirement-criteria-for-funds (1).pdf
PDF
Lundin Gold - August 2025.pdf presentation
PDF
In July, the Business Activity Recovery Index Worsened Again - IER Survey
PDF
2012_The dark side of valuation a jedi guide to valuing difficult to value co...
PPT
Relevant Information & Alternative Choice Decisions
PPTX
RISK MANAGEMENT IN MEDICAL LABORATORIES 2.pptx
PPTX
PROFITS AND GAINS OF BUSINESS OR PROFESSION 2024.pptx
PDF
2018_Simulating Hedge Fund Strategies Generalising Fund Performance Presentat...
PDF
USS pension Report and Accounts 2025.pdf
PDF
Fintech Regulatory Sandbox: Lessons Learned and Future Prospects
PPTX
PPT-Lesson-2-Recognize-a-Potential-Market-2-3.pptx
PPTX
ANALYZE MARKET DEMAND, MARKET SUPPLY AND MARKET.pptx
PDF
Very useful ppt for your banking assignments BANKING.pptx.pdf
Group Presentation Development Econ and Envi..pptx
Machine Learning (ML) is a branch of Artificial Intelligence (AI)
Very useful ppt for your banking assignments Banking.pptx
INDIAN FINANCIAL SYSTEM (Financial institutions, Financial Markets & Services)
NewBase 22 August 2025 Energy News issue - 1818 by Khaled Al Awadi_compresse...
01 KEY PROVISIONS on NGPA and PROFESSIONALIZATION.pdf
Call cute girls 😀 Delhi, call now pls cute girls delhi call🔙
epic-retirement-criteria-for-funds (1).pdf
Lundin Gold - August 2025.pdf presentation
In July, the Business Activity Recovery Index Worsened Again - IER Survey
2012_The dark side of valuation a jedi guide to valuing difficult to value co...
Relevant Information & Alternative Choice Decisions
RISK MANAGEMENT IN MEDICAL LABORATORIES 2.pptx
PROFITS AND GAINS OF BUSINESS OR PROFESSION 2024.pptx
2018_Simulating Hedge Fund Strategies Generalising Fund Performance Presentat...
USS pension Report and Accounts 2025.pdf
Fintech Regulatory Sandbox: Lessons Learned and Future Prospects
PPT-Lesson-2-Recognize-a-Potential-Market-2-3.pptx
ANALYZE MARKET DEMAND, MARKET SUPPLY AND MARKET.pptx
Very useful ppt for your banking assignments BANKING.pptx.pdf
Ad

Risk allocation for offshore wind

  • 1. 1 Recommended Risk Allocation of Taiwan Offshore Wind Projects For Taiwan Financial Institution ITEM PARTY BEARING RISK DISCUSSION A. Financing/Energy Revenues 1. Failure to make debt service payments to: a. higher than anticipated operating and maintenance expense Party B Under normal operating conditions b. insufficient revenues Party B Party B unless loss of revenues due to fault of Party A c. bankruptcy/insolvency/walkway Party B d. changes in interest rates Party B Any possibility to adjust tariff ? e. improper cash flow/mismanagement Party B Party B unless event due to fault of Party A f. facility shutdown or limited operation (Curtailment) Party B Party B in accordance with PPA g. changes in foreign exchange Party B 2. Insufficient Revenues from Energy Sales because: a. The energy is in a form not usable by the market due to: i. improper design Party B Guaranteed ii. improper operation Party B Guaranteed iii. change in energy market requirements Party A NOTE: 1. Party A (甲方)means the governmental entities either on behalf of Taiwan government to grant the concession of Taiwan offshore wind projects or Taiwan Power Corp (Taipower). 2. Party B (乙方)means project sponsors
  • 2. 2 b. The energy market is unable to accept all or a portion of the energy projected due to: i. market shutdown Party A ii. market energy demand reduction Party A iii. failure of energy transportation mechanism Party A iv. change in law Party A v. breach of contract by either party Party B/Party A Breaching party vi. uncontrollable circumstances Party A vii. market walkaway/bankruptcy/ insolvency Party A viii. Taipower walkaway/bankruptcy/insolvency c. The energy revenues are lower due to: i. lower than anticipated unit energy prices Party A ii. wind resource variability Party B iii. Facility non-performance Party B Guaranteed
  • 3. 3 ITEM PARTY BEARING RISK DISCUSSION B. Design/Construction/Testing 1. Construction Behind Schedule due to delays caused by: a. labor strikes Party B For strikes of employees under control of the Contractor b. uncontrollable circumstances Party A To the degree not covered by insurance c. unforeseen site conditions Party A d. Contractor/Party B mismanagement Party B e. failure to secure construction permits Party B f. suspension of work by the Party B Party B g. failure to receive equipment on schedule Party B 2. Construction cost overruns caused by: a. higher than anticipated inflation - i. Fixed price ii. Escalation price Party B Party A Adjustment of Tariff b. construction delays Party B c. change in law requiring additional equipment or design changes Party A Extent of needed change and cost negotiated d. Contractor error in design and/or construction Party B e. Party B initiated changes Party B f. uncontrollable circumstances Party A Extent of needed change and cost negotiated
  • 4. 4 3. The Facility cannot demonstrate anticipated performance levels during acceptance testing due to: a. defective technology which will not meet guarantees Party B b. errors in design Party B c. improper construction Party B d. wind resource variability Party B 4. The Facility cannot meet environmental regulations and EIA due to: a. failure of plant to perform as anticipated Party B b. change in law Party A Extent of needed change and cost negotiated 5. The Facility is not completed due to: a. cost overruns with insufficient additional funds available for completion Party B b. Taipower/Party A/walkaway/bankruptcy/insolvency Party A Cost liability negotiated c. Contractor/walkaway/bankruptcy/insolvency Party B d. defective technology which will not meet guarantees Party B
  • 5. 5 C. Operation and Maintenance 1. Equipment failure caused by: a. defective equipment which cannot meet guarantees Party B b. legal/court injunction Party B/Party A Party causing the injunction is responsible c. revocation of permits Party B Party B unless due to action or inaction of Party A d. design errors and omissions Party B e. poor construction Party B f. improper operation and/or maintenance Party B g. damaged caused by wind resource variability Party B/Party A Party A responsible for bringing acceptable waste only h. uncontrollable circumstances Party A Extent of needed change and cost negotiated 2. Excessive downtime caused by: a. equipment failure Party B b. uncontrollable circumstances Party B/Party A Extent of needed change and cost negotiated c. labor strikes Party B For strikes of employees under the control of the Contractor d. improper operation and/or management Party B e. wind resource variability Party B Service fee and lost energy revenues paid
  • 6. 6 3. Operation and maintenance costs are higher than anticipated due to: a. equipment failure Party B b. uncontrollable circumstances Party A Extent of needed change and cost negotiated c. poor labor productivity Party B d. change in law Party A Extent of needed change and cost negotiated e. estimating error Party B f. higher insurance costs Party B g. higher inflation rate Party A Adjustment to tariff h. wind resource variability Party B i. increase of backup capacity Party A j. increase of backup capacity cost Party A k. increased balancing cost Party A l. cost of necessary reinforcement of transmission and distribution network Party A 4. Facility cannot meet environmental regulations and EIA due to: a. equipment failure Party B b. change in law/permit requirements Party A Extent of needed change and cost negotiated 5. Permanent Facility shutdown caused by: a. Inability to pay operating expenses Party B/Party A depending on reason for inability
  • 7. 7 b. revocation of operating permit Party B/Party A depending on reason for revocation c. Taipower/Party A/walkaway/bankruptcy/ insolvency Party A d. Contractor/walkaway/bankruptcy/ insolvency Party B e. wind resource variability Party B f. technology failure Party B g. change in law Party A h. uncontrollable circumstances Party A 6. The wind resource varies from the assumed design criteria due to: a. error in estimating wind resource Party B b. adverse weather conditions Party B