Safety for Wiring Methods

By : Komarul Fausiyah
Wiring Methods for Construction ...
1. Cable shall be installed in accordance with drawings. The
following segregation will be adhered to throughout the
facility:
a. Medium voltage power cabling shall not occupy the same
enclosure, conduit, duct or tray with 600 volt or less light
and power conductors.
b. Conductor of 600 volt or less light and power systems and
associated 120 volt A.C. System control cabling shall be
permitted to occupy the same enclosure, conduit, duct or
tray where all co.
c. Conductors of A.C. and D.C. low voltage instrumentation,
control and communication system shall not occupy the
same enclosure, conduit, duct or tray with conductors
listed above. For detailed description of
power/instrument cabling segregations requirements refer
to specification VES-7112, section 6.2 thru 6.7.
Wiring Methods for Construction ...
2. All medium voltage power cabling within the plan
production area shall be installed underground
utilized an underground duct bank system. For pull
boxes and duct bank construction details refer to
standard drawing STD-60-07
3. Direct buried cables shall be acceptable for of-plot
services and for non essential plant utilities, where
such are located outside the production facility
boundary. For installation details refer to standard
drawing STD-60-06.
Wiring Methods for Construction ...
4. In general, 600 volt or less in-plant electrical power and
control distribution shall be installed in overhead cable
tray utilizing tray rated/ armored cables as listed in
section 13.2. Cable runs from the tray to the
equipment served shall be installed in rigid conduit or
via PVC underground duct or shall be properly
supported armored cable.
5. For above ground installations, multiples of single
conductor wire, and/or multi-conductor cable run in
rigid conduit or properly supported armored cable shall
be provide for those cases where the cable tray system
is not feasible, area lighting and instrumentation field
devices.
Wiring Methods for Construction ...
6. Where metal conduit is used, all phases of a three
phase circuit and neutral wire, if any, shall be located
in the same conduit.
7. All wire and cable shall be continuous without splices
from origin to termination as far as is practicable.
Where splices are required, they shall be made in
approved junction boxes. No splices or repaired
wires or cables will be permitted within conduits
between approved junction boxes or pull points.
Wiring Methods for Construction ...
8. No wire or cable shall be installed which has
damaged insulation or jacket.
9. All multi conductor cables shall remain sealed until
immediately prior to actual jointing or terminating.
10. The contractor shall not pull wire or cable through
boxes or enclosures where a change of raceway
alignment or direction occurs.
11. The contractor shall not cut strands from conductors
to fit lugs or terminals.
Wiring Methods for Construction ...
12. The contractor shall not bend cable to less than

recommended radius. The minimum cable
radius shall not be less than indicated in the
following table:
Cable Type
0.6/1 KV NYA
0.6/1 KV NYY
0.6/1 KV NYFGBY
3.6/6 KV N2XSY
3.6/6 KV N2XSEBY
3.6/6/ KV N2XSEFGby

Minimum Radius
5 times OD
5 times OD
8 times OD
12 times OD
12 times OD
12 items OD
Wiring Methods for Construction ...
13. The contractor shall employ temporary guides,
sheaves, pulley blocks, rollers and other suitable
hardware to protect cable from excess tension &
abrasion during installation.

14. The contractor shall be ring out each conductor of
each feeder for phase identification.
15. Each cable shall be tagged with the cable numbers
assigned on the drawings.
Instrument Cable
• In general, armored and unarmored
thermoplastic instrument wire, decorum (type
:IEB) or equal, 1.5 mm2 twisted single or multi
pair overall shielded instrument cable, U.L
listed as 300 Volt, 90oC, power limited tray
cable, approved for class I, Division 2 classified
areas, shall be used.
Splices, Taps and Terminations ...
1) Splices, taps and terminations on 600 volt and above
insulated conductors shall be made using crimp type
compression sleeves and lugs where possible. The
compression fittings used shall be compatible
metallurgic ally with the conductor material, and
shall be compactable with the wire, crimping tool,
and terminal strips. Plated or bare copper body
fittings shall be used on copper conductors only. The
crimping tool recommended by the fitting
manufacturer shall be the one used.
Splices, Taps and Terminations ...
2) The use of bolt-on clamp type fittings is
acceptable as a second choice method of
splicing, tapping and terminating 600 volt
insulated copper conductors only, and is not
acceptable as a method of splicing, tapping or
terminating aluminum conductors at any
voltage level or copper conductors at voltage
level above 600 volts.
Splices, Taps and Terminations ...
3) Where field insulation is required on a 600 volt cable
connection, the connection shall be wrapped uniformly
with rubber tape to a minimum thickness of twice the
cable insulation thickness and than covered by two layers
minimum of neoprene tape or scotch #88 or equal plastic
tape applied snugly but not stretched.
4) Scotch cast single conductor resin inline and wye splice
kits, type 82-A1 thru A3, 82-B1 and 90-B1 or equal, shall
be used for 600 volt cable connections. Splice taps and
terminations shall be made in accordance with and
instructions supplied with joint kit materials.
Splices, Taps and Terminations ...
5) KV shielded cable termination and splicing shall

be made in accordance with the drawings. In
general for single conductor cabling the following
quick termination kits shall be used:
a) Termination Kits
3M “Cold Shrink” Quick Term 11 Hi-K silicon
rubber termination kits 5630K series
outdoor/indoor Class 1 (For outdoor installation
s) and 5620K indoor low contamination class 3
for switchgear connections.
5) ...
b. Inline Splice Kits
3M “Cold Shrink” 5331 thru 5334 quick splice
inline splicing kits.
Termination and splicing of medium voltage cable
shall be done in accordance with the instructions
supplied by the kit manufacturer and in the
presence of the company’s representative. For
termination and splice kit drain wire grounding
details refer to standard drawing STD-60-02.
Splices, Taps and Terminations ...
6) 5KV multi-conductor cables shall be terminated/spliced
in accordance with issued drawings and instruction
sheets packed in the boxes with the kits purchased for
the particular installation. The work shall be
performed in the presence of the company’s
representative.
7) When forming cables for termination, sharp turns,
corners and edges shall be avoided in order to prevent
damage to, or weakening of the cable insulation.
8) For 5 kV cable, the cable shield shall be grounded at
each splice and termination points.
~ You can't start the next chapter if you
keep re-reading the last one~

Safety is Start from Ourselves

Safety for wiring methods

  • 1.
    Safety for WiringMethods By : Komarul Fausiyah
  • 2.
    Wiring Methods forConstruction ... 1. Cable shall be installed in accordance with drawings. The following segregation will be adhered to throughout the facility: a. Medium voltage power cabling shall not occupy the same enclosure, conduit, duct or tray with 600 volt or less light and power conductors. b. Conductor of 600 volt or less light and power systems and associated 120 volt A.C. System control cabling shall be permitted to occupy the same enclosure, conduit, duct or tray where all co. c. Conductors of A.C. and D.C. low voltage instrumentation, control and communication system shall not occupy the same enclosure, conduit, duct or tray with conductors listed above. For detailed description of power/instrument cabling segregations requirements refer to specification VES-7112, section 6.2 thru 6.7.
  • 3.
    Wiring Methods forConstruction ... 2. All medium voltage power cabling within the plan production area shall be installed underground utilized an underground duct bank system. For pull boxes and duct bank construction details refer to standard drawing STD-60-07 3. Direct buried cables shall be acceptable for of-plot services and for non essential plant utilities, where such are located outside the production facility boundary. For installation details refer to standard drawing STD-60-06.
  • 4.
    Wiring Methods forConstruction ... 4. In general, 600 volt or less in-plant electrical power and control distribution shall be installed in overhead cable tray utilizing tray rated/ armored cables as listed in section 13.2. Cable runs from the tray to the equipment served shall be installed in rigid conduit or via PVC underground duct or shall be properly supported armored cable. 5. For above ground installations, multiples of single conductor wire, and/or multi-conductor cable run in rigid conduit or properly supported armored cable shall be provide for those cases where the cable tray system is not feasible, area lighting and instrumentation field devices.
  • 5.
    Wiring Methods forConstruction ... 6. Where metal conduit is used, all phases of a three phase circuit and neutral wire, if any, shall be located in the same conduit. 7. All wire and cable shall be continuous without splices from origin to termination as far as is practicable. Where splices are required, they shall be made in approved junction boxes. No splices or repaired wires or cables will be permitted within conduits between approved junction boxes or pull points.
  • 6.
    Wiring Methods forConstruction ... 8. No wire or cable shall be installed which has damaged insulation or jacket. 9. All multi conductor cables shall remain sealed until immediately prior to actual jointing or terminating. 10. The contractor shall not pull wire or cable through boxes or enclosures where a change of raceway alignment or direction occurs. 11. The contractor shall not cut strands from conductors to fit lugs or terminals.
  • 7.
    Wiring Methods forConstruction ... 12. The contractor shall not bend cable to less than recommended radius. The minimum cable radius shall not be less than indicated in the following table: Cable Type 0.6/1 KV NYA 0.6/1 KV NYY 0.6/1 KV NYFGBY 3.6/6 KV N2XSY 3.6/6 KV N2XSEBY 3.6/6/ KV N2XSEFGby Minimum Radius 5 times OD 5 times OD 8 times OD 12 times OD 12 times OD 12 items OD
  • 8.
    Wiring Methods forConstruction ... 13. The contractor shall employ temporary guides, sheaves, pulley blocks, rollers and other suitable hardware to protect cable from excess tension & abrasion during installation. 14. The contractor shall be ring out each conductor of each feeder for phase identification. 15. Each cable shall be tagged with the cable numbers assigned on the drawings.
  • 9.
    Instrument Cable • Ingeneral, armored and unarmored thermoplastic instrument wire, decorum (type :IEB) or equal, 1.5 mm2 twisted single or multi pair overall shielded instrument cable, U.L listed as 300 Volt, 90oC, power limited tray cable, approved for class I, Division 2 classified areas, shall be used.
  • 10.
    Splices, Taps andTerminations ... 1) Splices, taps and terminations on 600 volt and above insulated conductors shall be made using crimp type compression sleeves and lugs where possible. The compression fittings used shall be compatible metallurgic ally with the conductor material, and shall be compactable with the wire, crimping tool, and terminal strips. Plated or bare copper body fittings shall be used on copper conductors only. The crimping tool recommended by the fitting manufacturer shall be the one used.
  • 11.
    Splices, Taps andTerminations ... 2) The use of bolt-on clamp type fittings is acceptable as a second choice method of splicing, tapping and terminating 600 volt insulated copper conductors only, and is not acceptable as a method of splicing, tapping or terminating aluminum conductors at any voltage level or copper conductors at voltage level above 600 volts.
  • 12.
    Splices, Taps andTerminations ... 3) Where field insulation is required on a 600 volt cable connection, the connection shall be wrapped uniformly with rubber tape to a minimum thickness of twice the cable insulation thickness and than covered by two layers minimum of neoprene tape or scotch #88 or equal plastic tape applied snugly but not stretched. 4) Scotch cast single conductor resin inline and wye splice kits, type 82-A1 thru A3, 82-B1 and 90-B1 or equal, shall be used for 600 volt cable connections. Splice taps and terminations shall be made in accordance with and instructions supplied with joint kit materials.
  • 13.
    Splices, Taps andTerminations ... 5) KV shielded cable termination and splicing shall be made in accordance with the drawings. In general for single conductor cabling the following quick termination kits shall be used: a) Termination Kits 3M “Cold Shrink” Quick Term 11 Hi-K silicon rubber termination kits 5630K series outdoor/indoor Class 1 (For outdoor installation s) and 5620K indoor low contamination class 3 for switchgear connections.
  • 14.
    5) ... b. InlineSplice Kits 3M “Cold Shrink” 5331 thru 5334 quick splice inline splicing kits. Termination and splicing of medium voltage cable shall be done in accordance with the instructions supplied by the kit manufacturer and in the presence of the company’s representative. For termination and splice kit drain wire grounding details refer to standard drawing STD-60-02.
  • 15.
    Splices, Taps andTerminations ... 6) 5KV multi-conductor cables shall be terminated/spliced in accordance with issued drawings and instruction sheets packed in the boxes with the kits purchased for the particular installation. The work shall be performed in the presence of the company’s representative. 7) When forming cables for termination, sharp turns, corners and edges shall be avoided in order to prevent damage to, or weakening of the cable insulation. 8) For 5 kV cable, the cable shield shall be grounded at each splice and termination points.
  • 16.
    ~ You can'tstart the next chapter if you keep re-reading the last one~ Safety is Start from Ourselves