Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : E

Explanation

Key functions as part of Plant Maintenance −

  • Inspection and Notifications
  • Corrective and Preventive Maintenance
  • Breakdown Maintenance
  • Repair
  • Other measures - charactertics and Key Figures

Answer : C

Explanation

In SAP PM, when there is a malfunction occurs for any of the equipment which requires a response from Maintenance team. The process of correcting this situation is known as Breakdown maintenance.

Q 3 - What is the order type to perform Preventive Maintenance in Plant Maintenance?

A - PM01

B - PM02

C - PM03

D - PM04

Answer : C

Explanation

In SAP system, PM01 is the order type to perform Corrective maintenance and PM03 is for performing Preventive maintenance.

Q 4 - Which of the following submodule of Plant Maintenance is used to control and monitor the safety measures?

A - Work Flow

B - Notification

C - Work Clearance Management

D - Enterprise Asset Management EAM

Answer : C

Explanation

Work Clearance Management in Plant Maintenance is used to control and monitor the safety measures. It provides safe working conditions for employees in the organization and to follow the environmental protection regulations.

Q 5 - In an Organization, Which of the following factor doesnt affect work place safety?

A - Task Category

B - Technical specifications of the system

C - Organization within the maintenance department

D - Bill of Material

Answer : D

Q 6 - To better manage and monitor Plant Maintenance process in Financial Management, you can integrate Plant Maintenance (PM) and Funds Management (FM)?

A - True

B - False

Answer : A

Q 8 - Which of the time based scheduling allows you to perform Maintenance strategy every 30 working days?

A - Time Based

B - Time Based by Key date

C - Time Based by factory calendar

D - All of the above

Answer : C

Explanation

Time-based (for example, every 30 days)

Time-based by key date (for example, every 30 days on the 30th day of the month)

Time-based by factory calendar (for example, every 30 working days)

Q 9 - What is the usage type for BOMs in plant maintenance?

A - 1

B - 2

C - 3

D - 4

Answer : D

Q 10 - In SAP Plant Maintenance, which of the following role is responsible to perform planning maintenance tasks based on incoming malfunction reports and is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery?

A - Maintenance Manager

B - Maintenance Planner

C - Maintenance engineer

D - Maintenance Supervisor

Answer : B

Explanation

In SAP Plant Maintenance, a Maintenance planner is responsible for planning maintenance tasks based on incoming malfunction reports. Maintenance planner is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery.