Daily Progress Report: Land Survey and Marking For Foundation

This daily progress report summarizes work done on November 2nd, 2011 for a 5MW solar project in Phalodi, Rajasthan. Key activities completed include pile marking for blocks 1, 2, 4, control room and inverter room raft casting, and control room foundation pillar casting reaching the first lift. Ongoing civil works include boring for all blocks, base pile casting for blocks 1-5, and pile cap casting for blocks 1-4. The report provides staffing details with 7 engineers, 6 supervisors, 25 skilled laborers and 81 unskilled laborers/security guards across 4 contractor teams. Machinery on site includes piling machines, generators, excavators, mixers and other equipment. Materials
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
505 views6 pages

Daily Progress Report: Land Survey and Marking For Foundation

This daily progress report summarizes work done on November 2nd, 2011 for a 5MW solar project in Phalodi, Rajasthan. Key activities completed include pile marking for blocks 1, 2, 4, control room and inverter room raft casting, and control room foundation pillar casting reaching the first lift. Ongoing civil works include boring for all blocks, base pile casting for blocks 1-5, and pile cap casting for blocks 1-4. The report provides staffing details with 7 engineers, 6 supervisors, 25 skilled laborers and 81 unskilled laborers/security guards across 4 contractor teams. Machinery on site includes piling machines, generators, excavators, mixers and other equipment. Materials
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT - 5MW SOLAR PROJECT PHALODI RAJASTHAN

DAILY PROGRESS REPORT


Format no SOL- 01

Date : 02-11-2011
WORK DONE

Discipline

Description of work

Land Survey and Marking for


foundation
PILE MARKING BLOCK -1
PILE MARKING BLOCK-2
PILE MARKING BLOCK-4
Control Room Raft Casting
Inverter room raft casting
Control Room Foundation Piller
casting( 1st lift)

Block
nos
nos
nos
nos

INVERTER ROOM 5 PILLER CASTING


(UP TO PLINTH BEAM)

Civil

Starting
Dt :

UOM

Actual/Expected
Finish date

20.09.11

ALL FIVE BLOCKS

14.09.11
15.10.11

1926
14
20

16.10.11

14

NOS

BORING
BLOCK - 1
BLOCK - 2
BLOCK - 3
BLOCK - 4
BLOCK - 5
BASE PILE CASTING
BLOCK - 1
BLOCK - 2
BLOCK - 3
BLOCK - 4
BLOCK - 5
PILE CAPE CASTING
BLOCK - 1
BLOCK - 2
BLOCK - 3
BLOCK - 4
BLOCK - 5

Scope

Planned

Actual Of Last Day

20

NO
NO

1992
5

NO

508
1849

NO

678

373
503
MAN POWER AND MACHINERY

Discipline

Category

BENIWAL
CONSTRUCTION

SWL

4
2

Engineer
Supervisor
Skilled Labor
Manpower

Bar Bender
Unskilled Labor
Security Guard

Machinery

Contractor C

Contractor D

Cumulative

2
2

1
2

7
6

20

25

14

57

24

81
4
137

1
1
2
2
3
4

1
1
1

Pile boring machine


DG
JCB
Concrete Mixers
Vibrator
Tractors
Water tanker
Fork Lifts
Hydra
Total Station
Air Compressor
Boaring Rig Machine

Decipline

Hemraj
Constraction

Item Description

Uom
BENIWAL
CONSTRUCTION

GRIT
20mm
10mm
SAND
STEEL
Cement

1
1
2
1

1
MATERIAL RECEIVED
Qty. Received

Cumulative Qty

Hemraj
Constraction

CUM
CUM
CUM
CUM
KG
Bags

184
134
174
45500
2540

Observations

Description
open issue

Sl.No

Category

Grouting of Module structure

Disturbance in
the structure in
the module in
the event of
severe wind and
electrical
shotcircuit
all locations

Prepared by SWL
Signature
Name
Designation

Location

k simhadri

Picture

Action agreed

Grouting required before


power flow

Pictures issue rectification

Detected by

welspun

Approved by WEL

Date

2/11/2011

e : 02-11-2011

WEL

Cumulative actual to Date

Remarks

completed
1009
883
14
16
14
16

13400 nos anchor bolts


received at site

2032
294
1843
1849
6018
1992
5
508
1849
4354
1140

40
289
0
1335
COMPLETED

COMPLETED
462
0
0
107
0

480
503

Remarks

Person
Responsible for
rectification

Priority

critical

PROJECT - 5 MW RAJASTHAN SOLAR POWER PROJECT

INCIDENT REPORT
Format No

Incident Details
Date

Time

Cause of Incident

Prepared by SWL
Name
Designation
Signature
Date

Effect

Approved by WEL

ER PROJECT
Date : DD-MM-2011

Corective action

Approved by WEL