A Presentation
on
Transmission line Basics
WHY A TRANSMISSION LINE?
Transmission lines are constructed basically for transmission
of power from one point to another
Normal connecting points
Interconnection between 2(two) generating stations
Connecting generating station with substations
Interconnection between substations
Interconnection between substation & power sub station
Interconnecting power substations
Connection from power substation to consumers
2
BASIC SCHEMATIC
GENERATION TRANSMISSION - DISTRIBUTION
Transmission
system
Power plant
Distribution system
Generator
GT
220 KV
11/220 kV
11 KV
220/33/11 kV
Distribution
Step down
transformer
11/0.4 kV
POWER SYSTEM- DIAGRAM
TRANSMISSION LINE CONCEPT
Power
Plant
Consumer
Home
POWER SYSTEM COMPONENTS
Source:
[Link]
TRANSMISSION LINE NETWORK OF NER
CHOICE OF GENERATION / TRASMISSION
VOLTAGE
Generation is normally at 0.4 or 11 kv
Stepped up through transformer and transmitted over a long
distance to the desired load centers at different voltages which
depends on
Quantum of power to be transmitted
Line length
Cost of terminal equipments
Economy consistent with desired reliability
8
CONDUCTOR SELECTION SCENARIOS
Scenario I : Conductor for low voltage lines ( 0.4 kV, 11 kV, 33 kV)
are selected from the point of view of current carrying capacity
Scenario II : Selection of conductor for EHV / UHV lines where
conductor size can not be increased beyond a certain limit in AC
Transmission because of factors like inductance (wL), capacitance
(1/wC), corona / RI effects etc. Corona / RI phenomena increases
directly with the diameter of conductor. Bundle conductor,
therefore, have to be used for voltage level for 400 kV and beyond
from Corona / RI consideration. Bundle conductor can also be used
in lower voltage line to increase the quantum of power to be
transmitted.
Skin effect of conductor in AC Transmission also limits size of
conductor where bundle conductor is more economical (both cost
and power loss) instead of a single large diameter conductor
9
WHAT IS CORONA?
Transmission-line conductors are surrounded by an electric field.
Corona discharge is generated when the electric field at the surface
of the conductor becomes larger than the breakdown strength of the
surrounding air.
Surface irregularities such as sharp points and water droplets cause
local field concentration, enhancing corona generation. Thus, during
bad weather, corona discharge is more intense and losses are much
greater.
Corona discharge generates audible noise and visible lights. The
visible light and audible noise can be observed simultaneously.
The voltage at which corona begins in called the discharge inception
voltage. Conversely, the voltage at which corona ceases is called
discharge extinction.
10
Corona produces radio and television interference.
CORONA DISCHARGE - PHOTO
Corona Camera
Corona event captured by corona camera on 500kV line
11
CORONA DISCHARGE - VIDEO
12
TRANSMISSION LINE VOLTAGE AND
CHOICE OF CONDUCTORS
Normal Transmission
voltage
Type of conductor Normally used
0.4 kV
ACSR Ant/ squirrel
11 kV
ACSR Weasel
33 kV
ACSR Racoon
66 kV
ACSR Dog
132 kV
ACSR Panther/ Zebra
220 kV
ACSR Zebra/ Moose
400 kV
Twin ACSR Moose / Bersimis/ Invar
765 kV
QUAD ACSR BERSIMIS/Invar
13
TRADE NAME OF CONDUCTORS
Trade name of conductors are normally kept after the names of
various animals, birds and insects. Some of the common ones are:
Code Name
Approx current carrying
Dia. of
capacity (Amp)
conductor
(mm)
40 ambient 45 ambient
Appox
UTS
(kg)
Approx
weight
(kg/km)
Squirrel
115
107
6.33
711
85
Gopher
133
123
7.08
952
106
Panther
520
482
21
9127
976
Zebra
795
736
28.62
13316
1623
Moose
900
835
31.77
16250
2002
14
INSULATED CABLE Vs OVERHEAD LINE
BARE CONDUCTOR
DECIDING FACTORS
Voltage level
Distance
Congestion
Cost consideration
Geographical consideration
Aesthetic consideration
Reliability
Available Technology
Special circumstances
15
LAYING OF TRANSMISSION LINK
I) Insulated cables
Underground
Overhead on Pylon
Supported by Bridge Girder
II) Bare Conductor
Direct supports on Insulators
Pylon supports
Laying of Underground cable
16
TYPES OF PYLONS
A. POLES (Standard length: 7.5 m/ 8.5 m/ 9.75 m/ 12 m)
Wooden
Steel Rail/ Channel
Pre-Stressed Concrete ( PSC)
Reinforced Cement Concrete
Steel Tubular Pole
Wooden Pole
PSC Pole
17
TYPES OF PYLONS
B. LATTICE STEEL STRUCTURE (Tower)
Modular welded (self supporting or guyed)
Bolted ( built up & self supporting)
18
MODULAR TOWER- ERS
19
TYPES OF LATTICE STRUCTURE
According to support condition
According to number of circuits they carry:
According to tower shapes/ base dimension
Further classification
According to angle of deviation
20
LATTICE STRUCTURE CLASSIFICATION
ACCORDING TO SUPPORT CONDITION:
Self supporting tower
Guyed tower
21
LATTICE STRUCTURE CLASSIFICATION
ACCORDING TO NO OF CIRCUIT THEY CARRY
Single circuit tower
Double circuit tower
Multi circuit towers
22
DETAILS OF SINGLE CIRCUIT TOWER
Cross arm at 3 levels
Cross arm at 2 levels
Cross arm at 1 level
23
DOUBLE & MULTI CIRCUIT TOWER
DOUBLE CIRCUIT TOWER
MULTI CIRCUIT TOWER
24
LATTICE STRUCTURE CLASSIFICATION
ACCORDING TO CONFIGURATION
Vertical configuration tower
Horizontal configuration tower
Delta configuration tower
25
LATTICE STRUCTURE CLASSIFICATION
ACCORDING TO TOWER SHAPES/ BASE DIMENSION
NOTE: To be chosen by designer on Techno economical consideration
WIDE BASED TOWER
NARROW BASED
800 kV NORMAL
TOWER
ROW
85 Mts
800 kV COMPACT
TOWER
ROW
64 Mts
26
400 kV Compact Single pole tower at Delhi &
Noida
27
LATTICE STRUCTURE CLASSIFICATION
ACCORDING TO ANGLE OF DEVIATION:
(Tangent tower/ suspension tower)
A type tower (0-2 degree).
Tension towers/angle towers:
B type tower (0-15 degree).
C type tower (0-30 degree).
(Also used for transposition)
D type tower (0-60 degree).
28
TRANSPOSITION TOWER
What is transposition tower and its configuration?
Transposition tower is normally parallel double circuit
transmission tower to facilitate interchange of transmission
line phase conductor, where the phase conductors occupy
different structure positions for different portions of the line
length so that transmission-line impedances is balanced.
For example, conductor placement on the structures may be
R-Y-B for one-third of the line length, Y-B-R for one-third
of the line length, and B-R-Y for the remaining third of the
line length.
C-type tower with modified cross-arm is generally used
with zero degree deviation.
29
WHY TRANSPOSITION?
Power transmission lines are transposed primarily for
impedance balance so as to eliminate or reduce
disturbances in the neighboring communication
circuits produced by geometric imbalances of power
line
Transposition tower are required for a line length
> 200 kms why?
Arrangement of transposition tower is shown below
30
LINE TRANSPOSITION
WITH C TYPE TOWER
T1
T2
T3
31
B
SINGLE Vs BUNDLE CONDUCTOR
Single Conductor : Normal Use
Bundle Conductors:
Deciding Factors
Capacity Enhancement
Technical reasons ( Handling & Erection easiness, Corona/ Radio
Interference ( R.I) consideration
Bundle conductor Configuration
Twin Bundle
Quad Bundle
Special Purpose Bundle (Hexagonal/ Octagonal etc)
32
TOWER SIZES
TOWER HEIGHT IS DECIDED BASED ON
Span : Longer the span, more is the height
Minimum Ground clearance (A) required to be
maintained
Conductor sag (B)
Insulator assembly length (C) to maintain
required electrical
Shield angle
E
D
D
C
B
Vertical separation of Cross arms (D)
Number of cross arm and its configuration
Peak Height- for fixing earth wire
corresponding to shield angle (E)
33
WHY EARTH WIRE?
To protect conductor against lightning flashovers
To provide a path for fault current
Direct Flashover
Occurs due to shielding failure with lightning on the conductor,
flashover taking place across the insulator string from conductor
to ground.
Back Flashover
Occurs due to high tower footing resistance with a high voltage at
the grounded tower cross arm compared to conductor, resulting in
a flashover across the insulator string from ground to conductor.
34
WHY EARTH WIRE?
Maximum allowable fault current (I) through earth wire mainly
depends on
Area of earth wire (A)
Maximum permissible temperature
Time of short circuit (t)
I varies proportional to A and inverse proportion to sqrt (t)
35
SHIELD ANGLE
Earth wire is placed on top of the structure to
provide a shied angle for protection against
lightning
over
power
conductors,
the
recommended angle being 30 degree with the
vertical in case of vertical formation of power
conductors.
Location where isokeraunic levels are high, lower
angle of shielding may be adopted
As cross arm width increases, horizontal spacing
of conductor increases . To protect the conductors
with specified shield angle, earth wire has to be
placed at a higher elevation in such cases. To
reduce the tower peak height, double peak with
double earth wire are used in those cases
36
STANDARD NORMAL SPAN
FOR VARIOUS VOLTAGE CLASSES
VOLTAGE
SPAN RANGE (METERS)
11 kV
75-100
33 kV
180-305 ( 90-135 over poles)
66 kV
204-320
132 kV
305-365
220 kV
320-380
400 kV
350- 450
765 kV
400-450
37
MINIMUM GROUND CLEARANCE
VOLTAGE
MINIMUM GROUND CLEARANCE
IN METERS (IS 5613)
11 kV
5.2
33 kV
5.2
66 kV
5.5
132 kV
6.1
220 kV
7.0
400 kV
8.84
765 kV
15.0
38
NO OF CROSS ARMS
AND ITS CONFIGURATION
3 for single circuit line
6 for double circuit line
12 or more for multi circuit lines
Cross arms can be of Horizontal / Vertical or Triangular
configuration
39
MINIMUM PHASE TO PHASE
ELECTRICAL CLEARANCE
VOLTAGE
MINIMUM PHASE CLEARANCE
(APPX) MM ( IS 5613)
11 kV
760
33 kV
1500
66 kV
2000
132 kV
3900
220 kV
6000
400 kV
8000
765 kV
15000
40
WHAT IS GALLOPING?
Galloping (dancing of conductor) is Very low frequency, high
amplitude vibrations induced by:
High velocity steady winds on conductors with asymmetrical
ice deposit
When ice on a portion of ice covered conductor melts and
suddenly drops off
When a flock of birds perching together on a conductor
suddenly takes off, leaving the conductor jumping in loops
Other wind induced vibrations are:
Aeolian vibrations : High frequency, low amplitude vibrations
induced by low, steady & laminar wind
Wake induced vibrations: Low frequency, medium amplitude
vibrations induced by high velocity steady winds on bundle
41
conductors
CONDUCTOR SAG
S= sag
Conductor sag depends on
Type of conductor
Span length
Weight of conductor
Conductor tension
Sag S = WL2 / 8T
L= span
W = conductor weight per meter
L= span length ( tower spacing)
T= Conductor Tension.
Developed Length D= L+ W2 L3
24T2
42
INSULATOR ASSEMBLY LENGTH
Voltage
Approximate Standard insulator assembly
length, single suspension string
11 kV
200 mm
33 kV
550 mm
66 kV
965mm
132 kV
1630 mm
220 kV
2340 mm
400 kV
3740 mm
765 kV
5500 mm
43
MINIMUM TOWER HEIGHT
MINIMUM TOWER HEIGHT IS GOVERNED BY
Minimum ground clearance (A)
+
Maximum sag (B)
+
Insulator assembly length ( C)
(for suspension tower only)
+
Cross arm spacing
(vertical conductor separation) ( D)
+
Earth wire peak distance from top most
cross arm point ( E)
D
D
C
B
A
44
CROSS ARM SIZE (WIDTH)
Minimum electrical clearance of conductor/ jumper from Tower body
(IS 5613)
Voltage
Minimum Body
clearance ( mm)
11 kV
33 kV
330
66 kV
610
132 kV
1070
220 kV
1675
400 kV
1860
765 kV
45
LOADS ON TOWER
VERTICAL LOADS
Dead weight of Tower
Dead weight of conductor & Earth wire
Live weight of working personal,
hoisting tools & tackles etc.
Snow loading (wherever applicable)
Transient loads
HORIZONTAL LOADS
For the purpose of convenience we
consider all horizontal loads in two
perpendicular axes
One in Transverse direction w.r.t cross
arm
One in longitudinal direction w.r.t cross
arm
46
ORIENTATION OF TOWER w.r.t CROSS ARM
A. Suspension Tower
Longitudinal direction
Line alignment
Transverse direction
Suspension tower positions
Longitudinal direction
Line alignment
Cross arm orientation (plan)
47
ORIENTATION OF TOWER w.r.t CROSS ARM
B. Angle Tower
Angle of
deviation
Angle of
deviation
Angle Tower Positions
Bisector
Cross Arm Orientation of Angle tower (plan)
48
TRANSVERSE LOAD ON TOWER
On account of wind pressure on tower body
On account of wind pressure on conductor, earth wire &
insulator string
On account of conductor / earth wire pull
Conductor
Wind load on tower = wind
pressure x projected area
Wind load on conductor/earth
wire = wind pressure x
projected area
49
TRANSVERSE LOAD ON TOWER ON A/c OF
CONDUCTOR / EARTHWIRE PULL
= angle of Deviation
Tsin /2
= 180 -
Tsin /2
T
2Tcos /2
50
LONGITUDINAL LOAD ON TOWER ON ACCOUNT
OF CONDUCTOR/ EARTHWIRE PULL
Longitudinal direction
Transverse direction
51
LONGITUDINAL LOAD ON TOWER
A. On account of conductor / Earth wire pull
In normal case, Longitudinal load due to conductor pull cancel
each other except for broken wire condition (BWC) where there
will be imbalanced pull on the cross arm.
DEAD END TOWER which are used for termination of a line at
switch yard end are subjected to severe pull by conductor which
are strung on one side only.
B. On account of unbalanced Tension of conductor / earth wire on
two sides of towers which may happen due to error during final
tensioning & temperature variation which may cause unbalance
tension due to linear expansion/ contraction when section length
on either side of the tower are different.
C. Under Broken wire condition (BWC)
52
LONGITUDINAL LOAD ON TOWER
Switch yard gantry
Dead End Tower
Connection to Switch yard gantry is
done at a later stage and with slack
span only
53
CONCEPT OF WEIGHT SPAN
What is weight span ?
It is the span length (length of conductor or earth wire)
which contribute to the vertical load on tower.
Weight span
(left)
Weight span
W1
Weight span
(right)
Weight span
W2
54
WHY NEGATIVE WEIGHT SPAN OCCURS ?
On steeply inclined spans, the low point of sag may fall beyond the
lower support. This indicates that the conductor in the uphill span is
exerting a negative or upward force on the lower tower. The amount
of this upward force is equal to the weight of the conductor from the
lower tower to the low point in the sag. If upward pull of the uphill
span is greater than the downward load of the next adjacent span,
actual uplift will be caused.
55
NEGATIVE WEIGHT SPAN
Total weight span of tower A = L A RA
Total weight span of tower B = L B + RB
B
LA
A
(-)RA
LB
RB
56
THEORETICAL FORMULA FOR CALCULATION
OF WEIGHT SPAN BETWEEN TOWERS AT
DIFFERENT ELEVATION
x = Distance of low point from
center of span in meter.
T = Conductor tension in kgf
h = Difference between
conductor support level in Mtr.
w = Unit weight of conductor in
kg/meter.
l = span length in meter
Distance of Null point or Low point of conductor from the center of span
is given by the formula x = (T h) / (w l)
Weight Span :
for Tower A, right hand side only: A = l / 2-x
for Tower B, left hand side only: A = l / 2+x
Similarly, weight span for other side of towers can be calculated and
57
total weight span obtained
THEORETICAL CONCEPT OF OF
NEGATIVE WEIGHT SPAN
T=T2COS2 = T1 cos 1
T2SIN 2 = wL2
T1
T2 COS 1 = T1COS 1
L1
T2SIN 2+wL1=T1SIN 1
T2
w(L1+L2)=T1SIN 1
L2
T
T1
T2
2
T2
wL1
58
SIGNIFICANCE OF NEGATIVE WEIGHT SPAN
Negative weight span will mean that conductor/ earth wire in
such a location will produce a vertically upward load instead of
vertically down in normal cases.
Vertically upward load = (-) weight span x weight per unit
length of conductor/ earth wire
EFFECT OF NEGATIVE WEIGHT SPAN
Effect of negative weight span is that suspension tower can not
be used at location with negative weight span as it will lift up
the suspension insulators. Angle towers are therefore, to be
used for such locations even if angle of deviation is zero
59
CONCEPT OF WIND SPAN
WHAT IS WIND SPAN?
It is the span length ( length of conductor & Earth wire) which contribute
to the transverse horizontal load on the tower
X1
X2
Wind span = ( X1 + X2) / 2
Wind load on conductor/ Earth wire = wind pressure x projected area
60
TOWER SPOTTING
Tower spotting is the process of choosing right type of Tower
along the line route
STEPS INVOLVED
Choosing Techno economical line route
Fixing of Angle ( deviation point) to avoid/ minimize obstacles
enroute
Taking levels at intermediate points for drawing of profile
between Angle points ( Digital instruments like total stations are
now a days used)
Drawing of Profile ( Electronic soft wares are now a days used
using data from digital instruments
61
TOWER SPOTTING
Tower spotting is done either manually using sag template
curves or through electronic soft ware like PLSCAD
Tower spotting on profile
62
SAG TEMPLATE CURVE
Conductor & Earth wire when strung between towers normally
takes shape of a catenary curve. Catenary curves of conductor
drawn at the working tension forms the sag- template curve.
Plastic sag-templates are made for the purpose of manual
tower spotting and also for random checking of spotting done
through electronic soft ware
63
TOWER SPOTTING DATA
Once the technical parameters like angle of deviation, weight
span, wind span etc are tabulated, the next step is to choose the
correct type of towers at various locations after comparing the
field parameters with the design parameters. In case of hillly
terrains, towers with unequal leg extension are also used. This
is mainly adopted to reduce benching work in a particular
location. The design parameters are contained in a document
called Tower- spotting Data.
64
UNEQUAL LEG EXTENSIONS
( + 3 mtr Extn.)
Leg C ( + 4.5 mtr Extn.)
( + 6 mtr Extn.)
Leg D ( + 6 mtr Extn.)
132 kV Badarpur Khliehriat Line
Loc. No. 1 C+LE (3, 3, 3, 6)
65
SAMPLE TOWER SPOTTING DATA
66
SAMPLE TOWER SPOTTING DATA
67
SAMPLE TOWER SPOTTING DATA
68
TOWER SCHEDULE
Loc Angle of
No Deviation
Weight Span
Left
Right
Total
Wind Span
Left
Right
Total
Recommended
tower type
69
GENERAL IDEA ON WIND PRESSURE
Wind pressure is proportional to wind velocity
Wind pressure zones
India is divided in 6 ( Six) wind zones based on wind speed
Wind Zone
Basic wind speed (Vb) m/sec
33
39
44
47
50
6
55
Vb is based
on peak gust velocity averaged
over a short time
interval of about 3 ( Three) seconds
Note: Wind as per IS 802 and Wind zone as per IS 875
70
WIND ZONES OF INDIA
71
WIND ZONES & BASIC WIND SPEEDS OF NER
Name of states
Wind zone
Basic wind speed ( Vb)
m/sec
Assam
6/5/4/2
55/50/47/39
Meghalaya
6/5/4
55/50/47
Arunachal Pradesh
5/3
50/44
Nagaland
4/3
47/44
Manipur
6/5/3
55/50/44
Mizoram
55
Tripura
55
72
WIND ZONE - ASSAM
73
WIND ZONE -MIZORAM
74
WIND ZONE - MANIPUR
75
WIND ZONE - MEGHALAYA
76
WIND ZONE - ARUNACHAL PRADESH
77
WIND ZONE - TRIPURA
78
WIND SPEED
METEOROLOGICAL REFERENCE WIND SPEED ( VR)
VR is extreme value of wind speed over an averaging period of 10
( ten) minutes duration.
VR = Vb/ K0
K0 is taken as 1.375 to convert 3 seconds peak gust speed in to 10
minutes average
DESIGN WIND SPEED ( Vd)
Vd = VR x K1 x K2
K1= Risk coefficient
K2 = Terrain Roughness coefficient
79
SELECTION TABLE FOR K1
Wind Zones
Reliability Level
Level 1 (up to 400 kV)
1.00 1.00 1.00 1.00 1.00 1.00
Level 2 (above 400 kV)+
triple & Quad ckt up to 400
kV
1.08 1.10 1.11 1.12 1.13 1.14
Level 3 (Tall River crossing
& special tower)
1.17 1.22 1.25 1.27 1.28 1.30
80
SELECTION TABLE FOR K2
Terrain Category
Value of K2
Cat 1: Exposed terrain with few or no obstructions
with average height of objects less than 1.5 m like
open sea coast/ water stretch, deserts, flat tree less
terrain
1.08
Cat 2: Open terrain with well scattered obstructions
having height between 1.5m to 10 m like normal
country with very few obstacles.
1.00
Cat 3 : Terrain with numerous closely spaced
obstructions like built up & forest area
0.85
Note: For lines encountering Hills/ ridges, K2 should be taken as next
higher value.
81
DESIGN WIND PRESSURE ( Pd )
Design wind pressure Pd = 0.6 Vd2 in N/ m2
82
WIND LOAD ON TOWER
Tower is divided into suitable nos of
panels taken between intersection of
legs and bracings say height of h
Fwt = pd x cdt x ae x GT in newton ( N)
Where
Pd = design wind pressure in N/m2
Cdt = drag coefficient
Ae = net projected area of members
GT = gust response factor
Note: Drag coefficient depends on solidity ratio
83
VALUE OF DRAG COEFFICIENT Cdt
FOR TOWER
Solidity Ratio
Drag Coefficient Cd
Up to 0.05
3.6
0.1
3.4
0.2
2.9
0.3
2.5
0.4
2.2
0.5 and above
2.0
84
SOLIDITY RATIO
Solidity ratio = Protected area of all members
Area of frame
NOTE: Drag coefficient takes in to account the shielding effects of
wind on the leeward face but if leeward members are not shielded
by the windward face, projected area of the leeward members shall
also be considered in the calculation
85
VALUES OF GUST RESPONSE FACTOR FOR
TOWER ( GT) AND INSULATOR ( GI)
86
WIND LOAD ON CONDUCTOR
& GROUND WIRE
Fwc = Pd x Cdc x L x d x Gc
Pd = Design wind pressure in N/m2
Cdc = Drag coefficient (1.0 for conductor and 1.2 for ground wire
/ earth wire)
L = Wind span = Half of sum of adjacent span
d = Diameter of conductor/ Earth wire in meter
Gc = Gust response factor
87
VALUES OF GUST RESPONSE FACTOR GC
FOR CONDUCTOR & EARTH WIRE
88
WIND LOAD ON INSULATOR STRING
Fwi = Pd x Cdi x Ai x Gi
Pd = Design wind pressure in N/m2
Cdi = Drag coefficient to be taken as 1.2
Ai = 50 % projected area of insulator string
Gi = Gust response factor
Note: No masking effect will be considered in case of multiple /
V insulator strings
89
TENSION LIMIT OF CONDUCTOR & E/WIRE
( Ref: IS 802 Part I/Sec I, 1995)
Conductor /Earth wire tension at everyday temperature and without
external load, should not exceed the following:
Condition I
Initial unloaded tension : 35 % of ultimate tension strength ( UTS)
Final unloaded tension: 25% of UTS ( for voltage level upto 220 kV)
22% for conductor & 20 % for Earth wire
( for 400 & 800 kV level)
90
TENSION LIMIT OF CONDUCTOR & E/WIRE
( Ref: IS 802 Part I/Sec I, 1995)
Condition II
Ultimate tension under every day temperature and 100%
design wind pressure or minimum temp. & 36% design wind
pressure should not exceed 70 % of UTS
Every day Temperature:
Shall be considered as : 32 C where minimum Temperature
will be above (-) 5 C
15 C where minimum temperature
will be (-) 5 C or below
91
FORMULA FOR CALCULATING CHANGE IN
TENSION OF CONDUCTOR/ E/WIRE DUE TO
CHANGE IN TEMP & PRESSURE (REF: IS 563 PART I)
T22 [ T2 { (T1 - l2w2q12 )/ 24T12 -t}] = l2w2q22 / 24
where
T2 = Tension at temp. t2 C in kg
T1 = Tension at temp. t1 C in kg
l = Span length in meter
W= Weight per meter
q1 = ( w2 +w12 )/w w1 = wind load in kg/ m
= EA
E = Young modulus in kg/ cm2
A= Cross section area ( m2)
= Coefficient of linier expansion per C
Q2 = loading factor
t = (t2 t1) C
92
SAG TENSION CHART
With change in ambient temperature, tension on conductor and
earth wire shall also change in the following pattern because of
thermal expansion/ contraction in the following manner
Temperature increases : Tension decreases
Temperature decreases : Tension increases
It is therefore important that correct tensions are maintained
during stringing of conductor / earth wire corresponding to
ambient temperature so that design tension and sags are
maintained during worst loading conditions as already
explained earlier
93
SAG TENSION CHART
For this purpose, tension and sags at different ambient
temperatures are calculated corresponding to base working
tension at every day temperature and with no wind & using
formula already discussed earlier.
The results are than tabulated in a convenient way for reference
94
SAG TENSION CHART
95
METHOD OF MAINTAINING CORRECT
TENSION AT THE TIME OF STRINGING
By measuring sag
By measuring tension
STEPS
Step-I
: Measure ambient temp.
Step II: Calculate average ruling span of the section using the
following formula
Step III : Consult Sag- Tension chart and note sag and tension
value corresponding to ambient temp. and corresponding
to average ruling span.
Step IV : Select the span whose length is nearest to the ruling span
& adjust sag or tension so as to attain the required value
before final tensioning (clamping on tower)
96
TOWER LOADING CONDITIONS
Loadings shall be determined for the Two loading conditions
Combination I : Corresponding to maximum wind at mean
annual temperature.
Combination II : Corresponding to 2/3 rd maximum wind at
the minimum temperature.
97
TOWER LOADING - TRANSVERSE LOADS
WIND LOADS
NORMAL CONDITION
On conductors and
ground wires on
full projected areas
Corresponding to full wind Corresponding to 50% of intact
span of bundled
span and 10% of broken span of
conductors & ground wire bundled conductor/ ground wire.
On Tower
On 1.5 times the projected
areas of members on the
windward face of towers
On insulator strings
1) Suspension
100 kg
2) Tension
300 kg
BROKEN WIRE CONDITION
On 1.5 times the projected areas
of members on the windward
face of towers
100 kg
300 kg
98
TOWER LOADING - TRANSVERSE LOADS
DEVIATION
LOADS
NORMAL
CONDITIONS
Transverse components
tension of bundled
conductors and ground
wire
BROKEN WIRE
CONDITIONS
a)
Suspension tower
Transverse components
corresponding to 50% of
the tension of bundled
conductors or 100% of the
tension of ground wire.
b)
Tension tower
Transverse component
corresponding to 100% of
the tension of bundled
conductor/ ground wire
99
TOWER LOADING VERTICAL LOADS
DUE TO
CONDUCTOR
NORMAL
CONDITIONS
BROKEN WIRE
CONDITIONS
Suspension
tower
Equal to the maximum/
minimum weight span of
bundled conductors
60% of maximum/
minimum weight span of
bundled conductors
Tension Tower
Equal to maximum weight
span of bundled
conductors ( downward or
upward)
60% of maximum weight
span of bundled
conductors ( downward or
upward)
100
TOWER LOADING VERTICAL LOADS
DUE TO
GROUND WIRE
NORMAL
CONDITIONS
BROKEN WIRE
CONDITIONS
Suspension tower
Equal to the maximum/
minimum weight span of
Ground wire
60% of maximum/
minimum weight span of
Ground wire
Tension Tower
Equal to maximum
weight span of Ground
wire ( downward or
upward)
60% of maximum weight
span of Ground wire
( downward or upward)
Due to Insulator &
conductor
Accessories
Equal to the weight of
Equal to the weight of Insulator
Insulator strings, spacers, strings, spacers, dampers etc
dampers etc
101
TOWER LOADING - LONGITUDINAL LOADS
DUE TO POWER
CONDUCTOR
NORMAL
CONDITIONS
BROKEN WIRE CONDITIONS
Suspension Towers NIL
50 % of the tension of bundled
conductors
Tension Towers
Equal to the tension of
bundled power
conductors for deadend towers only
Equal to the components of tension
of the bundled power conductors
corresponding to the relevant angles
of deviation
Due to Ground
wire
Normal conditions
Broken wire conditions
Suspension Towers NIL
Tension Towers
Equal to the tension of Ground wire
Equal to the tension of Equal to the components of tension
Ground wire for
of the Ground wire corresponding to
dead-end towers only the relevant angles of deviation
102
TOWER LOADING ERECTION LOADS
NORMAL
CONDITIONS
BROKEN WIRE
CONDITIONS
Man with Tools
NIL
Equal to the tension of
Ground wire
Loads due to lifting
tackles, line car etc
(to be considered at
conductor cross arm
and lifting points)
Equal to the
tension of
Ground wire for
dead-end towers
only
Equal to the components
of tension of the Ground
wire corresponding to
the relevant angles of
deviation
Note: The design of towers shall be based on loading combination
and condition which is more stringent for the particular member
103
FOUNDATION LOADINGS
Calculated from Tower Loadings
Typical Tower Loading tree is indicated below
104
FOUNDATION LOADINGS
Loads transmitted to Foundation through tower legs
Two types of loads act on foundation
A. VERTICAL ( + )
B. Horizontal or side thrust
105
UNDER VERTICAL LOAD
106
UNDER HORIZONTAL LOAD
A. OVERTURNING
OVERTURNING
107
UNDER HORIZONTAL LOAD
B. SLIDING
SLIDING
108
VERTICAL LOAD ON FOUNDATION
WIND
FORCE
VLM VLw
VLw
FST
L
VLM
FST
109
LOAD ON FOUNDATION
On account of gravity force (weight) on tower
If W = Total gravity force ( weight)
Then vertical load (VL) on account of W on each leg,
VLw = W/4 which acts downward (down thrust)
On account Horizontal forces (transverse / longitudinal ) on tower
Which produces turning moment at the base of tower
Net Moment MT = FH x h
Where FH = Horizontal force at a particular height
h = corresponding height from foundation top
110
LOAD ON FOUNDATION
External Moment M produces restoring moment in the form of upward &
downward thrust at leg/ foundation
Restoring Moment
MR = 2(upward/ downward thrust in each leg x leg to leg dist)
i.e. MR = 2 VLM x L
For stability: Net turning moment = Net Restoring moment
i.e. MT = MR ;
i.e. MT = 2VLM x L ; i.e. VLM = MT/2L
Net down thrust on 2 legs on one side
= +( VLW + VLM)
Net upward thrust on 2 legs on other side = - ( VLM VLW)
Normally VLM >>VLW and therefore there is net upward thrust on 2 legs
of a tower which also acts on the foundation and this is called uplift on
foundation
111
FOUNDATION LOADING WIND ZONE-II (33 M/SEC)
FOR 400 KV D/C TOWER WITH TWIN MOOSE CONDUCTOR
TOWER TYPE
COMPRESSION
(Kg)
UPLIFT (Kg)
SIDE THRUST
(TRANS) (Kg)
SIDE THRUST
(LONG) (Kg)
DA + 0
50,000
37,500
2450
1750
DA + 3/ 6 /9
53,500
39,500
2700
2750
DB + 0
81,000
65,000
4850
4700
DB + 3 / 6 /9
84,400
65,500
5150
4300
DC + 0
99,500
82,000
5550
5050
DC + 3 / 6 / 9
1,03,000
82,600
5750
4600
DD + 0
1,47,000
1,2,8500
8250
6000
DD + 3 / 6 / 9
1,53,500
1,31,300
8000
5500
112
LOAD ON FOUNDATION
B. HORIZONTAL LOAD ON FOUNDATION
Horizontal forces on tower also produces side thrust on
foundation
Side Thrust FST = FH / 4
Earth-quake forces
113
TOWER FOUNDATION
TASKS TO BE PERFORMED BY TOWER FOUNDATION
It must keep the tower rooted to the ground all the time under worst
loading conditions
It must be durable throughout life span of the transmission line
It must be cost effective
It should offer ease in construction
STABILITY OF THE TOWER FOUNDATION
It must effectively resist down thrust
It must effectively resist up thrust ( up lift)
It must effectively resist side thrust
It must effectively resist earth quake forces
114
TOWER FOUNDATION
Countering of down thrust is through suitable design so that
a)
Foundation is strong enough against compression, bulking &
Shear failure
b)
Base area is adequate to avoid soil settlement ie adequate
against soil bearing capacity
Countering of uplift is generally provided by adequate counter
weight which will be provided by
a)
Weight of foundation
b)
Weight of earth contained in the frustum of a pyramid on
footing pad with side inclined at certain angle depending on
soil type.
115
TOWER FOUNDATION
c) A footing with an under cut generally develops uplift
resistance of two to three times that of an identical footing
without under-cut. Under-cut foundations are normally
provided in fissured & soft rock foundations.
116
TOWER FOUNDATION
Failure plane
Soil Shear Stress
Undercut
Foundation
117
TOWER FOUNDATION
FOUNDATION TYPE
BROAD CLASSIFICATION :
Open Cast Most commonly used
Augured under reamed pile (where open excavation is Problematic)
Pile foundation
Well foundation
On Special Locations:
- River Bed,
- Nearby river, prone to erosion,
- Weak soil
118
OPEN CAST FOUNDATION
119
AUGURED UNDER REAMED PILE
FOUNDATION
120
PILE FOUNDATION
121
WELL FOUNDATION
122
PILE FOUNDATION
123
PILE FOUNDATION CONSTRUCTION
LIFTING OF CAGE
124
PILE FOUNDATION CONSTRUCTION
Lowering of reinforcement cage in pile bore
125
PILE FOUNDATION CONSTRUCTION
Lowering of reinforcement cage in pile bore
126
PILE FOUNDATION CONSTRUCTION
Installed pile
127
PILE FOUNDATION CONSTRUCTION
Laying of reinforcement for pile cap & pedestal
128
PILE FOUNDATION CONSTRUCTION
Erected tower on pile foundation
129
WELL FOUNDATION
WELL FOUNDATION
130
WELL FOUNDATION UNDER CONSTRUCTION
131
OPEN CAST FOUNDATION
Most commonly used, Convenient & quick in execution where
there is no high water table and soil collapse problem.
COMMON TYPE OF OPEN CAST FOUNDATION:
Depending on type of materials used
Steel Grillage Type foundation
PCC / RCC foundation
Depending on extent of excavation
Individual footing
Chimney frustrum type
Chimney Pad type
Block type
Spread type footing
132
STEEL GRILLAGE TYPE FOUNDATION
133
PCC / RCC FOUNDATION
134
CHIMNEY- PAD TYPE FOUNDATION
135
BLOCK TYPE FOUNDATION
136
SPREAD TYPE FOUNDATION
137
OPEN CAST FOUNDATION (Contd.)
Depending on type of soil
Normal dry soil foundation
Dry fissured rock (with under cut)
Rock Foundation (Anchored)
Black Cotton soil foundation, commonly known as Wet
Black Cotton (WBC) type.
Depending on depth of water table
Dry Foundation: Water table below footing depth
Wet Foundation: Water table 1.5 M from ground surface
Partially Submerged (PS): Water table between 1.5 to 0.75 m
from ground surface
Fully Submerged (FS): Water table above 0.75 m
138
WHY CLASSIFICATION
BASED ON WATER TABLE?
Weight of soil and concrete is less when submerged in water
because of buoyancy effect and therefore offers less
resistance to uplift then in dry condition.
Angle of internal friction () is less for wet soil and
therefore volume of frustum of soil above footing pad is less
in wet condition & therefore offers less resistance to uplift.
Economy in cost is therefore achieved in classifying
foundations based on water table instead of adopting one
type considering worst condition (F.S type)
139
FOUNDATION VOLUME
Comparison of foundation volume for different fdn classification:
Name of Line : 400 kV D/C Misa- Balipara
TOWER
TYPE
CONCRETE VOLUME (CUM)
DRY
WET
P.S
F.S
DA
9.68
10.33
12.69
15.74
DB
24.94
28.51
34.99
42.09
DC
27.86
43.531
53.049
63.62
DD
34.56
50.219
58.35
133.84
140
THANK YOU
141