BUILT-UP RATE FOR SCREEDING
TENDER FILE NO :
PROJECT :
LOCATION :
SUPPLIER :
SUB-CONTRACTOR :
QUOTATION DATE :
Material Cost
Cement 10.35 per bags 50kg ( Including Rm 0.25 for unloading )
Sand (ex-mining) 250.00 per loads ( 14 cu. yard ) or 23.48 per m3
Cement & Sand ( 1:3 ) Mixed Material Cost
Cement ( 1440kg/50 ) @ 1 m3 29 bags @ 10.35 300.15
White Lime ( 1 bag / 100 ft2 ) 0 bags @ 0.00 -
Sand 3 m3 @ 23.48 70.45
Total cost For 4 m3 370.60
Net volume after shrinkage @ 33 1/3% 2.67 m3
Material cost per m3 138.90
Plant cost ( Concrete mixer @ 3.00/m3 ) 3.00
Total Cost : 141.90
Labour Cost
Base screed 3.23 per m2 ( 0.30 per ft2 )
Labour Cost 2.20 per m2 ( 0.20 per ft2 )
Screeding Cost / m2
20mm thk 25mm thk
Material cost 2.84 3.55
Wastage @ 5% 0.14 0.18
Total material cost / m2 2.98 3.72
Labour Cost 2.20 2.20
Plant Cost ( Inclusived ) - -
Tender Cost / m2 5.18 5.92