88% found this document useful (8 votes)
9K views17 pages

Labour Productivity Rates

This document outlines productivity rates for various carpentry, masonry, plastering, and screeding works. It lists 24 types of carpentry formwork with expected production rates in square meters per hour for different crew sizes and job complexities. Block work and plastering productivity is also provided for tasks like hollow blockwork, plastering walls, and screeding floors - listing expected production in units like number per hour or square meters per hour based on crew size. Standard remarks are also included to provide additional context.

Uploaded by

mohammednatiq
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
88% found this document useful (8 votes)
9K views17 pages

Labour Productivity Rates

This document outlines productivity rates for various carpentry, masonry, plastering, and screeding works. It lists 24 types of carpentry formwork with expected production rates in square meters per hour for different crew sizes and job complexities. Block work and plastering productivity is also provided for tasks like hollow blockwork, plastering walls, and screeding floors - listing expected production in units like number per hour or square meters per hour based on crew size. Standard remarks are also included to provide additional context.

Uploaded by

mohammednatiq
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

Labour's Productivity Rates

Carpentry Work

Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
2 CARPENTERS, 1
1 Formwork to footings 12
HELPER
2 CARPENTERS, 1
2 Formwork to isolated footings 16
HELPER
2 CARPENTERS, 1
3 Formwork to rafts 14
HELPER
2 CARPENTERS, 1
4 Formwork to rafts D>0.75m 18
HELPER
2 CARPENTERS, 1
5 Formwork to tie beams 10
HELPER
2 CARPENTERS, 1
6 Formwork to high level tie beams D>0.45M 12
HELPER
2 CARPENTERS, 1
7 Formwork to Neck Columns 4
HELPER
2 CARPENTERS, 1
8 Formwork to U/G Water tank 6
HELPER
2 CARPENTERS, 1
9 Formwork to basement retaining walls 9
HELPER
2 CARPENTERS, 1
10 Formwork to columns (small size) 7
HELPER
2 CARPENTERS, 1
11 Formwork to Columns (large size) 9
HELPER
2 CARPENTERS, 1
12 Formwork to D/S beam internal (shallow) 6
HELPER
2 CARPENTERS, 1
13 Formwork to D/S beam external (Deep) 7
HELPER
2 CARPENTERS, 1
14 Formwork to D/S beam external (Shallow) 4
HELPER
2 CARPENTERS, 1
15 Formwork to D/S beam external (Deep) 6
HELPER
2 CARPENTERS, 1
16 Formwork to lift walls single core 6
HELPER
2 CARPENTERS, 1
17 Formwork to lift walls multi core 8
HELPER
2 CARPENTERS, 1
18 Formwork to slab decking (10ft) hourdi 16
HELPER
to slab decking (>10ft) hourdi D/S 2 CARPENTERS, 1
19 Formwork 12
beams HELPER
2 CARPENTERS, 1
20 Formwork 2 CARPENTERS, 1 HELPER 12
HELPER
2 CARPENTERS, 1
21 Formwork to slab decking (>10ft) hourdi to slab decking (>10ft) hourdi 10
HELPER
2 CARPENTERS, 1
22 Formwork to staircase (non spiral) 4
HELPER
2 CARPENTERS, 1
23 Formwork to balcony parapets 6
HELPER
2 CARPENTERS, 1
24 Formwork to roof parapets 8
HELPER

D = DEPTH
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
Labour's Productivity Rates

Block Work & Plaster Work

Production Rate
# Descraption Location Crew Size
(ML. Per Hour)
MASONARY WORKS

1 Hollow Blockwork (100, 150 & 200 mm) - 1 MASON, 1 HELPER 120 NR

2 Hollow Blockwork (large panels) - 1 MASON, 1 HELPER 140 NR

3 Solid blockwork - 1 MASON, 1 HELPER 95 NR

4 Solid Blockwork as Raft forms - 1 MASON, 1 HELPER 110 NR

PLASTERWORK

5 Plaster Final Coat Internal / walls 1 MASON, 1 HELPER 16 SM

6 Plaster Rush Coat Internal / walls 2 HELPER 150 SM

7 Plaster (internal), walls mesh Internal / walls 1 HELPER 100 SM

8 Plaster Hacking Internal / walls 1 HELPER 100 SM

9 Plaster (internal), walls guide point Internal / walls 1 MASON, 1 HELPER 100 SM

10 Plaster Corner Beads Internal / walls 1 MASON, 1 HELPER 100 SM

11 Plaster With Grooves External Walls 1 MASON, 1 HELPER 10 SM

12 Plaster Without Grooves External Walls 1 MASON, 1 HELPER 12 SM


13 Plaster Rsh Coat External Walls 2 HELPER 150 SM

14 Plaster (external), walls mesh External Walls 1 HELPER 100 SM

15 Plaster Hacking External Walls 1 HELPER 100 SM

16 Plaster Guide Points External Walls 1 MASON, 1 HELPER 100 SM

17 Plaster Crner Beads External Walls 1 MASON, 1 HELPER 100 SM

18 Plastering of Arches/Mullians Arches/Mullians 1 MASON, 1 HELPER 80

19 Screed 50mm thick Floor 1 MASON, 1 HELPER 20

20 Screed 100 mm thick Roof 1 MASON, 1 HELPER 15

21 Screed 25mm thick Floor 1 Mason + 1 Helper 6


Remarks
Labour's Productivity Rates

Concrete Work

Production Rate (ML. Per


# Descraption Location Crew Size Remarks
Remarks
Hour)
KERBING / BLOCK PAVING WORKS

1 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE

2 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE

3 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE

4 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE


Interlock paving on pre prepared sub -
5 1 MASON, 1 HELPER 2 SM
base
6 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM
Haunching ot Kerb Base (Mixing
7 1 MASON, 1 HELPER 10 M 100M
Truck)
MANHOLE/ DRAINAGE CONSTRUCTION

8 Excavation for drains / manholes 1 HELPER 5 CM

9 Backfill to drains / manholes 1 HELPER 10 CM

10 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS

11 Plaster to manholes 1 MASON, 1 HELPER 2 NOS

12 Benching to manholes 1 MASON, 1 HELPER 4 NOS

13 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS

14 Fix gulley traps 1 MASON, 1 HELPER 1 NO

15 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M


CONCRETE PLACEMENT WORKS
Concrete to PCC blinding (100 mm
16 1 MASON, 10 HELPERS 27 CM
thick)
6 MASONS, 18 HELPERS, 1
17 Concrete to slabs/beams, by pump 180 CM
CARPENTER
1 MASON, 6 HELPERS, 0.5
18 Concrete to slabs / beams by crane 8,10 27 CM
OPERATOR
4 MASONS, 16 HELPERS, 2
19 Concrete to walls / columns, by pump 1.2 81 CM
CARPENTERS
1 MASON, 12 HELPERS , 0.5
20 Concrete by site mix 1.6 9 CM
CARPENTER
21 Concrete Columns 8 HELPERS 1.4 10

22 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.8 150

23 Concrete parapets/staircases 8 HELPERS 1 7

24 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80

25 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1 10

26 Concrete footings & pile caps 1 MASON + 4 HELPER 12 120

27 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6 60

28 Concrete column necks 8 HELPER 1.5 15

29 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15

30 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M 3


Labour's Productivity Rates

Miscellaneous Work

Production Rate (ML. Per


# Descraption Location Crew Size Remarks
Remarks
Hour)
MISCELLANEOUS LABOUR WORKS

1 Bitumen Paint Blockwork Surfaces 1 HELPER 40 SM

2 sealant (12 mm) Vertical 1 HELPER 25 METRE

3 sealant (12 mm) Horizontal 1 HELPER 50 EMTRE

4 Polythene sheet fixing General 1 HELPER 30

5 Shaping of Soil Blinding General 1 MASON + 1 HELPER 10M

6 Protection Board installation General 1 CARPENTER + 1 HELPER 80M 2

MISCELLANEOUS CARPENTARY WORKS

7 A/C subframe manufacture / fixing General 1 CARPENTER 5 NOS


Door subframe manufacture /
8 General 1 CARPENTER 4 NOS
fixing
9 Water bar fixing General 1 CARPENTER 20 METRE
Labour's Productivity Rates

Excavation Work

Production Rate (ML.


# Descraption Location Crew Size
Per Hour)

1 Manual Excavation General 1 HELPER 3M 3

2 Backfill + levelling General 1 HELPER 5M 3

Shaping of sloped earth for blinding for bases including


3 General 1 MASON + 2 HELPER 6 LM/Day
compaction
Remarks
Labour's Productivity Rates

Tilling Work

Production Rate
# Size Location Area Crew Size Remarks
(Sqm. Per day)
1 Ceramic Tiles By Mortar 30 X 30 Floor Kitchen 1 Mason, 1 Helper 14

2 Ceramic Tiles By Mortar 30 X 30 Floor with pattern Corridor 2 Masons, 1 Helper 10

4 Ceramic Tiles By Mortar 20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10

6 Ceramic Tiles By Mortar 30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5

8 Ceramic Tiles By Mortar 30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15

9 Ceramic Tiles By Mortar 30 X 30 Wall Bathroom 2 Mason, 1 Helper 7

10 Terrazzo Tiles By Mortar 30 X 30 Floor Roof 2 Mason, 1 Helper 16

Marble Tiles By Mechanical


11 Wall Elevations 2 Masons, 1 Helper 5
Methode 30 X 60

12 Ceramic Tiles Cutted Pieces Floor General 1 MASON 20

13 Marble Tiles By Mortar Floor General 1 Mason, 1 Helper 6

Notes:
1 - One Day = 10 Houres
Labour's Productivity Rates

Reinforcement Work

Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
1 Fix Rebar Footings & Tie Beams 1 STEEL FIXER 25
Walls, Columns,
2 Fix Rebar 1 STEEL FIXER 20
Beams, Solid Slabs
3 Fix rebar Ribs of Hourdi Slab 1 STEEL FIXER 18
4 Fix rebar Mesh Reinforcement 1 STEEL FIXER 15
5 Fix rebar Hidden Beams 1 STEEL FIXER 20

6 Steel cutting and bending 18.25 mm - 1 STEEL FIXER 50

7 Steel cutting and bending 8 - 16 mm - 1 STEEL FIXER 40