NGR Test Procedure Overview

The document provides a test procedure for neutral grounding resistors (NGRs) that includes visual, electrical, and insulation resistance checks. The procedure involves 6 steps: 1) A visual and dimensional check of the NGR. 2) Measurement of the resistance value. 3) An insulation resistance test between connections. 4) A power frequency withstand test of the insulation. 5) A second insulation resistance test. 6) Checking connections and integrity of the terminal box. The tests confirm the dimensions and integrity of the NGR, measure its resistance, and ensure the insulation meets standards.

Uploaded by

zaheer ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
5K views6 pages

NGR Test Procedure Overview

The document provides a test procedure for neutral grounding resistors (NGRs) that includes visual, electrical, and insulation resistance checks. The procedure involves 6 steps: 1) A visual and dimensional check of the NGR. 2) Measurement of the resistance value. 3) An insulation resistance test between connections. 4) A power frequency withstand test of the insulation. 5) A second insulation resistance test. 6) Checking connections and integrity of the terminal box. The tests confirm the dimensions and integrity of the NGR, measure its resistance, and ensure the insulation meets standards.

Uploaded by

zaheer ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Reference Documents
  • Scope
  • Nomenclatures
  • Test Procedure

Doc.

Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 1 of 6

Title: : ‫ﻋﻨﻮان‬

Neutral Grounding Resistor Test Procedure

 

Revision
‫ﺗﺎرﯾﺦ‬
‫وﯾﺮاﯾﺶ‬
Rev
Date ‫وﯾﺮاﯾﺶ‬ Description: :‫ﺗﻮﺿﯿﺤﺎت‬ Compiled Checked Approved
Doc. Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 2 of 6

Table of Contents

Scope …….…………………………………………………………………………………....
………………………………………………………………………………….... 03
………………………………………………………………………… 03
Reference Documents…………………………………………………………………………
………………………………………………………………………...
Nomenclatures………………………………………………………………………………... 04
………………………………………………………………...……… 05
Test Procedure………………………………………………………………………...………
1- Visual and Dimensional Check………………………………………………..………..
………………………………………………..… 05
2- Resistance Measurement Test………………………………………………………….
………………………………………………… 05
3- Primary Insulation Resistance Test (Megger Test) …………………………………….
………………………… 05
4- Rated Short Duration Power Frequency Withstand Tests …………...………………...
…………...……… 06
5- Lifting Secondary Insulation Resistance Test (Megger Test) ...…………………………
……………… 06
Doc. Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 3 of 6

Scope
This document provides the routine test procedure of the Neutral Grounding resistors
(NGRs). The routine test contains both electrical and visual check tests.

Reference Document

 Requirements, Terminology, and Test Procedure for


1972 “Requirements,
ANSI/IEEE–32, 1972,
Neutral Grounding Devices”.
Devices
 Insulation Co-ordination”.
IEC 60071–1, “Insulation Co
 ANSI/NETA ATA, “StandardStandard for Acceptance Testing Specifications for
Electrical Power Equipment and Systems”.
Systems
Doc. Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 4 of 6

Nomenclatures:
Frame earth: The overall frame or enclosure which is connected to the
earth.
Tie rods: Individual frame of each resistor blocks.
Megger test: Measurement of insulation resistance of components
Power frequency withstand A dielectric test in which the voltage is a low frequency
test: alternating voltage from an external source applied between
conducting parts and between conducting parts and ground

The overall test procedures are defined as follows:

1- Visual and Dimensional CCheck


2- Resistance Value Test
3- Insulation Resistance Test
4- Power Frequency Withstand Test
5- Insulation Resistance Test
6- Incoming & Outgoing cable connection & integrity of Terminal box connections

The sufficient explanation of each section is presented in the rest


res of the document.
Doc. Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 5 of 6

1- Visual and Dimensional Check


1-1- Confirm Overall dimension is in accordance with the latest revision of applicable
drawing.
1-2- Confirm integrity of all resistor connections.
1-3- Confirm all components are correctly installed and connected in accordance with the
latest revision of applicable drawing.
1-4- Confirm paint (or other coverage) of Enclosure has not been damage.
1-5- Confirm accuracy & fixing of name plates and labels.

2- Resistance Measurement Test


2-1- Using a digital ohmmeter check and record the value of DC resistance at ambient
temperature and correct its value to specified temperature. According to the IEEE-32-
IEEE
1972, Sec 10.1.4, acceptance tolerance in the lack of customer request is ±10%.
±10%

3- Primary Insulation Resistance Test (Megger Test)


3-1- Using a digital insulation test, apply acceptance DC voltage between the resistor H.V.
connection and individual resistor bank tie rods regarding the ANSI/NETA ATS Table
100.1. Minimum acceptance value is obtained from the Table 100.1.
3-2- Repeat test (3-1) between H.V.
H connection and frame earth with acceptance DC voltage
according to the ANSI/NETA
ANSI ATS Table 100.1. This test checks the integrity of
secondary insulation materials. Minimum acceptance value
value is obtained from the Table
100.1.

4- Rated Short Duration Power Frequency Withstand Tests (1


1 Minute)
Remove the connecting link between the resistor and any base point and/or LV connection.

4-1- Using a suitable external source, apply the specified voltage between
between terminals and
ground for the complete device extracted from IEC 60071-1 Table 2.
IEEE-32-1972, Sec. 10.3.2 apply the
4-2- Using a suitable external source according to the IEEE
specified voltage between terminals of each unit and its own individual frame.

Note: The voltage applied from the terminals of each assembly to its own frame shall be:
Doc. Name:
Name Neutral Grounding Resistor Test Procedure :‫ﻧﺎم ﻣﺪرك‬

Construction & Engineering Project: :‫ﻧﺎم ﭘﺮوژه‬ Customer: :‫ﻣﺸﺘﺮي‬


‫ﺷﺮﮐﺖ ﻣﻬﻨﺪﺳﯽ و ﺳﺎﺧﺖ ﭘﺎرﺳﺎن‬
(‫)ﻣﺴﺌﻮﻟﯿﺖ ﻣﺤﺪود‬ Doc. No: IQ – 15 – 0008
Date:
Rev.: 00 Page: 6 of 6

 Twice the rated voltage of the section of which the frame is a part plus 1000V when
2V p
rated 600V or less. Vrmsapplied  kV    1000
N

 2.25 times the rated value plus 2000V when rated over 600V.
2.25V p
Vrms  applied  kV    2000
N

In the event of a retest the voltage shall be 80% of the original test voltage.

5- Secondary Insulation Resistance Test (Megger Test)


To ensure that the insulations interval in the section (3) isn’t damaged, again the same test is
applied.

5-1- Using a digital insulation test apply acceptance DC voltage between the resistor H.V.
connection and individual resistor bank tie rods regarding the ANSI/NETA ATS Table
100.1. Minimum acceptance value is obtained from the Tabl
Table 100.1.
5-2- Repeat test (3-1) between H.V.
H connection and frame earth with acceptance DC voltage
according to the ANSI/NETA
ANSI ATS Table 100.1. This test checks the integrity of
secondary insulation materials. Minimum acceptance value is obtained from the Table
100.1.

6- Incoming & Outgoing cable connection & integrity of Terminal box


connections
6-1- Check dimension, distance and integrity of terminals in relation to final drawings.