JoJo Tank Stands - Recommended Installation Instructions

The document provides recommended instructions for installing a tank stand, including leveling the ground, marking foundations, digging foundations, placing and leveling the tank stand frame, casting cement around the stand legs, tying down the tank after 7 days, and filling the tank with water after 14 days. It notes that each stand has an engineer's certificate and drawing that should be read according to these instructions, and offers to provide those documents upon request.

Uploaded by

Mfundo Dlamini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3K views1 page

JoJo Tank Stands - Recommended Installation Instructions

The document provides recommended instructions for installing a tank stand, including leveling the ground, marking foundations, digging foundations, placing and leveling the tank stand frame, casting cement around the stand legs, tying down the tank after 7 days, and filling the tank with water after 14 days. It notes that each stand has an engineer's certificate and drawing that should be read according to these instructions, and offers to provide those documents upon request.

Uploaded by

Mfundo Dlamini
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Tank Stand Installation Instructions: Provides step-by-step guidelines for installing a tank stand, emphasizing critical placement and safety precautions.

To : ALL CUSTOMERS

In re : RECOMMENDED TANK STAND INSTALLATION INSTRUCTIONS

1. Level the ground as evenly as possible.


2. Place the frame on the ground where you want to install the tank stand.
3. Mark the four by one square meter foundations on the ground.
4. Dig the four foundations 1m deep.
5. Place 50mm spacers on the ground and place the tank stand on top of the spacers.
6. Place a spirit level on the tank stand and set it level on all 4 corners.
7. Make sure the tank stand is firm on the ground and cast the cement around the metal legs of the stand until
the cement is level with the ground.
8. Leave the cement 7 days and place the tank on top of the stand and tie it down with the ropes on the
corners.
9. Leave the stand and tank for 14 days and fill the tanks up with water.

Please note, each tank stand has a very specific Engineer’s Certificate and technical drawing based on the
size, which should be read in accordance to these instructions.

If you do not have these documents, please contact us and we will gladly send them to you.

Kind Regards

Bianca Harmse