Saudi Aramco Typical Inspection Plan: Cement Lining of Pipes & Fittings SATIP-H-002-01 Mechanical

This document is a typical inspection plan for cement lining of pipes and fittings. It outlines 5 project phases: 1) document review, 2) material receiving, 3) application and acceptance, 4) inspection responsibilities, and 5) general notes. Key inspection responsibilities include the contractor reviewing procedures, Saudi Aramco witnessing in-process inspections, and Saudi Aramco holding the final inspection and acceptance. The contractor is responsible for 100% inspection of in-process cement lining.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
709 views1 page

Saudi Aramco Typical Inspection Plan: Cement Lining of Pipes & Fittings SATIP-H-002-01 Mechanical

This document is a typical inspection plan for cement lining of pipes and fittings. It outlines 5 project phases: 1) document review, 2) material receiving, 3) application and acceptance, 4) inspection responsibilities, and 5) general notes. Key inspection responsibilities include the contractor reviewing procedures, Saudi Aramco witnessing in-process inspections, and Saudi Aramco holding the final inspection and acceptance. The contractor is responsible for 100% inspection of in-process cement lining.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SAUDI ARAMCO ID/PID FORM REV 7 - 010109 Rev 7 COS 31-March-13

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cement Lining of Pipes & Fittings SATIP-H-002-01 30-Apr-13 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Review Procedure: Cement- Mortar


1.1
protective lining for steel water pipe
SAIC-H-2001 SAIC-H-2001 RH R

2.0 MATERIAL RECEIVING

Receiving Inspection of Raw Materials for


2.1
Cement Lining [Includes storage]
SAIC-H-2002 SAIC-H-2002 H W/R
APPLICATION &
3.0
ACCEPTANCE

3.1 Verification of Cement Lining Equipment SAIC-H-2004 SAIC-H-2004 H W

3.2 Welding (if required) See remarks See remarks Refer to SATIP-W-011-001

Pre-Application Inspection of Cement


3.3
Lining
SAIC-H-2005 SAIC-H-2005 H W Use SATR-H-2001

3.4 In-Process Inspection of Cement Lining SAIC-H-2006 SAIC-H-2006 W S Notify SA before the start of work

Final Inspection & Acceptance of Cement


3.5
Lining [Includes repairs]
SAIC-H-2007 SAIC-H-2007 H H

GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
2
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
3
attendance.
4 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 1 of 1