GIMPA Lecture Hall Construction Update

This monthly progress report provides updates on the construction of two 3-story lecture hall blocks at Ghana Institute of Management and Public Administration (GIMPA) as of November 8, 2018. [1] Work is 52% complete for Lot 1 and 50% complete for Lot 2, slightly behind the planned 53% overall progress. [2] The report details progress made on each floor of each building, as well as staffing levels, materials on site, health and safety, weather impacts, and photos of ongoing work.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
99 views8 pages

GIMPA Lecture Hall Construction Update

This monthly progress report provides updates on the construction of two 3-story lecture hall blocks at Ghana Institute of Management and Public Administration (GIMPA) as of November 8, 2018. [1] Work is 52% complete for Lot 1 and 50% complete for Lot 2, slightly behind the planned 53% overall progress. [2] The report details progress made on each floor of each building, as well as staffing levels, materials on site, health and safety, weather impacts, and photos of ongoing work.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

GHANA INSTITUTE OF MANAGEMENT

AND PUBLIC ADMINISTRATION(GIMPA).

CONSTRUCTION OF 2 NO. 3 STOREY LECTURE


HALL BLOCKS AT GIMPA CAMPUS LOT 1 & 2 –
Accra

Monthly Progress Report

AS AT NOVEMBER 8th,2018

Employer: GIMPA, Accra-Ghana

Consultant: ALBERT ESSAMUAH ASSOCIATES LIMITED.

Contractor: China State Hualong Construction (GH) Ltd.


MONTHLY PROGRESS REPORT AS AT NOVEMBER 8th ,2018

Client: Ghana Institute of Management and Public


Administration, (GIMPA), Accra – Ghana
Commencement date: 24/11/17
Expected completion
date: 02/01/19
Overall Planned Progress: 53%
Overall Actual progress: 52%
Forecast progress: 55%

1. WORK PROGRESS FOR LOT 1

PLANNED ACTUAL FORCAST


ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)

(LOT 1)

SUPERSTRUCTURE
WORKS

1.0 Ground floor works

i)First fix 75 95 100

ii)Plastering works 100 100

iii) Painting works 50 60

iv)Fixing of doors and


window frames 50 70

v)Tiling works 50 60

2.0 First floor works

i)First fix 95 95 100

ii)Tiling works 50 70

iii)Doors and windows


installation 50 70

1
iv) Painting works 50 70

3.0 Second floor works

i)First fix 85 90 100

ii)Painting works 50 60

iii) Tiling works 50 70

iii)Roofing works 80 85 100

iv)Doors and windows


installation 50 70

Planned Progress for


Lot 1: 53%
Actual Progress for
Lot 1: 52%
Forcast Progress for
Lot 1 55%

2
2. WORK PROGRESS FOR LOT 2

PLANNED ACTUAL FORCAST


ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)
(LOT 2)

SUPERSTRUCTURE
WORKS

1.0 Ground floor works

i) Blockworks 95 100

ii) First fix 80 90 100

iii) Plastering 70 70 100

2.0 First floor works

i)Blockworks 95 100

ii) First fix works 90 95 100

iii)Plastering works 70 80 100

3.0 Second floor works

i) First fix works 50 85 100

ii)Plastering works 60 70 80

iii)Roofing works 50 70 80

Planned Progress
for Lot 2: 52 %
Actual Progress
for Lot 2: 50%
Forcast Progress
for Lot 2: 52%

3
3. Site Labour Force

Ghanaian Staff
1.Foremen 5
2.Masons 4
3.Carpenters 6
4.Steel benders 3
5.Plumbers 5
6.Security 2
7.Labourers 15
8.Driver/cook 2
Total 42

4. Material s on Site

S/N Item Unit Q’ty


1 Fine Aggregate m³ 25

2 Coarse Aggregate m³ 20

3 Cement bags bags 150

4 Timber(2x6) pcs 400

5 Timber(2x3) pcs 250

6 6” blocks pcs -

9 2.5 Nails boxes 1

10 3” Nails boxes 2

11 6” Nails boxes -

12 Binding wire rolls -

13 Plywood pcs -

14 12mm reinforcement bars kg 200

4
5. Health and Safety.
The site experienced no injury related issue.
6. The Weather
The site experienced rains on 06-08th November,2018.
7. Progress Photos

L OT 1 & 2

Coring for AC indoor units Plastering works at Lot 2


Fig 1 Fig 2

Ongoing roofing works Plastering works at Lot 2


Fig 3 Fig 4

5
Endorsed by: George Dabi

……………………………
Clerk of works (GIMPA)

Endorsed by: Mr. Mao

………………………………………......
Site Manager (China State)

Prepared by: Emmanuel Siaw

………………………………………......