GHANA INSTITUTE OF MANAGEMENT
AND PUBLIC ADMINISTRATION(GIMPA).
CONSTRUCTION OF 2 NO. 3 STOREY LECTURE
HALL BLOCKS AT GIMPA CAMPUS LOT 1 & 2 –
Accra
Monthly Progress Report
AS AT NOVEMBER 8th,2018
Employer: GIMPA, Accra-Ghana
Consultant: ALBERT ESSAMUAH ASSOCIATES LIMITED.
Contractor: China State Hualong Construction (GH) Ltd.
MONTHLY PROGRESS REPORT AS AT NOVEMBER 8th ,2018
Client: Ghana Institute of Management and Public
Administration, (GIMPA), Accra – Ghana
Commencement date: 24/11/17
Expected completion
date: 02/01/19
Overall Planned Progress: 53%
Overall Actual progress: 52%
Forecast progress: 55%
1. WORK PROGRESS FOR LOT 1
PLANNED ACTUAL FORCAST
ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)
(LOT 1)
SUPERSTRUCTURE
WORKS
1.0 Ground floor works
i)First fix 75 95 100
ii)Plastering works 100 100
iii) Painting works 50 60
iv)Fixing of doors and
window frames 50 70
v)Tiling works 50 60
2.0 First floor works
i)First fix 95 95 100
ii)Tiling works 50 70
iii)Doors and windows
installation 50 70
1
iv) Painting works 50 70
3.0 Second floor works
i)First fix 85 90 100
ii)Painting works 50 60
iii) Tiling works 50 70
iii)Roofing works 80 85 100
iv)Doors and windows
installation 50 70
Planned Progress for
Lot 1: 53%
Actual Progress for
Lot 1: 52%
Forcast Progress for
Lot 1 55%
2
2. WORK PROGRESS FOR LOT 2
PLANNED ACTUAL FORCAST
ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)
(LOT 2)
SUPERSTRUCTURE
WORKS
1.0 Ground floor works
i) Blockworks 95 100
ii) First fix 80 90 100
iii) Plastering 70 70 100
2.0 First floor works
i)Blockworks 95 100
ii) First fix works 90 95 100
iii)Plastering works 70 80 100
3.0 Second floor works
i) First fix works 50 85 100
ii)Plastering works 60 70 80
iii)Roofing works 50 70 80
Planned Progress
for Lot 2: 52 %
Actual Progress
for Lot 2: 50%
Forcast Progress
for Lot 2: 52%
3
3. Site Labour Force
Ghanaian Staff
1.Foremen 5
2.Masons 4
3.Carpenters 6
4.Steel benders 3
5.Plumbers 5
6.Security 2
7.Labourers 15
8.Driver/cook 2
Total 42
4. Material s on Site
S/N Item Unit Q’ty
1 Fine Aggregate m³ 25
2 Coarse Aggregate m³ 20
3 Cement bags bags 150
4 Timber(2x6) pcs 400
5 Timber(2x3) pcs 250
6 6” blocks pcs -
9 2.5 Nails boxes 1
10 3” Nails boxes 2
11 6” Nails boxes -
12 Binding wire rolls -
13 Plywood pcs -
14 12mm reinforcement bars kg 200
4
5. Health and Safety.
The site experienced no injury related issue.
6. The Weather
The site experienced rains on 06-08th November,2018.
7. Progress Photos
L OT 1 & 2
Coring for AC indoor units Plastering works at Lot 2
Fig 1 Fig 2
Ongoing roofing works Plastering works at Lot 2
Fig 3 Fig 4
5
Endorsed by: George Dabi
……………………………
Clerk of works (GIMPA)
Endorsed by: Mr. Mao
………………………………………......
Site Manager (China State)
Prepared by: Emmanuel Siaw
………………………………………......
Works Engineer (China State)