Cost Parameter by RC
Cost Parameter by RC
Name of Project:
Package B:
Location :
COST PARAMETERS
18 Painting Neutralizer
Neutralize Laborer 60.00 sq.m./day 280.00 4.67 Putty
Primer Painter 45.00 sq.m./day 380.00 8.44 Primer
Putty Laborer 45.00 sq.m./day 280.00 6.22 Ist Coat
Sanding Laborer 45.00 sq.m./day 280.00 6.22 2nd Coat
Ist Coat Painter 45.00 sq.m./day 380.00 8.44 Sanding
F coat Painter 45.00 sq.m./day 380.00 8.44
42.44
19 Grooving Mason 6.00 l.m./day 380.00 63.33 Cement
Works Sanding
Asbestos Cement
59 board Carpenter 13.33 sq.m./day 380.00 34.10
Labor 50.00 sq.m./day 280.00
Demolition (Adobe
62 Wall) Labor 0.50 cu.m./day 280.00 560.00
ARCHITECTURAL SPECIALTIES
SC Plywood Flush
2 Type Carpenter 2.60 sq.m./day 550.00 403.85
Labor 500.00
Cyclone wire
6 Sliding door Carpenter 1.04 sq.m./day 550.00 1,009.62
Labor 500.00
Windows :
Fixed glass on
1 steel frame Carpenter 2.60 sq.m./day 550.00 403.85
Labor 500.00
Fixed asbestos
3 louver Carpenter 1.74 sq.m./day 550.00 604.84
Labor 500.00
Cyclone Wire 6a #
4 10 Partition Carpenter 31.51 sq.m./day 550.00 33.32
Labor 500.00
grade member :
suspended member :
Non-Metal
2 Roofings Carpenter 7.44 sq.m./day 380.00 51.08
Labor 280.00
FORMWORKS
Continous Wall
1 Type (CHB) Carpenter 11.43 sq.m./day 380.00 47.25
Labor 20.00 sq.m./day 280.00
Foundation on Pile
2 Caps Carpenter 5.33 sq.m./day 380.00 94.00
Labor 12.31 sq.m./day 280.00
Grade beam or
3 FTB Carpenter 10.67 sq.m./day 380.00 49.63
Labor 20.00 sq.m./day 280.00
Walls Ground to 8'
4 high Carpenter 7.27 sq.m./day 380.00 77.45
Labor 11.11 sq.m./day 280.00
Elevated Slabs
9 (Word Shores) Carpenter 6.96 sq.m./day 380.00 95.23
Labor 6.90 sq.m./day 280.00
Elevated Slabs
10 (Adjusted Shores) Carpenter 11.43 sq.m./day 380.00 64.75
Labor 8.89 sq.m./day 280.00
DEMOLITION
With
Pneumati
1 By hand w/ sledge Laborer 2.47 sq.m./day 280.00 113.40 c Breaker
ELEVATED SLABS
With
Pneumati
1 By hand w/ sledge Laborer 0.49 cu.m./day 280.00 568.40 c Breaker
CONCRETE WALLS
With
Pneumati
1 By hand w/ sledge Laborer 0.56 cu.m./day 280.00 504.35 c Breaker
With
Pneumati
1 By hand w/ sledge Laborer 0.44 cu.m./day 280.00 641.90 c Breaker
Common
Excavation
1 (Manual) Laborer 1.33 cu.m./day 280.00 210.00
Common
Excavation
2 (Machine) Spotter 16.00 cu.m./day 280.00 17.50
Hook Excavation
(Manual &
3 Machine) Labor 1.00 cu.m./day 280.00 280.00
Structural Backfill
4 (Manual) Labor 1.60 cu.m./day 280.00 175.00
Structural Backfill
5 (Backfill) Labor 4.00 cu.m./day 280.00 70.00
Trenching by
8 Machine Labor 40.00 cu.m./day 280.00 7.00
RC PIPES INSTALLATION
571.41 Php/cu.m.
Ex-ohp
oader & Tamped "
192.00 cu.m./day 12,857.60 66.97 260.04 Php/cu.m.
19.05 cu.m./day 380.00 19.95
250
Accessories
1,141.00
41.00 bd ft/day 33.00 1,353.00 2,253.00 Php/Set "
2x35x7/12
1.00 set 350.00 350.00
1,703.00
50.00 sq.m./gal 180.00 3.60 106.48 Php/sq.m. "
45.00 sq.m./gal 110.00 2.44
40.00 sq.m./gal 650.00 16.25
35.00 sq.m./gal 650.00 18.57
30.00 sq.m./gal 650.00 21.67
30.00 sq.m./sq ft 45.00 1.50
64.03
0.10 bags 200.00 20.00 105.83 Php/l.m. "
0.05 cu.m. 450.00 22.50
42.50
4.00 sq.m./can 120.00 30.00 185.00 Php/sq.m. "
0.50 bags 200.00 100.00
130.00
- - Php/cu.m. "
-
-
- - Php/cu.m. "
-
-
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
2,400.00 sq.m./day 314,875.90 258.10
2.00 trips 12,000.00 141.20
(Mob & Demob)
67.39 sq.m./day
5.38 cu.m./day
11.65 cu.m./day
22.22 lm/day
1.01 cu.m./day
CANVASS SHEET
Name of Project:
Package B:
Location :
COST PARAMETERS
18 Painting Neutralizer
Neutralize Laborer 60.00 sq.m./day 280.00 4.67 Putty
Primer Painter 45.00 sq.m./day 380.00 8.44 Primer
Putty Laborer 45.00 sq.m./day 280.00 6.22 Ist Coat
Sanding Laborer 45.00 sq.m./day 280.00 6.22 2nd Coat
Ist Coat Painter 45.00 sq.m./day 380.00 8.44 Sanding
F coat Painter 45.00 sq.m./day 380.00 8.44
42.44
19 Grooving Mason 6.00 l.m./day 380.00 63.33 Cement
Works Sanding
Fixed Glass on
35 Steel Frame Carpenter 2.60 sq.m./day 550.00 211.54
Labor
Plywood
36 Partitions Carpenter 24.40 sq.m./day 550.00 22.54
Labor
1/4" thk
37 plywood Labor 46.78 sq.m./day 550.00 11.76
Carpenter
Aluminum
42 Sliding Window Carpenter 1.94 sq.m./day 550.00 369.50
Labor 5.80 sq.m./day 500.00
Jalousie
Windows on
Aluminum
43 Frame Carpenter 4.62 sq.m./day 550.00 154.56
Labor 14.04 sq.m./day 500.00
Hollow Metal
Door Single
44 Swing Carpenter 0.63 sq.m./day 380.00 766.63
Labor 1.67 sq.m./day 280.00
Fixed Glass on
45 Wood Frame Carpenter 4.62 sq.m./day 380.00 102.13
Labor 14.04 sq.m./day 280.00
Hollow Metal
Door Double
46 Swing Carpenter 0.63 sq.m./day 380.00 766.63
Labor 1.67 sq.m./day 280.00
Steel Sliding
47 Doors Carpenter 0.85 sq.m./day 380.00 559.13
Labor 2.54 sq.m./day 280.00
Aluminum Door
48 Single Swing Carpenter 1.27 sq.m./day 380.00 372.75
Labor 3.81 sq.m./day 280.00
Wooden Panel
49 Door Carpenter 0.69 sq.m./day 380.00 687.88
Labor 2.07 sq.m./day 280.00
Wooden Sliding
50 Door Carpenter 0.92 sq.m./day 380.00 516.05
Labor 2.75 sq.m./day 280.00
Acoustic Tile
51 Out Runner Carpenter 1.42 sq.m./day 380.00 332.88
Labor 4.28 sq.m./day 280.00
Acoustic Tile on
Plywood
52 Ceiling Carpenter 0.00 sq.m./day - 47.95
Labor 5.84 sq.m./day 280.00
Wire Mesh
53 Partition Carpenter 1.90 sq.m./day 380.00 248.98
Labor 5.71 sq.m./day 280.00
Colored
54 Cement Mason 5.71 sq.m./day 380.00 115.50
Labor sq.m./day 280.00
Pebble
55 Washout Mason 2.80 sq.m./day 380.00 235.95
Labor sq.m./day 280.00
Asbestos
59 Cement board Carpenter 13.33 sq.m./day 380.00 34.10
Labor 50.00 sq.m./day 280.00
Plywood
60 Panelling Carpenter 13.33 sq.m./day 380.00 34.10
Labor 50.00 sq.m./day 280.00
Demolition
62 (Adobe Wall) Labor 0.50 cu.m./day 280.00 560.00
Cabinets &
63 Doors Carpenter 5.58 sq.m./day 380.00 118.28
Labor 280.00
ARCHITECTURAL SPECIALTIES
SC Plywood
2 Flush Type Carpenter 2.60 sq.m./day 550.00 403.85
Labor 500.00
Cyclone wire
6 Sliding door Carpenter 1.04 sq.m./day 550.00 1,009.62
Labor 500.00
Windows :
Fixed glass on
1 steel frame Carpenter 2.60 sq.m./day 550.00 403.85
Labor 500.00
Fixed G.I.
2 louver Carpenter 1.74 sq.m./day 550.00 604.84
Labor 500.00
Fixed asbestos
3 louver Carpenter 1.74 sq.m./day 550.00 604.84
Labor 500.00
Cyclone Wire
6a # 10
4 Partition Carpenter 31.51 sq.m./day 550.00 33.32
Labor 500.00
grade member :
suspended member :
Non-Metal
2 Roofings Carpenter 7.44 sq.m./day 380.00 51.08
Labor 280.00
Non-Metal
4 Sidings Carpenter 5.59 sq.m./day 380.00 67.95
Labor 280.00
FORMWORKS
Continous Wall
1 Type (CHB) Carpenter 11.43 sq.m./day 380.00 47.25
Labor 20.00 sq.m./day 280.00
Foundation on
2 Pile Caps Carpenter 5.33 sq.m./day 380.00 94.00
Labor 12.31 sq.m./day 280.00
Grade beam or
3 FTB Carpenter 10.67 sq.m./day 380.00 49.63
Labor 20.00 sq.m./day 280.00
Walls Ground
4 to 8' high Carpenter 7.27 sq.m./day 380.00 77.45
Labor 11.11 sq.m./day 280.00
Beams &
8 Girders Carpenter 4.21 sq.m./day 380.00 132.95
Labor 6.56 sq.m./day 280.00
Elevated Slabs
9 (Word Shores) Carpenter 6.96 sq.m./day 380.00 95.23
Labor 6.90 sq.m./day 280.00
Elevated Slabs
(Adjusted
10 Shores) Carpenter 11.43 sq.m./day 380.00 64.75
Labor 8.89 sq.m./day 280.00
DEMOLITION
With
By hand w/ Pneumati
1 sledge Laborer 2.47 sq.m./day 280.00 113.40 c Breaker
ELEVATED SLABS
With
By hand w/ Pneumati
1 sledge Laborer 0.49 cu.m./day 280.00 568.40 c Breaker
CONCRETE WALLS
With
By hand w/ Pneumati
1 sledge Laborer 0.56 cu.m./day 280.00 504.35 c Breaker
With
By hand w/ Pneumati
1 sledge Laborer 5.41 lm/day 280.00 51.80 c Breaker
CUT CONCRETE OPENINGS
With
By hand w/ Pneumati
1 sledge Laborer 0.44 cu.m./day 280.00 641.90 c Breaker
Common
Excavation
1 (Manual) Laborer 1.33 cu.m./day 280.00 210.00
Common
Excavation
2 (Machine) Spotter 16.00 cu.m./day 280.00 17.50
Hook
Excavation
(Manual &
3 Machine) Labor 1.00 cu.m./day 280.00 280.00
Structural
Backfill
4 (Manual) Labor 1.60 cu.m./day 280.00 175.00
Structural
Backfill
5 (Backfill) Labor 4.00 cu.m./day 280.00 70.00
Trenching by
7 Hand Labor 1.33 cu.m./day 280.00 210.00
Trenching by
8 Machine Labor 40.00 cu.m./day 280.00 7.00
RC PIPES INSTALLATION
571.41 Php/cu.m.
Ex-ohp
oader & Tamped "
192.00 cu.m./day ### 66.97 260.04 Php/cu.m.
19.05 cu.m./day 380.00 19.95
250
Accessories
1,141.00
41.00 bd ft/day 33.00 1,353.00 2,253.00 Php/Set "
2x35x7/12
1.00 set 350.00 350.00
1,703.00
50.00 sq.m./gal 180.00 3.60 106.48 Php/sq.m. "
45.00 sq.m./gal 110.00 2.44
40.00 sq.m./gal 650.00 16.25
35.00 sq.m./gal 650.00 18.57
30.00 sq.m./gal 650.00 21.67
30.00 sq.m./sq ft 45.00 1.50
64.03
0.10 bags 200.00 20.00 105.83 Php/l.m. "
0.05 cu.m. 450.00 22.50
42.50
4.00 sq.m./can 120.00 30.00 185.00 Php/sq.m. "
0.50 bags 200.00 100.00
130.00
- - Php/cu.m. "
-
-
- - Php/cu.m. "
-
-
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
0 0 Php/cu.m. "
2,400.00 sq.m./day ### 258.10
2.00 trips ### 141.20
(Mob & Demob)
67.39 sq.m./day
5.38 cu.m./day
11.65 cu.m./day
22.22 lm/day
1.01 cu.m./day
MASON@520PHP LABOR@481
520 481 CEMENT(class"B") SAND ALLOWANCE
52 48.1 49.2 24 18.75
MASON@520PHP LABOR@481 CHB@25
520 481 25 CEMENT(class "D" SAND ALLOWANCE
104 96.2 312.5 129.765 101.25 18.75
TOTAL VAT AND PROFIT TOTAL UNIT COST
202.05 35 237.05