Petrochemical Plants have their own: - design standards - Terminology - Practices and - Constraints. Raw material storage tanks, hoppers, piles, etc. Product storage tanks, warehouses, baggers, etc. Waste Storage (DOE, EPA, USGS) sales - Everyone Else is Temporary Process Plant Client Funds the engineering and construction of the plant Generally supplies or approves the processes to be used Accepts the work performed

Uploaded by

Chooi Jia Hoong
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
399 views8 pages

01a-Introduction To Process Plant Design

Petrochemical Plants have their own: - design standards - Terminology - Practices and - Constraints. Raw material storage tanks, hoppers, piles, etc. Product storage tanks, warehouses, baggers, etc. Waste Storage (DOE, EPA, USGS) sales - Everyone Else is Temporary Process Plant Client Funds the engineering and construction of the plant Generally supplies or approves the processes to be used Accepts the work performed

Uploaded by

Chooi Jia Hoong
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Introduction to Process Plants

Process Plant • Characterized by Chemical Processes


– Different from power (including nuclear), propulsion,
Design etc.
– Hazards from both energy and substance release
– Substances and their temperature and pressure, etc.,
usually drives the selection of piping materials and
design ratings
• Petrochemical Plants have their own:
– Design standards
– Terminology
– Practices and
Copyright ©, 2009
William G. Beazley, PhD – Constraints
Photo: Air Products All Rights Reserved

Basic Components of a Raw Material Storage


Typical Chemical Process
(R. K. SINNOTT)
• Tanks, Hoppers, Piles, etc.

Tanks, Pumps,
Compressors, Reactors, Drums, Reflux, Tanks,
Warehouses, Furnaces, Towers, Strippers, Warehouses,
Hoppers, Exchangers,
Heaters, etc. Filters, Treaters, Baggers,
Piles, etc. Dryers, etc. etc. etc.
Crushers,
Mixers, etc.

Feed Preparation Reaction


(US Navy, Nasa, Transportation, (US Army, DOE, )
• Pumps, Compressors, Exchangers, Heaters, • Reactors, Furnaces, etc.
Crushers, Mixers, etc.

http://www.ih.navy.mil/Departments/ord/che-ext-tec-div/index.asp
http://www.tfhrc.gov///pubrds/05jan/02.htm
http://www.netl.doe.gov/technologies/coalpower/cctc/summaries/tampa/tampaedemo.html
http://www.npt.nuwc.navy.mil/facilities/QuietWater/default.htm http://www.pmcd.apgea.army.mil/multimediaviewer.aspx?id=585

1
Product Separation Product Purification
(US DOE) (US OSHA, DOT)
• Drums, Towers,
• Reflux, Strippers,
Filters, Dryers, etc.
Treaters, Sorters, etc.

http://www.nrel.gov/data/pix/searchpix.cgi?
http://www.greensboro-nc.gov/departments/Water/watersystem/treatment.htm http://iforms.osha-slc.gov/dts/osta/otm/otm_iv/otm_iv_2.html

Product Storage Waste Storage


(DOE, EPA, USGS)
• Tanks, Warehouses,
• Baggers,
• etc.

http://pubs.usgs.gov/gip/gw_ruralhomeowner/gw_ruralhomeowner_new.html
http://www.fedcenter.gov/_storage/Photos/176.jpg

http://www.tobyhanna.army.mil/about/certifications/environmental/rcra%20cleanup.htm

The Manufacture of Cement by the


Sales Portland Process
(US CDC)

Limestone,
Clay, etc.

http://www.msc.navy.mil/sealift/2005/September/katrina.htm http://www.cdc.gov/elcosh/docs/d0200/d000279/ilochap93.html

2
Parties to Plant Process Plant Client
Design • Funds the engineering and construction of the plant
(The 'PIPING GUIDE') • Generally supplies or approves the processes to be used
• Client wants a finished • Accepts the work performed
plant
– Business Case Primary
Concern
– Everyone Else is
Temporary
• Design Engineers
produce highly quality
assured product
definition data
• Construction Realizes
Design
Source:
The 'PIPING GUIDE'
http://www.pipingguide.com

The Project Engineer The Project Engineer

• Reviews the Design


• Formal point of contact with the client Basis of Plant
– Voice of the client inside the engineering organization • Enforces Client
– Usually “seals” design as professional engineer Requirements
•http://www.nps.gov/hfc/products/imi/imi-ser-class.htm
Responsible for completeness and correctness of work http://www.osha.gov/dcsp/partnerships/regional/region2/453_signing.html

The Project Engineer


Procured Materials and Services
• Items that has been obtained from vendor or
supplier
• Assistance or advice provided by a vendor
or supplier
• Obtained through a procurement process
• Result in a list of vendors and
subcontractors
• Plans and Schedules
Work
http://www.osha.gov/dcsp/partnerships/regional/region2/459_signing.html

3
Project Organization Project
Design
Groups and
Information
Flow
(Source: The
'PIPING GUIDE')

Source: The 'PIPING GUIDE'


http://www.pipingguide.com
http://www.pipingguide.com

Design Organizational Roles Design supervisor/Group leader


Project • Manages the documentation of in process
Data and approved engineering data
• Contacts the Project Engineer for any
Design approvals required
Checker
Supervisor
• Assigns work to designers at the appropriate
Designer time
Designer • Assures all data needed for work is
Designer available to designers
Designer

The Piping Designer Engineering Design Specifications


• Established basis for final plant design
• Responsible for correctness of his • Includes:
work – start-up procedures,
• Inform supervisor if questions arise – initial site selection information,
– general pre-commissioning guidelines,
• Recognize need for data required to – equipment testing procedures and acceptance
complete work methods
• Never contact the client directly – final process topology,
– material and energy balance information

4
Functional Equipment Characteristics Vendor-Proprietary Equipment
• Describe or specify: • Equipment whose performance is
guaranteed by the vendor.
–Functional requirements for the
equipment • Specified by equipment datasheet in
process design specifications
–Service provided to the process by
package.
the equipment
• Usually designed by first selecting a
–What equipment is supposed to do
vendor who performs testing and
sizing of the item

Supplier/Vendor Relationship Documentation


• Request the required information only
• All project management, design,
• Disclosing only necessary information to contractual, regulatory, and disposal
get the right data documents produced during the life
• Avoid: cycle of a process plant.
– Disclosing competition • Has versions and releases that must
– Telling vendor he’ll get the order be managed.
– Gratuities and never demand them (lunch) • Includes all documentation retained
– Ordering to get information then cancel past the end of the plant life cycle

Operations Documents Handover


• Covers all the many different phases and
• Transfer of responsibility for the plant
aspects of plant operation
– Construction team to commissioning team
• Documentation necessary to run the
– Commissioning team to operating team
plant safely:
• Involves transfer of all supporting
– Procedure to start up and shut down the
plant documentation
– Parameters and settings for process
equipment and controls

5
Activity Model of the Oil and Gas Common Status Terms
Production Facility Life-cycle
(ISO 15926) • As-built: Process plant's actual physical
and functional aspects at a specific point
Produce Conceptual
Process Design
Produce Detailed
Process Design
Commission
Plant
Operate Plant
Decommission
Plant
in time
As-approved: Product data provide to
Produce Conceptual
Produce Detailed Construct Plant Maintain Plant Demolish Plant
and approved by client
Engineering Design
(Front End)
Engineering Design Pre-Commission and Equipment and Restore Site
As-specified: Approved data provide to
engineer by client
Suppliers and
Fabricators
Procure and Control Equipment, Material and Services
As-released: Product data officially
provided to anyone
http://www.tc184-sc4.org/About_TC184-SC4/About_SC4_Standards/

Construction Release Finalized Construction Documents


• All documentation related to the erection,
• All data needed to realize the plant commissioning and operation
– Build, • Includes:
– Commission, – As-built reports,
– Train to operate, maintain – Equipment certification,
– Nameplate information of installed equipment,
• Approved for release by engineering for
– Operating manuals,
construction – Testing procedures,
• Stamped by a registered professional – Field changes, and
engineer – Photos of as-built units, modules and plant

Plant Commissioning Maintenance


• Required before
client handover
• Proven operational
through specific
procedures
– Confirm Staff
Skills
– Verify product
data
– Test equipment
• Equipment
Commissioning
Procedures - Step-
by-step explanation
of start-up actions
required to
commission
equipment in the
http://www.usaid.gov/iraq/photogallery/gallery_8/capconstr1_06.html plant http://flickr.com/photos/coolnewspics/244371213/in/dateposted/

6
Maintenance Shutdown/Decommissioning
• Shutting down the
plant
• Preserving it for
later
commissioning or
demolition
• May not include
site remediation
http://splash.metrokc.gov/wtd/southplant/index.htm

http://www1.usaid.gov/iraq/photogallery/gallery_39/photo18.html http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html
http://www.srs.gov/general/busiops/tech-transfer/plant.htm http://www.lm.doe.gov/land/sites/oh/fernald_orig/VImages/PhotoTour/1998/Dec98/Plt6c.htm
http://www.eere.energy.gov/industry/bestpractices/energymatters/full_issue.cfm/volume=37 http://www-als.lbl.gov/als/als_news/news_archive/vol.240_042804.html

Project Schedule
• Duration
• Start Date
• Critical Path Questions
– Sequence of Tasks
such that if any is late
the project is late.
– Can be more than one

http://www.coconino.az.gov/cji.aspx?id=383

PISTEP Process Plant Engineering Processes


Production Output
• Materials or energy to be sold or
traded
• Result of processing raw material(s)
(Production Input)
• Produced according to a scheduled
delivery time, grade, and quantity of
product to be produced
Source: EPISTLE Process Industries Data Handover Guide - Part 1
http://www.uspi.nl/projects/Joint_Projects/fr_joint_projects.html

7
Course Outline
• Part 1 Pipe Lifecycle
• Part 2 Pipe Fluid Flow & Control
• Part 3 Plant Equipment
• Part 4 Pipe Structural Design
• Part 5 Project Practices & Management
• Part 6 Project