Abstract
S no Particular Unit Qty Indian Amount
Rate
A Concrete
1 pile Cum 139.887 25000 3497175
2 pile cap Cum 68.75 14000 962500
3 pier Cum 233.145 14000 3264030
4 pier cap Cum 132 14000 1848000
5 trapeziodal section Cum 63.25 14000 885500
6 support beam Cum 39.6 14000 554400
7 slab Cum 200 14000 2800000
Total 13811605
B Steel MT 140.26112 60000 8415667.2
C For Liner, 6668181.66
shuttering , all
equipments and
tools and tackles
etc
Total 28895453.86
Area of Bridge Sqm 80 10 800
Rate / 36119.31733
Sqm
Note It does not include preparing access to the project site ,
installation of crane , barge etc
It does not include labour camp construction
It does not include electrical costs , DG set cost
Measurement Sheet
S NO ITEM UNIT NOS LENGTH BREADTH HEIGHT
A Concrete
1 PILE Cum 44 0.63585 5
2 PILE CAP Cum 11 2.5 2.5 1
3 PIER Cum 11 1.76625 12
4 PIER CAP Cum 33 2 2 1
5 TRAPEZOIDAL Cum 11 10 1.5 1
SECTION
6 SUPPORT BEAM Cum 33 8 0.3 0.5
7 SLAB Cum 10 8 10 0.25
Total
B Steel KG
MT
C Shuttering
Pier Sqm 11 104
Quantity Considerations
139.887 pile dia 0.9
68.75 pier dia 1.5
233.145
132
63.25
39.6
200
876.632
140261.12
140.26112
1144