100% found this document useful (1 vote)
542 views1 page

Plumbing Inspection Checklist Guide

The plumbing inspection checklist summarizes the results of a plumbing inspection for a 300-room hotel project in 3 sentences or less. The inspection covered 38 items related to drainage, venting, sizing, supports, and protection of piping. The majority of items passed inspection, while some were disapproved or not applicable. The inspector noted that alternate materials must meet required testing standards according to the plumbing code.

Uploaded by

Abhijeet Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
542 views1 page

Plumbing Inspection Checklist Guide

The plumbing inspection checklist summarizes the results of a plumbing inspection for a 300-room hotel project in 3 sentences or less. The inspection covered 38 items related to drainage, venting, sizing, supports, and protection of piping. The majority of items passed inspection, while some were disapproved or not applicable. The inspector noted that alternate materials must meet required testing standards according to the plumbing code.

Uploaded by

Abhijeet Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Plumbing Inspection Checklist

Plumbing Inspection Checklist RESULT OF INSPECTION

Pass
Fail
Partial Pass

Project : 300 Rooms Hotel (Leela) - GARUD

Date:

INSPECTION ITEMS A D N/A INSPECTION ITEMS A D N/A

1. Make sure that all piping is properly supported 1. Check the listing of manufacture’s approvals –
and strapped – 308.1 303.1

2. Check the materials and workmanship – 1102.6 20. Check for approval agency - 303.4.1

21. Require all concealed work to be left exposed


3. Check heights of vents above fixture rims – 905.4 until after the inspection – 405.8
4. Follow vents to the roof, checking for size and
22. Access to concealed equipment - 405.8, 422.5
length limits – 905.1
5. Building traps shall be provided with a clean out 23. Water heaters shall be located and connected so
and a relief vent or fresh air intake on the inlet as to provide access for observation,
side of the trap -1002.6 maintenance, servicing and replacement – 501.4
6. Relief vent or fresh air intake shall be carried 24. An inspection opening shall be provided over
above grade & terminated in a screened outlet either the inlet or outlet baffle of every treatment
located outside the building – 1002.6 tank – 802.5
7. Drainage and vent water test, filling stack with
25. Check water pressure with a gauge 312.5
water – 312.2

8. Drainage and vent air test – 312.3 26. Verify that piping is properly supported – 308.1

27. Plumbing systems shall not be located in an


9. Gravity sewer test 312.6 elevator shaft or in an elevator equipment room –
301.6
10. Check waste pipe for required size and type – 28. In inspecting layout and size of water piping –
301.5 603.1
11. Add up units to determine size of main drain – 29. Separation of water service and building
1103.1 sewer/drain – 603.2

12. Check that drain pipe is supported – 306.1 30. Location of full-open valves – 606.1

13. Check horizontal pipes for proper grade – 905.2 31. Check for cross-connections – 608.1

14. Verify that all piping in the ground is suitably 32. Determine number of fixture units for each branch
protected - 306.2 line – 710.1
33. Septic tank shall be not less than 50-0 gallons and
15. Make sure that backfill is code complaint - 306.3 the secondary tank shall be not less than 250
gallons – 802.2

16. Check trap sizes and location 504.7.1 34. Drain well shall be a minimum of 50’ deep

35. Septic tank shall have not less than two tanks –
17. Check cleanouts – 708.2-4, 708.4
802.3
18. Inspect system for leaks and workmanship – 36. Tank shall have sanitary tees or baffles to distribute
1102.6 flow – 802.3
19. Where pipe is to be installed by tunneling it is 37. Septic tank manhole cover shall have (2) 24” x 24”
protected – 306.4 access/manhole covers at grade – 802.4

20. Inspect backflow prevention – 312.9 38. Alternate materials and required testing - 105.2-3