PROPOSED LINDE OFFICE INTERIOR FIT- OUT
WEEKLY ACCOMPLISHMENT
REPORT
AS OF AUG 04 -10, 2019, 2019
Reception
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Energized Lighting Fixtures & Supply Duct
4. Lighting Fixtures installation and Supply Grills
Pantry Pantry Booth seat
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation and
Supply Grills
4. Installation of Pantry Cabinet
5. Accent Paint Application
6. Droppings of Electrical Wires
7. Booth Seat Installation including Trellis
Hallway to Reception Area
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation
4. Baseboard Installation
5. Installed Carpet
Hallway to Work Area
Board Room Board Room
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation
4. Baseboard Installation
5. Installed Carpet
6. Fixing of Ceiling Trellis
Meeting Room 2
Board Room
HR Shared IS Sales
Procurement Finance Managers Marketing
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation
4. Energized Electrical Works
5. Fixed and Door Glass Installation
6. Acoustic Ceiling Alignment
7. Carpet Installation
8. Fire Pro. Relocation
9. Acoustic Board Installation @ Work Area
Work Area
President Room Manager’s Room
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation
4. Energized Electrical Works
5. Fixed and Door Glass Installation
6. Acoustic Ceiling Alignment
7. Carpet Installation
8. Fire Pro. Relocation
9. Acoustic Board Installation @ Work Area
Server
President
WorkRoom
Area Work Area
On Going Activities
1. Finishing of Walls & Ceiling
2. Fixed Glass installation
3. Lighting Fixtures installation
4. Energized Electrical Works
5. Fixed and Door Glass Installation
6. Acoustic Ceiling Alignment
7. Carpet Installation
8. Fire Pro. Relocation
9. Acoustic Board Installation @ Work Area
Work Area
Server
ACCOMPLISHMENT MONITORING
Contract WT. Previous Present To-Date
Item No. DESCRIPTION
% Actual % Wt. % Actual % Wt. % Actual % Wt. %
I PRELIMINARIES 5.70% 89.84% 5.12% 6.81% 0.39% 96.65% 5.51%
II WALL FINISHES 16.17% 81.96% 13.25% 6.99% 1.13% 88.95% 14.38%
III FLOOR FINISHES 6.70% 83.30% 5.58% 16.70% 1.12% 100.00% 6.70%
IV CEILING WORKS 3.01% 93.06% 2.80% 6.94% 0.21% 100.00% 3.01%
V DOORS AND HARDWARE/SPECIAL WORKS 8.91% 61.16% 5.45% 19.57% 1.74% 80.73% 7.19%
VI JOINERIES 11.07% 52.61% 5.82% 22.05% 2.44% 74.66% 8.26%
VII PAINTING WORKS 3.46% 89.09% 3.09% 9.67% 0.33% 98.76% 3.42%
VIII PLUMBING WORKS 1.52% 100.00% 1.52% 0.00% 0.00% 100.00% 1.52%
IX ELECTRICAL WORKS 15.27% 89.44% 13.66% 8.35% 1.27% 97.79% 14.93%
XV MECHANICAL WORKS 21.58% 86.57% 18.68% 3.48% 0.75% 90.05% 19.43%
XVII FIRE DETECTION AND ALARM SYSTEM 3.36% 84.88% 2.85% 0.00% 0.00% 84.88% 2.85%
XVIII FIRE PROTECTION WORKS 3.25% 85.97% 2.80% 11.79% 0.38% 97.76% 3.18%
TOTAL 100.00% 80.62% 9.77% 90.39%