Pradeep Report

The inspection report summarizes the major overhaul of two Siemens GG 26/25 turbines at an IFFCO plant in Odisha, India in April 2014. It details the assembly protocol, including checks of bearing clearances, rotor settings, centering readings, rotor float, alignment readings, rotor runouts, steam flow path clearances, final diaphragm gaps, safety systems, spare parts consumed, and spare parts recommended. The overhaul was performed to specifications by Rotodyne Engineering Services and concluded with a summary of the inspection and overhaul work.

Uploaded by

Sameer Kulkarni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views2 pages

Pradeep Report

The inspection report summarizes the major overhaul of two Siemens GG 26/25 turbines at an IFFCO plant in Odisha, India in April 2014. It details the assembly protocol, including checks of bearing clearances, rotor settings, centering readings, rotor float, alignment readings, rotor runouts, steam flow path clearances, final diaphragm gaps, safety systems, spare parts consumed, and spare parts recommended. The overhaul was performed to specifications by Rotodyne Engineering Services and concluded with a summary of the inspection and overhaul work.

Uploaded by

Sameer Kulkarni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

ROTODYNE ENGINEERING SERVICES PVT.

LTD DT: 09-5-2014


INSPECTION REPORT

REPORT
ON
MAJOR OVERHAULING
OF
SIEMENS MAKE TURBINE GG 26/25 - 2 type
M/S. IFFCO , PARADEEP
ODISSA
APRIL 2014

M/S ROTODYNE ENGINEERING SERVICES PVT LTD


Rotodyne House 9 & 10, Annapurna Enclave
[Link] to BSNL Office, Chandanagar, Hyderabad-500 050
PH NO: 040-3032362/66, FAX: 040-3034508
E-MAIL:admin@[Link]
ROTODYNE ENGINEERING SERVICES [Link] DT: 09-5-2014
INSPECTION REPORT
INDEX

Page no.
I. TECHNICAL DATA 1
II. TECHNICAL SPECIFICATIONS 2
III. INTRODUCTION OF OVER HAUL 3
IV. BRIEF HISTORY 6
V. ASSEMBLY PROTOCOL ON MAJOR OVER HAUL 8
TURBINE
1.00 BEARING CLEARANCES 8
2.00 OIL GLAND CLEARANCES 10
3.00 ROTOR SETTING DIMENSIONS 11
4.00 CENTERING READINGS 12
5.00 ROTOR FLOAT AND DISTANCE B/W ROTORS 13
6.00 ALLIGNMENT READINGS 16
7.00 ROTOR RUNOUTS 20
8.00 STEAM FLOW PATH CLEARANCES 21
8.01 AXIAL CLEARANCES 21
8.02 RADIAL CLEARANCES 24
9.00 FINAL THERMAL GAPS OF DIAPHRAGMS 25
10.00 SAFETY SYSTEM 26
11.00 SPARE CONSUMED 34
12.00 SPARES RECOMMENDED 34
VI. SUMMARY REPORT 35