100% found this document useful (1 vote)
6K views5 pages

Productivity Rate Interior Painting PDF

This document outlines the productivity rates for interior painting of residential units. It provides details on the surface preparation, primer application, and coating application steps for both wall and ceiling painting. Productivity rates are calculated based on the area painted and total man-hours spent on units ranging in size from 55 to 111 square meters. The average productivity rate across all units was 0.6288 man-hours per square meter.

Uploaded by

Raphael Arch
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
6K views5 pages

Productivity Rate Interior Painting PDF

This document outlines the productivity rates for interior painting of residential units. It provides details on the surface preparation, primer application, and coating application steps for both wall and ceiling painting. Productivity rates are calculated based on the area painted and total man-hours spent on units ranging in size from 55 to 111 square meters. The average productivity rate across all units was 0.6288 man-hours per square meter.

Uploaded by

Raphael Arch
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROJECT : SM LIGHT RESIDENCES

LOCATION : BONI AVE. EDSA MANDALUYONG CITY

SUBJECT : PRODUCTIVITY RATE


SCOPE OF WORK : INTERIOR PAINTING OF UNITS
FINISH : SEMI-GLOSS (2 COATS)
PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FIRST COAT
- Application of Semi-Gloss
4. FINAL COAT
- Application of Semi-Gloss

PAINTING TO MASONRY WALL

FLOOR : 17TH FLOOR


UNIT NO. : 18
AREA :
2
UNIT 46.9 m
2
CR 8.86 m
2
55.76 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

TOTAL 37.75 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.6770

FLOOR : 17TH FLOOR


UNIT NO. : 19
AREA :
2
UNIT 46.9 m
2
CR 8.86 m
2
55.76 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 3.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

TOTAL 37.75 Man-Hrs


2
PRODUCTIVITY (Man-hr/m ) 0.6770

PAINTING TO MASONRY WALL

FLOOR : 17TH FLOOR


UNIT NO. : 37-38
AREA :
2
UNIT 93.8 m
2
CR 17.72 m
2
111.52 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter Surface Preparation - Putty Works 22 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 8.5 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 3 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 5.5 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
13-Nov Painter Final Coat - Application of Semigloss 12 Man-Hrs

TOTAL 61 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.5470

PAINTING TO MASONRY WALL

FLOOR : 8TH FLOOR


UNIT NO. : 21-22
AREA :
2
UNIT 93.8 m
2
CR 17.72 m
2
111.52 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter Surface Preparation - Putty Works 14 Man-Hrs
8-Nov Painter Surface Preparation - Putty Works 10 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 7.5 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 6 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 13 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
Painter Final Coat - Application of Semigloss 12 Man-Hrs

TOTAL 68.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.6142

AVERAGE PRODUCTIVITY (Man-hr/m2) 0.6288

FINISH : FLAT FINISH


PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FINAL COAT
- Final application of flat latex

PAINTING TO CONCRETE CEILING

FLOOR : 17TH FLOOR


UNIT NO. : 18
AREA :
2
UNIT 12.8 m
2
12.8 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 2 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 0.75 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter Final Coat - Application of flat latex 1.25 Man-Hrs

TOTAL 11.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.8984

FLOOR : 17TH FLOOR


UNIT NO. : 19
AREA :
2
UNIT 12.8 m
2
12.8 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Sanding 2 Man-Hrs
7-Nov Painter 1 Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter 2 Primer - Application of Flat Latex 0.75 Man-Hrs
8-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter 1 Final Coat - Application of flat latex 1.25 Man-Hrs

TOTAL 11.5 Man-Hrs


2
PRODUCTIVITY (Man-hr/m ) 0.8984

FLOOR : 17TH FLOOR


UNIT NO. : 37-38
AREA :
2
UNIT 25.6 m
2
25.6 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter 1 Surface Preparation - Putty Works 5.5 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 6 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

TOTAL 19.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.7617

FLOOR : 8TH FLOOR


UNIT NO. : 21-22
AREA :
2
UNIT 25.6 m
2
25.6 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter 1 Surface Preparation - Putty Works 9 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 4 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

TOTAL 21 Man-Hrs
2
PRODUCTIVITY (Man-hr/m ) 0.8203

AVERAGE PRODUCTIVITY (Man-hr/m2) 0.8447


210 972.625
105 69.47321 0.330825
5 1 43.69
6 2
7 2
8 3
9 4
10 5
11 6

You might also like