Gantt Chart PDF

This document outlines the tasks, durations, and schedule for a project to construct an elevator. It includes 14 days for planning, 35 days for construction, 24 days for installation, and 15 days for commissioning. Key tasks include sketch and design, electrical design, 3D drawing, platform and shaft construction, installation of electrical, mechanical and safety systems, and pilot testing before final review and handover.

Uploaded by

MeliRampersand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
1K views1 page

Gantt Chart PDF

This document outlines the tasks, durations, and schedule for a project to construct an elevator. It includes 14 days for planning, 35 days for construction, 24 days for installation, and 15 days for commissioning. Key tasks include sketch and design, electrical design, 3D drawing, platform and shaft construction, installation of electrical, mechanical and safety systems, and pilot testing before final review and handover.

Uploaded by

MeliRampersand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID WBS Task Task Name Duration Start Finish 29 Sep '19 6 Oct '19 13 Oct '19 20 Oct '19

'19 6 Oct '19 13 Oct '19 20 Oct '19 27 Oct '19 3 Nov '19 10 Nov '19 17 Nov '19 24 Nov '19 1 Dec '19 8 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19 5 Jan '20 12 Jan '20 19 Jan '20 26 Jan '20
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 1 Project Planning 14 days Tue 1/10/19 Fri 18/10/19
2 1.1 Sketch & Design 3 days Tue 1/10/19 Thu 3/10/19
3 1.2 Electrical Design 1 day Fri 4/10/19 Fri 4/10/19
4 1.3 3D Drawing 3 days Mon 7/10/19 Wed 9/10/19
5 1.4 Cost Estimation 4 days Thu 10/10/19 Tue 15/10/19
6 1.5 JKKP Authorization 1 day Fri 18/10/19 Fri 18/10/19
7 2 Construction 35 days Mon 21/10/19Fri 6/12/19
8 2.1 Unnecessary 5 days Mon Fri 25/10/19
Materials & 21/10/19
Components
9 2.2 Platform Construction
4 days Mon 28/10/19Thu 31/10/19
10 2.3 Shaft's Supporting 7 days Fri 1/11/19 Mon 11/11/19
wall construction

11 2.4 Building conduits 4 days Tue 12/11/19 Fri 15/11/19


12 2.5 landing door 9 days Mon Thu 28/11/19
construction 18/11/19

13 2.6 Lift Machine room 3 days Fri 29/11/19 Tue 3/12/19


14 2.7 Lift Interior (wall 3 days Wed 4/12/19 Fri 6/12/19
panels, ceiling &
flooring)
15 3 Installation 24 days Mon 9/12/19 Thu 9/1/20
16 3.1 Electrical 9 days Mon 9/12/19 Thu 19/12/19
17 3.1.1 Wiring 3 days Mon 9/12/19 Wed 11/12/19
18 3.1.2 Ventilation 2 days Thu 12/12/19 Fri 13/12/19
19 3.1.3 Lift control System
2 days Mon 16/12/19Tue 17/12/19
20 3.1.4 Trunking installation
1 day Wed 18/12/19Wed 18/12/19
21 3.1.5 lighting and speakers
1 day Thu 19/12/19 Thu 19/12/19
22 3.2 Mechnical 9 days Fri 20/12/19 Wed 1/1/20
23 3.2.1 Buffer Spring 2 days Fri 20/12/19 Mon 23/12/19
24 3.2.2 Control Box 2 days Tue 24/12/19 Wed 25/12/19
25 3.2.3 Roof pulley system
2 days Thu 26/12/19 Fri 27/12/19
26 3.2.4 Traction system 2 days Mon Tue 31/12/19
& Counter 30/12/19
weight
27 3.2.5 lift door controllers
1 day Wed 1/1/20 Wed 1/1/20
28 3.3 Safety and security6 days Thu 2/1/20 Thu 9/1/20
29 3.3.1 Emergency alarm1 day Thu 2/1/20 Thu 2/1/20
30 3.3.2 CCTV 1 day Fri 3/1/20 Fri 3/1/20
31 3.3.3 Fire extinguishers1 day Mon 6/1/20 Mon 6/1/20
32 3.3.4 Intercom 1 day Tue 7/1/20 Tue 7/1/20
33 3.3.5 Weight 2 days Wed 8/1/20 Thu 9/1/20
measuring
system
34 4 Commisioning 15 days Fri 10/1/20 Thu 30/1/20
35 4.1 Pilot testing 13 days Fri 10/1/20 Tue 28/1/20
36 4.1.1 Site clean up 3 days Fri 10/1/20 Tue 14/1/20
37 4.1.2 Testing 3 days Wed 15/1/20 Fri 17/1/20
38 4.1.3 Feedback 2 days Mon 20/1/20 Tue 21/1/20
39 4.1.4 Pilot Run 5 days Wed 22/1/20 Tue 28/1/20
40 4.2 Review 2 days Wed 29/1/20 Thu 30/1/20
41 4.2.1 Close meeting 1 day Wed 29/1/20 Wed 29/1/20
42 4.2.2 Project handover1 day Thu 30/1/20 Thu 30/1/20

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: EPM gantt chart
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 27/11/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress