ID Task Task Name Duration Start Finish Predecessors Resource NamesJul 5,Cost
'20 Jul 12, '20
Mode S S
1 Problem definition 1 day Mon 7/13/20 Mon 7/13/20 Samra Jamshora ,Stationary[1 tons]
$100.00 Sam
2 Collect requirements 2 days Tue 7/14/20 Wed 7/15/20 1 Madan $200.00
Shah,Samra
3 Analyze requirements 2 days Thu 7/16/20 Fri 7/17/20 2 Jamshora
saurav ,Sunit $200.00
Khadhgi,Analyzing
4 Planning 2 days Mon 7/20/20 Tue 7/21/20 2,3 tools[1]
bijay ,dabindra,Food,Stationary[1
$300.00
tons]
5 Business Case 5 days Mon 7/20/20 Fri 7/24/20 3 saurav $100.00
6 Cost and Effort 2 days Mon 7/27/20 Tue 7/28/20 3,5 dabindra,Madan $200.00
Estimation Shah,Sunit
7 Create Module 1 1 day Wed 7/22/20 Wed 7/22/20 4 Khadhgi
Design $300.00
design tools[1],Food,Stationary[1
8 Create Module 2 1 day Wed 7/22/20 Wed 7/22/20 4 tons]
Design $350.00
design tools[1],Food,Stationary[1
9 Create Module 3 1 day Wed 7/22/20 Wed 7/22/20 4 tons]
Design $400.00
design tools[1],Food,Stationary[1
10 Code module 1 2 days Thu 7/23/20 Fri 7/24/20 4,7 tons]
coding team1 $500.00
11 Code module 2 2 days Thu 7/23/20 Fri 7/24/20 4,8 coding team2 $500.00
12 Code module 3 2 days Thu 7/23/20 Fri 7/24/20 4,9 coding team 3 $500.00
13 Module’s integration 3 days Mon 7/27/20 Wed 7/29/20 10,11,12 Food,Integeration $600.00
team
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: [Link] final project
Summary Manual Summary Rollup Progress
Date: Mon 7/13/20
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource NamesJul 5,Cost
'20 Jul 12, '20
Mode S S
14 System testing 3 days Thu 7/30/20 Mon 8/3/20 13 Testing team $400.00
15 Acceptance testing 2 days Tue 8/4/20 Wed 8/5/20 13,14 Acceptance team $300.00
16 Design FAQs 1 day Thu 8/6/20 Thu 8/6/20 15 Customer interaction team $200.00
17 System Deployment 2 days Fri 8/7/20 Mon 8/10/20 14,15,16 Hardware[1] $3,000.00
18 Closing Project 2 days Tue 8/11/20 Wed 8/12/20 17 handoveer project[1] $600.00
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: [Link] final project
Summary Manual Summary Rollup Progress
Date: Mon 7/13/20
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Samra Jamshora ,Stationary[1 tons]
7/15
saurav ,Sunit Khadhgi,Analyzing tools[1]
bijay ,dabindra,Food,Stationary[1 tons]
saurav
dabindra,Madan Shah,Sunit Khadhgi
Design tools[1],Food,Stationary[1 tons]
Design tools[1],Food,Stationary[1 tons]
7/22
coding team1
coding team2
7/24
Food,Integeration team
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: [Link] final project
Summary Manual Summary Rollup Progress
Date: Mon 7/13/20
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3
Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Testing team
Acceptance team
Customer interaction team
8/10
handoveer project[1]
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: [Link] final project
Summary Manual Summary Rollup Progress
Date: Mon 7/13/20
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 4