CO2 System Inspection Checklist

The document outlines an inspection and test chart for a newly installed high pressure CO2 system in a scrub room on the Odin Star rig. It lists 12 check points to test the system components, including manifold and downstream piping leak tests, actuator operations from two control stations, alarm and ventilation tests. Upon completing all checks, the system was deemed in operative condition.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views3 pages

CO2 System Inspection Checklist

The document outlines an inspection and test chart for a newly installed high pressure CO2 system in a scrub room on the Odin Star rig. It lists 12 check points to test the system components, including manifold and downstream piping leak tests, actuator operations from two control stations, alarm and ventilation tests. Upon completing all checks, the system was deemed in operative condition.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

INSEPCTION & TEST CHART FOR SCR ROOM

HIGH PRESSURE CO2 SYSTEM NEW INSTALLATION

RIG : ODIN STAR CLASS : A.B.S.


OWNER : NABORS DRILLING FLAG :
PANAMA
PROTECTED AREA: SCR ROOM HULL : B-178

PERFORMANCE
CHECK POINT CARRIED NOT
OUT APPLICABLE
01) Complete installation as per the
approved drawing
02) Manifold leak test, at 7 Bar with
main valve closed for 02 minutes
03) Down stream pipe leak test at 7 Bar
with nozzle ends blanked (for 02
Minutes)
04) Time delay and cylinder actuator
operation test (operating 04 Nos.
actuators after 30 seconds) from
Control Station I
05) Pilot discharge line leak test at 7 bar
for 2 minutes from Control Station I
06) Distribution Main Valve function test
(Main Valve for SCR Room) from
Control Station I
07) Function test for audible & visual
alarms, ventilation shutdown test from
Control Station I
08) Time delay and cylinder actuator
operation test (operating 04 Nos.
actuators after 30 seconds) from
Control Station II
09) Pilot discharge line leak test at 7 bar
for 2 minutes from Control Station II
10) Distribution Main Valve function test
(Main Valve for SCR Room) from
Control Station II
PERFORMANCE
CHECK POINT CARRIED NOT
OUT APPLICABLE
11) Function test for audible & visual
alarms, ventilation shutdown test from
Control Station II
12) CO2 Operating Instructions &
evacuation sign board checked
13) Reset the system

NOTE: The system is now in operative condition.

REMARKS: …………………………………………………………………………………….

……………………………………………………………………………………

WITNESS: OWNER’S REPRESENTATIVE:

CLASS: __________________ SIGN & STAMP :

SIGN & STAMP NAME :


NAME : TITLE :
DATE : DATE :

SOLAS REPRESENTATIVE : LAMPRELL


REPRESENTATIVE :

SIGN & STAMP : SIGN & STAMP :

NAME : _________________ NAME : __________________


TITLE : __________________ TITLE : __________________
DATE : __________________ DATE : __________________

RIG REPRESENTATIVE

SIGN & STAMP :

NAME : _________________
TITLE : __________________
DATE : __________________