Distribution System Reliability
Distribution System Reliability
ABSTRACT
A stable and reliable electric power supply system is a pre-requisite for the technological and
economic growth of any nation. Nigeria's power supply has been experiencing incessant power
interruptions caused by a failure in the distribution system. This paper developed a system
planning approach as part of the key mitigation strategies for improved reliability and protection
of the distribution network. The developed algorithm is tested using 33kV feeder supplying
electricity to Kaura-Namoda, Zamfara State, Nigeria. A customer-based reliability index was
used as a tool to evaluate the reliability assessment of the feeder test system. The result showed
that alternative 3 gives better results in terms of improvement of the system average
interruption duration index (SAIDI), which in turn gives the minimum interrupted energy. Also,
it is found that a greater number of sectionalizing switches do not give better results. It is very
important to place the sectionalizing switches at a strategic location. If it is located at such
points that will facilitate to sectionalize the faulty sections faster and to make the supply
available to the unfaulty part of the network. Hence the utility company should apply this
mitigation algorithm for system reliability improvement, depending on their needs and
requirements. Thus, utilities can optimize network performance and better serve customers by
adopting mitigation strategies in addressing trouble-prone areas to achieve a stable and reliable
supply
Keywords: distribution system; reliability; reliability indices; system performance evaluation; protection
system; mitigation algorithms and sectionalizing switches.
The studies [3] used genetic algorithm (GA) based IEEE 57-bus test systems were successful but the
optimization to optimally locate FACTS devices - work is more of theoretical assumptions.
Unified Power Flow Controllers (UPFC) and the In the study [15], a static var compensation (SVC)
Thyristor Controlled Series Controllers (TCSC) was conducted on the Nigerian 330kV transmission
devices in the Nigeria 330kV integrated power network with the focus of developing indices for
network for power transfer increase and loss improving the transient stability using an appropriate
minimization at different active and reactive power size to locate SVC within the network. The result
loadings. The result showed that there was a showed an improved voltage profile and stability of
reduction in transmission line losses of both active network but the authors did only consider the
and reactive power, after incorporation of TCSC and optimal size of the DG. Kotamarty et al [16] proposed
UPFC devices optimally into the network This contingency analysis in the system due to DG
approach of optimization technique which is initiated location and sizing. The objective function was to
with random generation of the population always find the optimal location and size of DG to minimize
lack accuracy when a high-quality solution is voltage deviation from a predetermined profile but
required. Particle swarm optimization (PSO) the method did not meet the requirement of
technique was applied by the authors [4] for the robustness.
optimal placement of DG in the distribution network Jokojeje et al [17] carried research on improving the
of 33 and 69 -bus systems. The paper presented 330kV Nigeria grid network through static
different types of DGs using the PSO technique for synchronous compensator (STATCOM). In their
active and reactive power compensation to minimize work, the effect of the application of static
the real power losses in the primary distribution synchronous compensator, a FACTS controller was
networks. A Genetic Algorithm based optimal size examined on the performance on Nigeria 330kV, a
and placement of DG in the distribution network has 28-bus power system. Conventional and modified
been proposed [5 - 10]. The GA methods are used Newton-Raphson based power flow equations
to find optimal size and bus location for placing DG describing the steady-state condition before and
using power loss and energy loss minimization in a after compensation was analyzed through the
network system based on bus admittance, system. Results from the analysis showed that 5 out
generation information, and load distribution of the the 28 buses of the sample system have their voltage
system. magnitudes fell outside the statutory limits of 0.95 ≤
The authors [11-12] tackled the problem of network vi ≤ 1.05, were improved, and the total system
reconfiguration to minimize real power loss in the power losses were reduced by 5.88%.
system. They applied a meta-heuristic optimization This study proposed the use of mitigation strategies
method to achieve the objective. The algorithm through the development of an algorithm for
developed predicts the switching pattern for improving the reliability and protection of the system
reconfiguration which gives minimum loss and network. A 33kV feeder network supplying electricity
minimum voltage deviation. It also reduces the from Gusua to Kaura-Namoda Zamfara state, Nigeria
number of switching operations and at the same time is used as a case study.
satisfying constraints. Rama Rao et al [13] presented
a method of using a plant growth simulation 2. METHODOLOGY
algorithm (PGSA) for radial distribution network The appropriate placement of protection devices,
reconfiguration. The effectiveness of this proposal sectionalizes, and switches in the distribution feeders
was tested on a 69-node radial distribution system. have a significant impact on reliability improvement
The result, when compared with the genetic and this will be further enhanced by the application
algorithm optimization method, showed that PGSA of outage mitigation techniques for the distribution
succeeded in finding a global solution with a high system in Nigeria. The Mitigation Techniques like
probability of approximate solution. Ankur et al [14] electric or non-electric methods could be used to
proposed a network reconfiguration based on a improve the reliability in the system. Modern
genetic algorithm that employs the use of graphical automation technologies can reduce contingency
user interface (GUI) of MATLAB software. Tests margins, improve utilization and economy of
carried on 6-bus, IEEE 14-bus, IEEE 30-bus, and operation, and even provide improved scheduling
and effectiveness of maintenance and service [1,
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1199
RELIABILITY AND PROTECTION IN DISTRIBUTION POWER SYSTEM CONSIDERING CUSTOMER-BASED INDICES, J. N. Nweke, et al
18]. However, they must be applied well, with the 2.2.1 Analysis of Load and Generation
technologies selected to be compatible with the The determination of the required amount of system
system’s need and targeted effectively. On the other generating capacity is to ensure an adequate supply.
hand, a non-electric method such as vegetation This is an important aspect of power system planning
management, system improvements, crew and operation and, it is divided into static and
placement and management, maintenance practices operating capacity requirements. The static capacity
play an important role in improving reliability in the area relates to long term evaluation of this overall
system [19]. system requirement, while, the operating capacity
area relates to the short-term evaluation of the
2.1 Value-based reliability planning actual capacity required to meet a given load level.
The bid for Power Company to balance between the
cost of improving service reliability and quality, and
the economic benefits that these improvements
bring to customers and this approach is generally
known as Value Base Reliability Planning (VBRP).
Value-Based Reliability Planning directly takes
account of the value of reliability and power quality
to customers in assessing the cost-effectiveness of
the proposed investment alternatives [20]. In
general, VBRP follows the process as shown in Figure
1. This involves the assessment of power quality
supply to customers and the application of measures
to improve the prevailing conditions. The probability
of consumers being disconnected for any reason can Figure 1: Value-based Reliability Planning
be reduced by an increased investment during the
planning phase, operating phase, or both and vice
versa. It is evident therefore that the economic and
reliability constraints can be competitive, and this
can lead to difficult managerial decisions at both the
planning and operating phases [21]. Despite the
above constraints, it is necessary to ensure a
reasonable balance in the reliability of the various
constituent parts of a power system, i.e generation,
transmission, and distribution. Once the distribution
systems are planned, designed, and built, they must
be continually monitored, adjusted, expanded, and
repaired.
preventive and corrective maintenance. Corrective reclosers have been used along with the mitigation
maintenance replaces or repairs failed components, techniques such as vegetation management and
while preventive maintenance is a proactive overvoltage protection to evaluate the reliability of
approach to improve the condition of an active a 33 kV feeder installed for power supply to Kaura-
component that may be deteriorated to some Namoda in Zamfara state of Nigeria shown in figure
degree. 3. For reliability analysis of an existing system, the
reliability indices are calculated but the predictive
2.3 Reliability Assessment Test on 33kv reliability analysis of a future system, its reliability
Feeder System indices are interpolated. Reference values are
The summarized reliability data (2018) for the obtained from the values of the best alternative of
feeder collected from the Gusau distribution the previous year in case of predictive analysis,
substation Zamfara state is presented Table 1 whereas calculated values are obtained based upon
Reliability indices are statistical aggregations of the historical data of failures with the number of
reliability data from a well-defined set of loads, customers connected and affected by the outage.
components, or customers. Several alternatives The following customer-based indices [26] are used
such as placement of load break switch (LBS), auto to test the 33kV feeder system.
14
27
13
26
20 12
25
24 19 11
23 18 10
22
9
Substation
1
4 5 7
6
2 8
3 15
28 21
16
29
30 17
SAIFI
Total number of customer int erruption
N i i
(1)
Total number of customers connected N i
Where λi is the failure rate and Ni is the number of customers of load at the ith node.
SAIDI
Sum of customer int erruption duration
N i i
(2)
Total number of customers connected N i
Where Ui is the annual outage time and Ni is the number of customers of load at ith node
CAIDI
Sum of customer int erruptions duration
N
i i
SAIDI
(3)
Total number of customers int erruptions N i i SAIFI
Where λi is the failure rate, Ui is the annual outage time and Ni is customers at ith load point.
CAIFI
Total number of customer int errupted
i Ni
(4)
Total number of customers connected N
ASAI
Costomer hours of available service
N i 8760 i Ni
(5)
Total hours of demanded N i 8760
Table 2 Reliability results with the existing system for the year 2018
Calculated Reference Alternative Alternative Alternative
Indices Unit
Value Value 1 2 3
SAIFI Inter/yr 18.699 15.264 15.264 15.264 15.264
SAIDI h/inter 30.130 26.100 25.310 25.405 25.211
CAIDI h/yr 1.611 1.709 1.658 1.664 1.651
ASAI % 99.66 99.702 99.711 99.710 88.712
Average
kWh/yr 13300.90 12843.70 12892.20 12795.30
Interruption
Peak power MW 1.035
Heaviest loaded line % 4.28
Max. voltage drop % 0.44
30
RELIABILITY INDICES
State, Nigeria. A customer-based index via SAIFI,
SAIFI
SAIDI SAIDI, CAIDI, and ASAI were used as tools to
25
evaluate the reliability assessment of the feeder test
20
system. The result showed that alternative 3 gives
better results in terms of improvement of SAIDI,
Indices
4000 5. REFERENCES
2000
[1] Okorie P.U., Aliyu U. O, Jimoh B., and Sani S. M.,
“Reliability Indices of Electric Distribution
0 Network System Assessment”, Journal of
Electronics and Communication Engineering
Ref. Values Alt. 1 Alt. 2 Alt. 3
Figure 5 Energy interrupted due to interruption Research, vol. 3, no. 1, Dec.2015, pp. 1 – 6.
[2] Brown R. E., “Electric Power Distribution
Figure 4 shows the customer-based reliability indices Reliability”, 2nd Edition. Cambridge University
analysis using SAIFI and SAIDI with different Press, pp. 94-100, 1998
alternative It is found that an Alternative. 3 gives the [3] Eseosa O and Roland U., “Genetic Algorithm-
minimum SAIDI where SAIFI is found to be the same Based Optimal Placement of TCSC and UPFC in
the Nigeria 330KV Integrated Transmission Line
with all the alternatives. Hence, Alt.3 indicates the
Network at Different Reactive Power Loadings”,
best choice for the better performance of the Journal of Engineering Science and Technology
network. Review, vol. 6, no. 5, Jan. 2014 pp. 82 – 89.
The customer-based reliability indices are measured [4] Satish K, Vishal K., and Barjeev T.“Optimal
based on the energy interrupted. Figure 5 shows the Placement of Different Type of DG Resources in
energy interrupted due to interruption in the Distribution Networks”, Electrical Power and
network. The result indicates that Alt. 3 gives less Energy Systems,vol. 53, 2013, pp.752-760.
energy interrupted and thus the best alternative for [5] Deependra S., Devender S., and Verma K. S, “GA
Based Optimal Sizing and Placement of
improved reliability.
Distributed Generation for Loss Minimization”,
International Journal of Electrical and Computer
4. CONCLUSION Engineering, vol. 2, no. 8, 2007, pp. 556 –562.
Developing the reliability improvement strategy is [6] Mithulananthan N., Than O., and Le Van P.,
important as well as applying interruption mitigation “Distributed Generator Placement in Power
techniques to obtain improved results. This paper Distribution System Using Genetic Algorithm to
developed a system planning approach as part of the Reduce Losses”, Thammasat International
Journal of Science and Technology, vol. 9, no.3,
key mitigation strategies for improved reliability and Sept. 2004, pp. 55 – 62,
protection of the distribution network. The
[7] Soma B. and S. K. Goswami, “Genetic Algorithm
developed algorithm is tested using 33kV feeder based on Optimal Placement of Distributed
supplying electricity to Kaura-Namoda, Zamfara Generation Reducing Loss and Improving
Voltage Sag Performance”, International Journal Contingency Analysis”, Electric Power Resource,
on Electrical and Power Engineering, vol. 2, no. vol. 78, no. 9, 2008, pp 1537- 1545.
1, 2011, pp. 21 – 23. [17] Jokojeje R A., Adejumobi I A., Mustapha AO,
[8] Rashmi P., Surya P., Geeta K., Khan Z.R, and and. Adebisi O I, “Application of
Komal S., “Optimal Location and Sizing of StaticSynchronous Compensator (STATCOM) in
Generator in Distributed Generation System”, Improving Power System Performance, A Case
International Journal of Innovative Research in Study of the Nigeria 330kV Electricity grid”,
Electrical, Electronics, Instrumentation and Nigerian Journal of Technology, vol. 34, no. 3,
Control Engineering Vol. 2, no. 3, March 2014, July 2015, pp. 564 – 572.
pp.1272- 1277. [18] Northcote-Green J and Wilson R., “Control and
[9] Shukla T. N., Singh S. P., and. Naik K. B., Automation of Electrical Power Distribution
“Allocation of Optimal Distributed Generation Systems, Taylor and Francis Group, 2008.
using GA for Minimum System Losses”, Fifteenth [19] Jibril Y and Ekundayo, K.R., “Reliability
National Power Systems Conference (NPSC), IIT Assessment of 33kV Kaduna Electricity
Bombay, Dec. 2008, pp.113 –118. Distribution Feeders, Northern Region, Nigeria”,
[10] Zahra B and. Seyyed M. H, “GA Based Optimal Proceedings of the World Congress
Placement of DGs for Loss Reduction and onEngineering and Computer Science, (WCECS),
Reliability Improvement in Distribution Networks San Francisco, USA, 23-25, 2013, pp.1 – 5.
with Time-Varying Loads”, International Journal [20] Michael J, Sullivan B., Suddeth N., Vardell T and
of Intelligent Systems and Applications, vol. 4, Vojdani A., “Interruption Costs Customer
pp. 2013, 55 – 63. Satisfaction and Expectations for Service
[11] Rajaram R, Sathish K. K, and Rajasekar N., Reliability”, IEEE Transactions on Power
“Power System Reconfiguration in a Radial Systems, vol.11, no. 2, May 1996, pp. 989 - 995
Distribution Network for Reducing Losses and to [21] Billinton R. and. Allan R. N., “Reliability
Improve Voltage Profile using Modified Plant Evaluation of Power System”, Tata McGraw-Hill
Growth Simulation Algorithm with Distributed Publishing Company Limited, New Delhi, New
Generation (DG)” Energy Reports, vol. 1, 2015, York, 2nd edition.2005, pp. 184-205.
pp.116 – 122.
[22] Da Silva M.G., Rodrigues A. B, de Castro C. L.C.,
[12] Chidanandappa R., Ananthapadmana T., and Neto A.C., Moutinho E.A, Neto N.S.A., and
Ranjith H. C., “Genetic Algorithm-Based Network Cavalcante A.B.,“Reliability Assessment of
Reconfiguration in Distribution Systems with Distribution Networks in Brazil Northeast”,8th
Multiple DGs for Time-Varying Loads”, Science International Conference ond Probabilistic
Direct Proceeding Technology, vol. 21, Aug. Methods Applied to Power Systems, Iowa State
2015, pp. 460 – 467. University, September 12-16, 2004, pp 134 - 152
[13] Rama Rao P. V.V and Sivanagaraju S., “Radial [23] Kjolle G and Sand K., “An Analytical Approach
Network Reconfiguration for Loss Reduction and for Distribution System Reliability Assessment”,
Load Balancing Using Plant Growth Simulation IEEE Transactions on Power Delivery, vol.7, no.
Algorithm,” International Journal on Electrical 2, April 1991, pp. 729 – 734.
Engineering and Informatics, vol.2, no. 4,
Nov.2010. pp. 266 – 277. [24] Woczynski E., Billinton R, and Wacker G.,
“Interruption Cost Methodology and Results- A
[14] Ankur A and Prabodh K., “GUI Based Network Canadian Commercial and Small Industry
Reconfiguration System for Loss Minimization in survey”, IEEE Transactions on Power Apparatus
Distribution Network,” International Journal of and Systems, vol. PAS-103, no. 2, Feb. 1984,
Science and Research, vol. 4, no. 1, January pp.437- 444.
2015, Pp. 805 – 808.
[25] Wacker G. and Billinton R., “Customer Cost of
[15] Ayodele T. R., Ogunjuyigbe, A.S. O. and Alodele Electric Service Interruptions” Proceedings of the
O. O., “Improving the Transient Stability of IEEE, vol.77, no. 6, June 1989, pp.919 – 930.
Nigerian 330kV Transmission Network using
Static Var Compensator”, Nigerian Journal of [26] Dorji T, “Reliability Assessment of Distribution
Technology, vol. 32, no. 1, January 2016, pp. Systems,A Case Study on Wangdue Distribution
155 – 166. System in Bhutan,” Master thesis, Norwegian
University of Science and Technology, May 2009,
[16] Kotamarty S, Khushalani S., and Schulz N., Pp 9-16.
“Impacts of Distributed Generation on