Tile Work Quotation and Labor Cost
Tile Work Quotation and Labor Cost
Surigao City
OFFICE OF THE BUILDING AND ESTIMATES
AMOUNT (P)
10,340.00
23,340.97
#NAME?
663,940.00
484,460.00
416,615.00
205,653.13
136,845.00
136,845.00
56,900.00
287,955.00
85,675.00
77,820.00
45,825.00
#NAME?
2,256,538.00
871,350.00
225,653.80
156,394.40
3,509,936.20
II. EARTHWORKS:
A. Excavation: (Volume = 104.91 cu.m)
LABOR COST 14,984.93
V. STEEL WORKS:
16mm.Ø x 6m. Deformed Bars 2285 kgs. 60.00 137100.00
12mm.Ø x 6m. Deformed Bars 573 kgs. 55.00 31515.00
10mm.Ø x 6m. Deformed Bars 2634 kgs. 55.00 144870.00
#16 Tie Wire 101 kgs. 75.00 7575.00
TOTAL ESTIMATED MATERIAL COST 321060.00
LABOR COST 163,400.00
TOTAL COST 484,460.00
X. RAILINGS:
30 mm Φ x 6m Stainless Pipe 13 lgths. P 3,200.00 P 41,600.00
Welding Electrodes 34 kgs. P 350.00 P 11,900.00
Grinding Stone 4 pcs. P 200.00 P 800.00
TOTAL ESTIMATED MATERIAL COST P 54,300.00
TOTAL ESTIMATED LABOR COST P 2,600.00
TOTAL COST P 56,900.00
XII.
PaintPAINTING
Thinner WORKS:
Liquid Tile Primer White 33 gals. P 730/ gal P 24,090.00
33 gals. P 845/ gal P 54,300.00
Flatwall Enamel Paint, Davies 13 gals. P 535/ gal P 6,955.00
Tinting Color , Latex 17 gals. P 120/ gal P 840.00
Quick Dry Enamel Paint, Davies 34 gals. P590 / gal P 20,060.00
Concrete Neutralizer 13 li. P 410/ gal P 5,330.00
Paint Thinner 26 gals. P 245/ gal P 6,370.00
TOTAL ESTIMATED MATERIAL COST P 74,475.00
TOTAL ESTIMATED LABOR COST P 11,200.00
TOTAL COST P 85,675.00
CONSTN.
1 500 3,567.84
FOREMAN 5 men excavate
53.52 7.5 cu.m / day 7
LABORER/
4 400 11,417.09
HELPERS
SUB-TOTAL 14,984.93
B. BACKFILL
STRUCTURE AREA(sq.m) DEPTH(m) VOLUME QUANTITY TOTAL (cu.m)
(cu.m)
F1 0.91 1 0.91 18 16.38
CONSTN.
1 400 1,187.44
FOREMAN 5 men (backfill)
44.53 15cu.m/ day 3.0
LABORER/
4 250 2,968.60
HELPERS
SUB-TOTAL 4,156.04
C. GRAVEL FILL
VOLUME
STRUCTURE AREA(sq.m) DEPTH(m) (cu.m) QUANTITY TOTAL (cu.m)
F1 1 0.1 0.10 18 1.80
Septic tank 4.5 0.1 0.45 1 0.45
CB & GT 0.36 0.1 0.04 9 0.32
Wall footing 29.08 0.1 2.91 1 2.91
Floor 121 0.1 12.10 1 12.10
SUB-TOTAL 17.58
LABOR COST
TOTAL VOLUME TOTAL DAY NO. OF COST PER DAY TOTAL COST
WORKER (cu.m.) CAPABILITIES
FINISHED WORKERS (₱) (₱)
SUB-TOTAL 59,886.75
B. SCAFFOLDINGS
WORK TOTAL AREA MATERIAL TOTAL COST
(sq.m.) PIECES BOARDFEET KILOGRAM
DESCRIPTION COST (₱) (₱)
COLUMN - SCAFFOLDINGS
COCO LUMBER
VERTICAL
SUPPORT 469 18.00 8,436.31
(2"x3"x10')
99.72
COCO LUMBER
HORIZONTAL
SUPPORT 2094 15.00 31,411.80
(2"x2"x10') 99.72
COCO LUMBER
DIAGONAL
SUPPORT 1167 18.00 21,001.03
(2"x3"x10')
BEAM
Top Bars 432 681 60 40,860.00
Bottom Bars 384 606 60 36,360.00
Extra Bars 438 691 60 41,460.00
SUB-TOTAL 118,680.00
16mmØ X 6m [Link]
LENGTH OF
VERTICAL BAR NO. OF QUANTITY / MATERIAL TOTAL COST
STRUCTURE PER COLUMN FACTOR
COLUMN Kgs COST (₱) (₱)
(m)
C1 52.14 0.6336 m. / 19 164 9,840.00
60
C2 69.52 kg 7 19 1,140.00
SUB-TOTAL 10,980.00
12mmØ X 6m [Link]
QUANTITY / MATERIAL TOTAL COST
STRUCTURE AREA(sq.m) FACTOR
Kgs COST (₱) (₱)
1-WAY SLAB 16 2.866 pcs. / sq.m 42 2,310.00
55
2-WAY SLAB 184 3.252 pcs. / sq.m 531 29,205.00
SUB-TOTAL 31,515.00
#16 G.I TIE WIRE
LENGTH OR
STRUCTURE AREA (m / FACTOR
sq.m)
WALL 600.36 .024 kg. tie wire /sq.m 14 1,050.00
FOOTING 2.3 53 meter / kg. 11 825.00
SLAB 1 16 0.228 kg. / sq.m 3 225.00
75
SLAB 2 184 .35 kg / sq.m 63 4,725.00
BEAM 6 450.00
53m/kgs
COLUMN 4 300
SUB-TOTAL 7,575.00
LABOR
TOTAL CAPABILI - TOTAL DAY NO. OF COST PER DAY TOTAL COST
WORKER
WEIGHT (kgs) TIES FINISHED WORKER (₱) (₱)
CONSTN. 1 men take
1 400 34,400.00
FOREMAN 12.5 kgs/day
5368 86
STEELMEN 5 men take 5 300 129,000.00
62.5 kgs./day
SUB-TOTAL 163,400.00
TOTAL 484,460.00
[Link] WORKS
CONCRETE HOLLOW BLOCK
STRUCTURE AREA (sq.m) FACTOR QUANTITY MATERIAL TOTAL COST
COST (₱) (₱)
100mm THK
600.36 12.5 pcs/sq.m 7505 15.00 112,575.00
(4") CHB
SUB-TOTAL 112,575.00
MATERIAL
BAGS OR TOTAL COST
COMPONENT AREA(sq.m) FACTOR COST (₱)
CU.M (₱)
PORTLAND Block Laying 600.36 0.522 313 260.00 81,380.00
CEMENT
(CLASS B) Plastering 1200.72 0.192 231 260.00 60,060.00
PLASTERING
CONSTN. OF CHB. 3
1 400.00 16,800.00
FOREMAN MEN PLASTER
12 SQ.M/ DAY
1200.72 42
LAYING OF
MASON/ CHB. 2 MEN
8 300.00 100,800.00
LABORERS LAY 100PCS /
DAY
SUB-TOTAL 117,600.00
TOTAL 416,615.00
VII. TILE WORKS
MATERIAL TOTAL COST
MATERIAL DESCRIPTION TILE TYPE AREA (sq.m) QUANTITY
COST (₱) (₱)
FLOOR TILES (CR) (0.20x0.20) Unglazed 8.68 217 35.00 7,595.00
WALL TILES (CR) (0.20x0.20) Glazed 19.01 475 35.00 16,633.75
FLOOR TILES (0.40x0.40) Marble 91.32 571 110.00 62,782.50
OUTDOOR FLOOR TILES
Ceramic 25.25 158 70.00 11,046.88
(0.40x0.40)
SUB-TOTAL 98,058.13
TOTAL AREA QUANTITY / MATERIAL TOTAL COST
MATERIAL DESCRIPTION FACTOR
(sq.m) KG. COST (₱) (₱)
SUB-TOTAL 13,200.00
TOTAL 205,653.13
`
SURIGAO STATE COLLEGE OF TECHNOLOGY
Surigao City
OFFICE OF THE BUILDING AND ESTATES
C. EQUIPMENTS
D. MISCELLANEOUS / CONTINGENCIES