AKG02 WH10 & WH11 Decks and Pipelines Facilities: General
AKG02 WH10 & WH11 Decks and Pipelines Facilities: General
PROJECT SERVICES
IGM0135 Prepare Project Execution Plan 93 30MAY06* 30AUG06 30MAY06A 30AUG06 50
SCHEDULE
IGM0155 Prepare Contract Master Schedule 31 30MAY06* 29JUN06 30MAY06A 13JUL06A 100
IGM0145 Prepare Front End Schedule 124 30JUN06 31OCT06 30JUN06A 31OCT06 60
COMMON
ENGINEERING
GENERAL
PLANNING PACKAGE
ITEG0005 Compile CTR's for awarded scope 21 19JUN06 09JUL06 14JUN06A 04JUL06A 100
ITEG0020 Compile & Submit Planning Package 4 28AUG06 31AUG06 11SEP06 27SEP06 50
DESIGN ENGINEERING
PROCESS ENGINEERING
ICPRO203A Process Design Basis (AFD) 60 01JUL06 09SEP06 01JUL06A 09SEP06 80
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 1 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
ICPRO204A Design & Operating Philosophy (AFD) 81 10SEP06 16DEC06 10SEP06 16DEC06 0
STRUCTURAL ENGINEERING
ICSTR202 Detailed Design Basis 49 22JUL06 17SEP06 26JUL06A 16SEP06 55
MECHANICAL ENGINEERING
VALVES
ICMEC231A1 Enquiry Requisition for 28" Valves 4 09SEP06 12SEP06 07SEP06 11SEP06 0
(Actuated)
ICMEC231A5 Enquiry Requisition for 24" Valves 4 09SEP06 12SEP06 07SEP06 11SEP06 0
(Actuated)
ICMEC241A1 TBE/CBE for 28" Valves (Actuated) 58 26SEP06 05DEC06 25SEP06 04DEC06 0
ICMEC241A5 TBE/CBE for 24" Valves (Actuated) 58 26SEP06 05DEC06 25SEP06 04DEC06 0
ICMEC231K Enquiry Requisition for Manifold Valves 4 09SEP06 12SEP06 05NOV06 08NOV06 0
ICMEC241K TBE/ CBE for Manifold Valves Large Bore 58 26SEP06 05DEC06 22NOV06 04FEB07 0
MECHANICAL
ICMEC258J ITRS/DRS for valves 242 22JUL06 22JUL06 22JUL06A 25AUG06 25
ICMEC258K ITRS/DRS for mechanical equipments 242 20MAR07 20MAR07 22JUL06A 20MAR07 25
ICMEC240A TBE/ CBE for Test Separator 107 10FEB07 14JUN07 27JUL06A 07DEC06 25
ICMEC240G TBE/ CBE for Instrument/ Plant Air Skid 1 17AUG06 17AUG06 26AUG06 26AUG06 0
ICMEC242A TBE/ CBE for Pedestal Crane 1 22AUG06 22AUG06 26AUG06 26AUG06 0
ICMEC205A Calculation - Pipe Wall Thickness Report 60 28SEP06 10DEC06 28SEP06 10DEC06 0
ICMEC230A Enquiry Requisition for Barred Tee / Boot 4 29MAY07 02JUN07 30SEP06 03OCT06 0
Tee
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 2 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
ICMEC230B Enquiry Requisition for Pig Launcher 4 29MAY07 02JUN07 30SEP06 03OCT06 0
ICMEC241C TBE/ CBE for Ball Valves Large Bore 35 23OCT06 03DEC06 19OCT06 30NOV06 0
(Alloy)
ICMEC241D TBE/ CBE for Double Block & Bleed 35 23OCT06 03DEC06 19OCT06 30NOV06 0
Valves
ICMEC241E TBE/ CBE for Wafer Check Valves 35 23OCT06 03DEC06 19OCT06 30NOV06 0
ICMEC245A TBE/ CBE for Barred Tee / Boot Tee 48 18JUN07 13AUG07 19OCT06 17DEC06 0
INSTRUMENTATION ENGINEERING
ICEI152IE ITRS/DRS for E & I 247 12SEP06 16MAY07 12SEP06 16MAY07 0
PROCUREMENT
GENERAL
IGPP0005 Prepare Early Procurement & Subcontract 41 30MAY06 09JUL06 30MAY06A 09JUL06A 100
Plan
WH 10 DECK
ENGINEERING
DESIGN ENGINEERING
MECHANICAL ENGINEERING
I10MEC221A Data Sheet for 28" Valves (Actuated) 258 27JUL06 04JUN07 26JUL06A 04JUN07 55
I10MEC22A5 Data Sheet for 24" Valves (Actuated) 258 27JUL06 04JUN07 26JUL06A 04JUN07 55
I10MEC220A Data Sheet for Test Separator & Internals 258 27JUL06 04JUN07 27JUL06A 04JUN07 80
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 3 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
I10MEC222A Data Sheet for Pedestal Crane 4 09AUG06 13AUG06 09AUG06A 13AUG06A 100
I10MEC220B Data Sheet for Pig launcher 241 16AUG06 04JUN07 16AUG06A 04JUN07 55
I10MEC220G Data Sheet for Instrument/ Plant Air Skid 241 16AUG06 04JUN07 16AUG06A 04JUN07 55
I10MEC224A Data Sheet for Barred Tee / Boot Tee 241 16AUG06 04JUN07 16AUG06A 04JUN07 55
I10MEC220F Data Sheet for Diesel Filter Coalescer 237 22AUG06 04JUN07 22AUG06A 04JUN07 85
I10MEC220Q Data Sheet for Closed drain Pump 237 22AUG06 04JUN07 22AUG06A 04JUN07 85
I10MEC221B Data Sheet for Manifold Valves 65 01JUL06 14SEP06 26AUG06 11NOV06 0
I10MEC220D Data Sheet for Chemical Injection pumps 228 02SEP06 04JUN07 02SEP06 11JUN07 0
I10MEC220H Data Sheet for Well Service Pump 228 02SEP06 04JUN07 02SEP06 04JUN07 0
Package
I10MEC220R Data Sheet for Closed drain Booster Pump 216 16SEP06 04JUN07 16SEP06 04JUN07 0
I10MEC220S Data Sheet for Open Drain Tank Pumps 216 16SEP06 04JUN07 16SEP06 04JUN07 0
I10MEC220T Data Sheet for Wash down Pump 216 16SEP06 04JUN07 16SEP06 04JUN07 0
I10MEC220U Data Sheet for Diesel Transfer Pump 216 16SEP06 04JUN07 16SEP06 04JUN07 0
I10MEC220Z Data Sheet for Basket Strainer 216 16SEP06 04JUN07 16SEP06 04JUN07 0
I10MEC220K Data Sheet for Washdown Storage Tanks 204 30SEP06 04JUN07 30SEP06 04JUN07 0
I10MEC220L Data Sheet for Diesel Storage Tank 204 30SEP06 04JUN07 30SEP06 04JUN07 0
I10MEC220E Data Sheet for CP Separator 203 01OCT06 04JUN07 01OCT06 04JUN07 0
I10MEC220I Data Sheet for Closed Drain Vessel 203 01OCT06 04JUN07 01OCT06 04JUN07 0
I10MEC220J Data Sheet for KHI Storage Tank 203 01OCT06 04JUN07 01OCT06 04JUN07 0
I10MEC220M Data Sheet for Antifoam & Ethylene Glycol 203 01OCT06 04JUN07 01OCT06 04JUN07 0
Tanks
I10MEC220N Data Sheet for Open Drain Tank 203 01OCT06 04JUN07 01OCT06 04JUN07 0
I10MEC220O Data Sheet for Well Service Tank 191 15OCT06 04JUN07 15OCT06 04JUN07 0
I10MEC220P Data Sheet for CI Storage Tank 191 15OCT06 04JUN07 15OCT06 04JUN07 0
I10MEC224D Building- Design data, Safety & interior 191 15OCT06 04JUN07 15OCT06 04JUN07 0
elemts.
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 4 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
STRUCTURAL INPUTS TO MODEL
I10STR406C Issue MTO for Primary & Secondary Steels 0 14SEP06 07DEC06 0
AREA DESIGN
I10PIP120A Studies - Layout Studies (All Area) 86 16SEP06 28DEC06 16SEP06 28DEC06 0
ELECTRICAL ENGINEERING
I10EI206EF Data sheets for Subsea cable & 248 15OCT06 09AUG07 15OCT06 09AUG07 0
Accessories
PROCUREMENT
PROCUREMENT SERVICES (Dur from PO to Del at JAY)
PROCUREMENT SERVICES
I10PRIN25 Proc. DCS & TMR System 350 16JUL06 30JUN07 16OCT06 30SEP07 0
WH11 DECK
ENGINEERING
DESIGN ENGINEERING
MECHNICAL ENGINEERING
I11MEC220A Data Sheet for Test Separator & Internals 273 27JUL06 21JUN07 27JUL06A 21JUN07 55
I11MEC222A Data Sheet for Pedestal Crane 1 09AUG06 09AUG06 09AUG06A 09AUG06A 100
I11MEC220G Data Sheet for Instrument/ Plant Air Skid 256 16AUG06 21JUN07 16AUG06A 21JUN07 85
I11MEC220F Data Sheet for Diesel Filter Coalescer 252 22AUG06 21JUN07 22AUG06A 21JUN07 85
I11MEC220Q Data Sheet for Closed drain Pump 252 22AUG06 21JUN07 22AUG06A 21JUN07 85
I11MEC221A Data Sheet for 28" Valves (Actuated) 231 16SEP06 21JUN07 16SEP06 21JUN07 0
I11MEC22A5 Data Sheet for 24" Valves (Actuated) 231 16SEP06 21JUN07 16SEP06 21JUN07 0
I11MEC220B Data Sheet for Pig launcher 231 07OCT06 12JUL07 07OCT06 12JUL07 0
I11MEC224A Data Sheet for Barred Tee / Boot Tee 213 07OCT06 21JUN07 07OCT06 21JUN07 0
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 5 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
PIPELINE
COMMON
ENGINEERING
GENERAL
ICPLP0035 Prepare Procurement Plan 104 30MAY06 10SEP06 30MAY06A 10SEP06A 100
ITEG0055 Compile & Submit Planning Package 4 11SEP06 14SEP06 14SEP06 17SEP06 0
DESIGN ENGINEERING
GENERAL
IOM Kick off Meeting 0 19JUN06 12SEP06 0
ICPLE200A Engg Managmnt, Doc Con, Project 256 26JUN06 21JUN07 19SEP06 14SEP07 0
Controls & Admin
ICPLE200B Engineering Execution Plan - GS 50 28JUN06 06SEP06 21SEP06 29NOV06 0
REPORTS
ICPLE202A Pipeline Engineering Design Basis 55 24JUL06 06OCT06 27JUL06A 06OCT06 85
ICPLE200C Re-analysis of WH6 & WH8 due to 186 15AUG06 31MAR07 07NOV06 19JUN07 0
Additional WYE
ICPLE230A Pipeline Wall Thickness Analysis 60 29AUG06 20NOV06 21NOV06 14FEB07 0
ICPLE223A WH10/ WH11 Flow assurance steady state 80 05SEP06 26DEC06 28NOV06 21MAR07 0
ICPLE223C Design pressure & HIPPS Philosophy 75 05SEP06 18DEC06 28NOV06 14MAR07 0
ICPLE223B WH10/ WH11 Flow assurance Transient 148 12OCT06 09MAY07 08JAN07 02AUG07 0
Analysis
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 6 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
MTO & DATA SHEET
ICPLE206A Datasheets for Linepipe - CS 41 01AUG06 26SEP06 01AUG06A 26SEP06 55
ICPLE206B Datasheets for Linepipe - CRA Clad & 41 29AUG06 24OCT06 29AUG06 24OCT06 0
Lined CS
ICPLE206C Datasheets for Bends 41 29AUG06 24OCT06 29AUG06 24OCT06 0
ICPLE206G Datasheets for Pipeline weight coating 41 31OCT06 27DEC06 22DEC06 20FEB07 0
TBE/CBE
ICPLE207A TBE/ CBE for Linepipe (CS) 18 19SEP06 12OCT06 19SEP06 12OCT06 0
ICPLE207B TBE/ CBE for Clad pipes & Induction Bend 18 17OCT06 09NOV06 17OCT06 09NOV06 0
PURCHASE REQUISITION
ICPLE208A PR for Line Pipe (CS) 7 13OCT06 19OCT06 13OCT06 19OCT06 0
ICPLE208P PR for Additional Subsea Ball Valve 7 10SEP06 16SEP06 01DEC06 07DEC06 0
DRAWING
ICPLE101A Overall drawing index & General notes 50 10OCT06 18DEC06 04JAN07 14MAR07 0
PROCUREMENT
GENERAL
ICPLP0005 Prepare Early Procurement & Subcontract 41 30MAY06 09JUL06 30MAY06A 09JUL06A 100
Plan
WH 10 PIPELINE
PROCUREMENT SERVICES
I10PLP080 Procurement of Additional Subsea WYE 365 27SEP06 26SEP07 19DEC06 18DEC07 0
I10PLP090 Procurement of Additional Subsea Ball 365 08OCT06 07OCT07 29DEC06 28DEC07 0
Valves
WH 11 PIPELINE
PROCUREMENT SERVICES
I11PLP080 Procurement of Additional Subsea WYE 365 27SEP06 26SEP07 19DEC06 18DEC07 0
I11PLP090 Procurement of Additional Subsea Ball 365 08OCT06 07OCT07 29DEC06 28DEC07 0
Valve
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 7 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.
Activity Activity TotalOrig Target Targetl Act Act Total % 2006
ID Description Float Dur Early Start Early Finish Fcst Comp M
Fcst Float JUN JUL AUG SEP OCT N
Start Finish 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
IGM0060 Mobilize Construction Team & Set up on 2 08OCT06 09OCT06 08OCT06 09OCT06 0
Drill Rig
IGM0070 Offshore Construction - Piping, Electrical 15 10OCT06 24OCT06 10OCT06 24OCT06 0
and I
IGM0080 N2/He Leak Testing 3 25OCT06 27OCT06 25OCT06 27OCT06 0
IGM0090 Punch List Clearance, Dossier Submission 3 28OCT06 30OCT06 28OCT06 30OCT06 0
& Revie
IGM0100 Final Handover 1 31OCT06 31OCT06 31OCT06 31OCT06 0
26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27
M JUN JUL AUG SEP OCT N
2006
Start Date 01SEP05
Early Bar FE01 Sheet 8 of 8 Date Revision Checked Approved
Finish Date 23DEC09 RAS GAS COMPANY LTD (III) 12AUG06 Rev. A For Internal Review & Comments Rajesh
Progress Bar
Data Date 25AUG06 14SEP06 Rev. B Rajesh
Critical Activity
AL KHEEJ GAS PROJECT (PHASE-2)
Run Date 19SEP06 17:35
FRONT END SCHEDULE
(Activities planned for next 120 days)
AKG-02 (WH10 &11 Facilities)
© Primavera Systems, Inc.