Slinging Operation Skill Training Course: Supplementary Text
Slinging Operation Skill Training Course: Supplementary Text
厚生労働省委託事業
玉掛け技能講習
補助テキスト
本補助テキストは,一般社団法人 日本クレーン協会のご協力の下,
『技能講習用テキスト 玉掛け作業者必携』
(日本クレーン協会発行,令和2年3月10日改訂2版)
を基に,令和元年度厚生労働省委託事業において設置
した
「補助テキスト作成検討会」
の審議を経て作成した抜粋対語訳版であり,上記の技能講習用テキストと併
2020年3月発行
用することにより,外国人労働者に対する教育効果を高める等の目的で作成されたものです。 受託:国際航業株式会社
印刷・製本:YAMAGATA株式会社
2020年3月
Table of Contents
Chapter 1
Knowledge of Cranes and Other Lifting Equipment
Chapter 2
Knowledge of Dynamics Necessary for Slinging Crane Loads
Chapter 3
How to Select and Handle Sling Gear
The figure number, table number, and page number in the parenthesis refer to the separate textbook (Japanese version).
1 (EN)
Chapter 4
Slinging and Signaling Methods
Chapter 5
Practical Slinging Methods
Chapter 6
Relevant Laws and Regulations
2 (EN)
Chapter 1
Knowledge of Cranes and Other Lifting
Equipment
Slinging is the work to secure a load or remove it from the hoisting accessory with sling gear.
Derrick ● Those who have completed the special ● Those who have completed the special
training course *1
training course *1
Cargo hoist
● Those who have approved by the Minister ● Those who have approved by the Minister
of Health, Labour and Welfare*2 of Health, Labour and Welfare*2
● Those who have completed the special
education for the sling works
*1: The training course listed in the column of training courses of Appended Table 4 of the Enforcement Ordinance on the Human
Resources Development and Promotion Act
*2: A person who has completed the training of crane operation course prescribed in the Ordinance on the Human Resources
Development and Promotion Act
3 (EN)
2 Overview of Cranes (p.2)
Cranes
“Crane” means any mechanical device designed to lift loads by power and carry the lifted loads horizontally,
other than mobile cranes, derricks and cargo hoists. Accordingly, the crane does not include any of the
mechanical devices which lift goods by human power. On the other hand, the crane includes those mechanical
devices which lift goods by a power even if they rely on human power for the horizontal conveyance of the lifted
goods.
Mobile Cranes
“Mobile crane” means any of those cranes which have built-in motors to move themselves to unspecified place.
Derricks
Derricks are those mechanical devices which are designed to lift goods by motive power, have a mast or a
boom and are operated by wire ropes with motors installed separately.
Cargo Hoists
Cargo hoists are those mechanical devices which are attached to ships to load or unload the ships or move
cargo in the hold.
4 (EN)
3 Motions of Crane (p.3)
The following are the motions of a crane in lifting a load and carrying it to the desired place.
3.2 Traversing
Traversing is a motion of the crane to move its trolley (or hoist) along the girder of the overhead traveling crane/
bridge crane, horizontal jib of the hammer-head crane, or rope of the cable crane. See Fig. 1-1.
3.3 Traveling
Traveling is the movement of the whole crane such as girder, jib and tower on its traveling rail or runway. See
Fig. 1-1.
Girder Trolley
Traversing
Traveling
Lifting
Lowering
5 (EN)
3.4 Derricking
Derricking is the upward/downward movement of the job or boom from its end.
Jib angle
The motion of the jib in the direction that increases the jib angle (the angle between the centerline of the jib and
the horizontal plane) is called the “lifting or raising of the jib”, while its motion toward a smaller jib angle is called
the “lowering of the jib”. An ordinary jib crane, when derricking, brings the load up or down.
A structural improvement is provided to remove this undesirable motion so that the load can be held at a given
height and moved horizontally during derricking. This improved motion is called “level luffing.” “Luffing in” means
the movement of the load toward the jib and “luffing out” means the movement of the load away from it.
This level luffing does not include an upward or downward motion of the lifted load that may be involved in jib
derricking.
6 (EN)
3.5 Slewing
“Slewing” means the rotation of the jib or other similar component of the jib crane/mobile crane with its center of
rotation as the axis.
Center of rotation
Increasing the length of the jib is called “extension” and decreasing its length is called “retraction.” (See Fig. 1-7:
p.6.)
7 (EN)
4 Technical Terms Relating to Cranes (p.6)
For the cranes with jib or mobile crane/derrick with boom, it is the load after deduction of the weight of the hook,
grab bucket or any other hoisting accessory from the maximum load that may be laid according to its
construction or configuration (jib/boom angle and length, trolley position on the horizontal jib) and materials
used.
For mobile cranes, the hooks are changed depending on the type of the operation. Even when the jib length and
operating radius are the same, the rated load varies with a change of the hook. In general, the rated gross load
(the weight of the hook or any other hoisting accessory is added to the rated load) is used. See Fig. 1-5.
Jib length in
minimum
Extended in maximum
Fig. 1-5 Relation Between Lifting Load, Rated Gross Load, and Rated Load
8 (EN)
4.4 Limit Load
The term “limit load” means the maximum load that may be laid on a cargo hoist according to its construction
and materials used. The limit load includes the weight of the hoisting accessory such as hook or grab bucket.
4.6 Lift
The term “lift” means the distance between upper and lower limit that the crane can lift and lower the hook, grab
bucket or any other hoisting accessory normally.
9 (EN)
4.7 Operating Radius
The “operating radius” means the horizontal distance between the center of rotation of a jib crane and the center
of its hoisting accessory. The operating radius is also known as the “slewing radius”, of which the largest limit is
called the “maximum operating (or slewing) radius” and the smallest limit is called the “minimum operating (or
slewing) radius”. (See Table 1-2: p.9)
Center of rotation
Maximum operating radius
10 (EN)
4.10 Liftoff
This means the motion of lifting the load slightly away from the ground, floor, and/or bearer blocks. For the
slinging work, inching up the load slowly, stop once the load has been lifted off, and confirm the stability of the
load and the safety of the sling gear.
Lifting
4.11 Grounding
This means the motion to lower the load to the intended location. For the slinging work, check the conditions of
the landing location and set up the bearer blocks for the load to stabilize. Inching down the load, then stop it
once when the load is landed. After confirming the stability of the load, fully lower the load, remove the sling
gears.
Lowering
11 (EN)
Chapter 2
Knowledge of Dynamics Necessary for
Slinging Crane Loads
Fig. 2-1 b explains the method of finding a resultant force. The resultant of the forces F1 and F2, which work on
the point O from two different directions, can be determined by drawing a parallelogram (OADB) with these
forces on its two sides. The diagonal R in the figure represents the magnitude and direction of the resultant
force to be determined. This is called the parallelogram law.
12 (EN)
The “decomposition of force” is the process of dividing a force working on an object into two or more forces at
an angle to one another. Each of the portions into which a force is thus divided is called a “component” or a
“component force” of the original force. To find a component of a force, the parallelogram of forces described in
the “composition of forces” is used in reverse sequence to divide the force into two or more forces at an angle to
one another.
Let us look at a man dragging a sled as shown in Fig. 2-2 a by way of example. Since he pulls the rope forward
at an angle to the ground, i.e., somewhat upward, the sled is hauled horizontally (longitudinally) but, at the same
time, vertically. So we have to find the magnitude of the force that actually draws the sled horizontally.
Force F Force F
O
O
As shown in Fig. 2-2 b, the force F (OA) is divided into F1 (OB) and F2 (OC) using by the parallelogram law.
This is the decomposition of force and it can be found that the horizontal force of the sled becomes F1 (OB).
13 (EN)
1.3 Moment of Force (p.38)
The moment of a force is the work of the force to turn an object.
In turning a nut with a spanner wrench as in Fig. 2-3, a smaller force is required when you hold the wrench near
the end of the shaft than when yon hold it in the middle of the shaft. This example indicates that the turning work
of force is related not only to the magnitude of the force but also to the distance between the center of the axis
of rotation and the line of action of the force (i.e., the length from the axis of rotation O to the F1 or F). This
distance (L1 or L in Fig. 2-3) is called the “length of arm”.
In lifting a heavy load with a lever as shown in Fig. 2-4, the nearer the grip is to the fulcrum, the greater the
required force becomes.
Fulcrum
With the magnitude of a force given as F and the length of arm given as L, the moment of the force M can be
written as M = F x L. Where the magnitude of the force F is stated in N (newton) and the length of arm L in m
(meter), then the moment of the force M can be represented in N·m (newton meter).
14 (EN)
If this is applied to the lifting of a load by a jib crane, as described in Fig. 2-5, the moment working to make the
crane fall when the jib carrying the load (m) to the position A differs from when the jib comes further to the
position B. The lengths of arms from the fulcrum O (or the axis of rotation) at the jib positions A and B are given
as L1 and L2, respectively, in the diagram. Accordingly, each moment (M1 and M2) can be written as follows:
By comparing these two lengths, you can find L1 < L2, and therefore, the moment M1 is smaller than the
moment M2.
Usually moment works to turn an object either clockwise or counterclockwise. To find the sum or equilibrium of
two or more moments, therefore, you have to take into account the rotational direction of each of them.
15 (EN)
1.4 Equilibrium of Forces (p.40)
Center of rotation
In this diagram, let us examine the moments of forces with the worker’s shoulder as the axis of rotation. With the
weights of the two loads given as m1 and m2 and with the load-supporting places on the pole (horizontal
distances between the loads and the shoulder) given as L1 and L2
The moments around the axis of rotation are kept in equilibrium as below:
9.8 x m1 x L1 = 9.8 x m2 x L2 (1)
m1 x L1 = m2 x L2 (2)
m1 x L1 = m2 x (L - L1) (3)
m1 x L1 = m2 x L - m2 x L1 (4)
m1 x L1 + m2 x L1 = m2 x L (5)
Needless to say, the worker’s shoulder serves as the axis of rotation that supports the weight of the loads (m1 +
m2).
Accordingly, the loads will be equilibrated if the pole is held at the point determined by internally dividing the pole
in inverse proportion to the weights of the loads m1 and m2.
16 (EN)
2 Weight and Center of Gravity (p.43)
Table 2-1 shows approximate weight in tons (t) of different materials per cubic meter (m3). Based on this table,
you can find the weight of a specific material body if its volume (in cubic meters) is known.
The weight of a load to be lifted (W in tons), for instance, can be found by multiplying the volume of the load (V
in cubic meters) by the numerical value in the table indicating the weight of its material per cubic meter (d in
tons):
17 (EN)
Simple equations for calculation of volume are shown in Table 2-2.
(D)2 x H x 0.8
Sphere
(D)3 x 0.53
Circular corn
(D)2 x H x 0.3
18 (EN)
[Exercise]
Calculate the weight of steel plate (thickness: 0.05 m, width: 1.5 m, length: 3.0 m)
[Answer]
Specific gravity = Weight of a material body / Weight of an equal volume of pure water at 4°C
19 (EN)
How to Find COG
The COG of a material body can be found based on the phenomenon that when the body is suspended with a
string, the line of action of force passing through the COG becomes perpendicular, resulting in the location of
the COG right under the spot of the body by which it is suspended. More specifically, you can determine the
COG by suspending the material body by two different spots on it and finding the point at which the lines of
action of force supporting the body in the two instances crosses each other. (Fig. 2-19: p.46)
If, for instance, an object sitting on a level surface is tilted as in Fig. 2-8 (a) and then let go, it returns to its
original position. This is because the gravity acting on the COG G generates the moment of a force which, with
the center of rotation O as a fulcrum, works to right the tilted object. However, if the object is tilted so far that the
perpendicular passing through its COG comes outside its base as shown in Fig. 2-8 (b), it falls on its side
instead of returning to its original position.
Accordingly, the diagram (a) is in a stable state, and (b) in an unstable state.
20 (EN)
An important consideration in setting an object in a stable state is to let it have a greater base area and a lower
COG.
3 Motion (p.48)
If an object in uniform motion moves 50 meters in 10 seconds, its speed can be expressed as 5 m/s. The speed
of an object in uniform motion is expressed by the result of dividing the distance the object has moved in a
certain period of time by the required number of unit lengths of time, as written below:
Distance (L)
Velocity (v) =
Time (t)
Among commonly used units of speed are meters per second (m/s), meters per minute (m/min) and kilometers
per hour (km/h).
In determining the motion of an object, however, it is hardly sufficient to think of its speed alone. We have to find
the direction of its motion as well, and the term “velocity” is often used as a quantity indicating both the direction
and speed of motion.
21 (EN)
3.2 Inertia (p.50)
A material body has a tendency to remain at rest if at rest, or, if moving, to continue moving in the same
direction, forever in either case, unless it is affected by some external force. This tendency is known as “inertia”,
and the force that works on a material body because of inertia is called the “force of inertia”.
The force which thus sets an object in circular motion is called “centripetal force”. In this connection, a force that
is equal in magnitude but opposite in direction to centripetal force is called “centrifugal force”. (See Fig. 2-11.)
Centrifugal force
Centrifugal force
Centripetal force
Centripetal force
Center
Tangential direction
Tangential direction
22 (EN)
As shown in Fig. 2-12, the faster the lifted load turns, the greater the centrifugal force becomes, resulting in the
movement of the load further outward. Compared with the situation where the lifted load is at rest, this condition
increases the moment of a force that works to make the jib crane fail. Under some extreme conditions, it is not
unlikely that the crane will fall actually.
Fig. 2-12 Outward Movement of Lifted Load and Changes in Operating Radius due to Centrifugal Force
23 (EN)
4 Pulley Blocks (p.53)
“Pulley block” is a general term for assemblies consisting of a combination of sheaves. These assemblies can
be divided into the following categories:
Pull 1 m
It will rise 1 m
24 (EN)
4.2 Movable Pulley (p.54)
This is the same type of pulley as those used for the hook blocks of cranes. As shown in Fig. 2-14, a movable
pulley is operated by moving up and down one end (A in the diagram) of the rope that runs on its wheel or
wheels, with the other end fixed. The pulley itself moves up and down carrying a load, according to the vertical
motion of the rope end A. You can lift a load by this device with a force equivalent to half the weight of the load
(assuming that the pulley is free from any friction), but when the rope is pulled 2 meter, for example, the load
moves up only 1 meter - half the length by which the rope is pulled. In other words, the pulley requires a smaller
input force to lift a given weight of load but so much greater length of rope has to be pulled.
Meanwhile, the direction of inputted force remains unchanged as the rope is pulled up whenever a load is to be
lifted.
25 (EN)
4.3 Combination Pulley (p.55)
A combination pulley block, made by combining several movable and stationary pulleys, can lift or lower a very
heavy load with a relatively small force. A combination of three movable pulleys and three stationary ones, as
described in Fig. 2-15, is capable of lifting a load with a force equivalent to only one sixth of the weight of the
load, assuming that the pulley system is free from any friction. However, it can lift a load only one sixth of a
meter for every one-meter length of the rope pulled. This means that the velocity of a lifting or lowering load is
also one sixth of that of the inputted force.
1 1
F= x Fw Vm = xv L= 2xnxL
2xn 2xn
F: Force to pull rope Vm: Winding speed L: Winding length
Fw: Weight of load v: Lifting speed of load Lm: Lifting distance of load
26 (EN)
5 Load, Stress, Strength of Materials (p.56)
Tensile load pulls a rod by the force F that works on the longitudinal axis of the rod. A typical example of it can
be found in the load on a wire rope by which cargo is being lifted.
Compressive Load
Compressive load works in a direction opposite to tensile load, as indicated in Fig. 2-18, to compress the rod
longitudinally with the force F. You can find a typical example of it in the force working on the ram of a jack.
27 (EN)
Shearing Load
A reamer bolt may, when exposed to the force F as described in Fig. 2-19, be cut along a sectional plane
parallel to the direction of F if this force is very strong. Such action of force is called “shearing load”.
Bending Load
A beam supported at both ends may bend if the force F perpendicular to its longitudinal axis works on it as
shown in Fig. 2-20. This action of force is known as “bending load”. An example of it can be found in the weight
of a load or the trolley working on the girder of an overhead traveling crane.
Twisting Load
A shaft may be twisted if one end of it is fixed and the other is exposed to the force F working in two opposite
directions on its circumference, as described in Fig. 2-21. Such work of force is called “twisting load”. You can
find an example of this load in the instance where the shaft of a winch is pulled and twisted by the wire rope.
28 (EN)
Compound Load
Mechanical components of a crane are affected more often by a combination of the loads described above
rather than by their individual actions. For instance, the wire rope and hook are both subject to a combined
action of tensile and bending loads, while power unit shafts in general are subject to a combination of bending
and twisting loads.
Static load means a fixed or standing load that has invariable magnitude and direction of force like the dead
weight of crane structure.
Dynamic Load
Dynamic load, which is variable in magnitude, is classed under two categories. One is repeated load that
continually varies with time, and the other is impact load that suddenly applies force to an object for a very short
period of time.
Repeated load can be further divided into single-acting load and double-acting load, of which the former always
works in the same direction but varies in magnitude with time like the load on such crane components as the
wire rope and winch bearings, while the latter varies with time both in direction and magnitude like the load on
gear shafts.
Machines or structures may break under any of these dynamic loads even if its magnitude is far smaller than
static load. This phenomenon is called “fatigue fracture” which, arising from the fatigue of materials, accounts for
a substantial percentage of fractures that occur actually.
Dynamic load
Other Classifications
Load can also be classified, according to the state of its distribution, into concentrated and distributed loads of
which the former focuses on a single spot or a very small area while the latter works on a wide area.
29 (EN)
5.2 Stress (p.58)
Any object, when under load, generates a force in it (internal force) that works to resist and counterbalance the
applied load as shown in Fig. 2-23. This internal force is called “stress”, whose intensity is represented by the
magnitude of force per unit area.
Stress
Stress can be divided into tensile, compressive and shearing stresses, of which the first occurs under tensile
load, the second under compressive load and the third under shearing load. With the sectional area of the
structural member under load given as A and the tensile load working on the member given as F kg, the tensile
stress can be written as:
Tensile load applied to the structural member (N) F
Tensile stress = = (N/mm2)
Sectional area of the structural member (mm2) A
30 (EN)
6 Strength of Wire Rope, Chain and Other Sling Gear (p.60)
Wire ropes, chains or other sling gear may differ in strength, depending on their materials, even if they are in the
same size and shape. These articles are also subject to a much greater force than the weight of the lifted load
itself because such weight dynamically works on them.
Taking these factors into account, steps are taken generally to set a reference standard below the load at which
the selected sling gear, such as wire rope or chain, may break. Then an arrangement is made to avoid using the
sling gear above the reference load and to provide an effective means of directly comparing the reference load
with the actual load to be born by the sling gear, so that lifting work can be carried out safely and smoothly.
6.1 Safety Factor and Safe Load of Wire Rope, Chain (p.60)
Breaking Load
The breaking load is the maximum load at which single wire rope breaks. (Unit: kN)
Safety Factor
The ratio of the breaking load of the wire ropes and chains to the maximum load applied to them is called the
“safety factor”.
The safety factor is defined taking the type, shape, material and using method of the sling gear into
consideration. The safety factor for sling gears are stipulated as follows in the Safety Ordinance for Cranes.
Standard Safe Load (t) = Breaking load (kN) / (9.8 x Safety Factor)
31 (EN)
Safe Load
The safe load (or working load) is the maximum load (t) that can be lifted vertically using a wire rope or chain,
according to the number of ropes and sling angle. Some sling gears indicates the safe load as a rated load or
working load.
Diagonal
32 (EN)
When the load is lifted using two wire ropes as shown in Fig. 2-25, the force to support the weight m of the load
is the resultant force (F) of the tensions (F1, F2), which are each larger than the value of F/2. For a load of a
given weight, the tensions F1 and F2 increase when the sling angle is increased.
In addition, the horizontal component P of the tensions F1 and F2 also increases with the sling angle. This
horizontal component P acts as a compressive force on the load, and it pulls the sling wire ropes inward. Careful
attention is therefore required when the sling angle is large.
Sling angle
Sling wire rope
33 (EN)
Tension Factor
Tension factor is the value to calculate the load (tension) applied to single wire rope for each sling angle. The
load (tension) to the single wire rope can be calculated by finding tension factor and number of ropes even the
number of the ropes are changed. For the relation between the sling angle of the wire rope and tension, refer to
the textbook (Table 2-4: p.63).
Fig. 2-26 show the relationship between the sling angle and the tension of wire ropes, indicating that as the sling
angle increases, thicker wire ropes have to be used even if the weight of the load remains unchanged, since the
tension applies to the wire rope increases.
Mode Factor
The ratio of the safe load of the wire ropes to the standard safe load at a certain number of ropes and sling
angle is called the “mode factor”. (See Table 2-5: p.61.)
This value varies depending on the actual sling angle, however, the sling angles are classified into certain
ranges, and a certain value is shared in each range for practical use.
34 (EN)
6.2 Calculation for Selecting Sling Wire Ropes (p.64)
To calculate the safe load for selecting the sling wire rope, tension and mode factors are used.
Standard safe load required for single wire rope = (Weight of Load / Number of ropes ) x Tension Factor
Sling angle: 40 °
Weight: 8 t
35 (EN)
Chapter 3
How to Select and Handle Sling Gear
Wire ropes, chains, belt slings, hooks, and shackles are used as sling gears for slinging with the crane,
depending on the weight and shapes of the load. The safety factor for these sling gears are stipulated as follows
in the Safety Ordinance for Cranes (Article 213 and 214).
● Wire sling chain: 5 or more, or 4 or more when certain conditions are met
Clamps and hackers are also used, and the use of fiber ropes such as belt slings and round slings has also
become more common. Although the safety factors for these items are not stipulated in the regulations, the
Japan Crane Association Standard has specified the safety factors indicated below.
Core
Strand
Wire
36 (EN)
The material at the center of the wire rope is called the “core”, and it works to keep the rope shape, provide the
flexibility, and absorbs the shocks and vibration to prevent the stands from breaking. The core is made of fabric
fiber or wire. For slinging purposes, six-strand wire ropes are used widely. (See Table 3-1: P.68).
The wire rope filled with the wires (filler wires) inside the strand is called “filler type”.
The construction of wire rope is usually indicated by a structural code (the number of strands x the number of
wires contained in each strand), such as 6 x 24 or 6 x 37.
Among different wire ropes of a given diametric size, those made with a larger number of smaller wires in
general have greater flexibility, and those prepared with a core at the center of each strand in particular are still
more flexible and easier to handle.
Types of Lays
Fig. 3-2 shows types of lays used for wire ropes. The “ordinary lay” has the twist of wire rope and that of strands
in opposite directions, while the “lang lay” has the twist of rope and strands in the same direction. Each of these
lays is further divided into right and left-hand lays (Z and S). Compared with a lang-lay product, an ordinary-lay
wire rope wears away sooner but is easier to handle because it is less liable to untwist or kink. For slinging,
ordinary-lay Z (right-hand) wire ropes are used widely.
37 (EN)
Wire Rope Diameter
The diametric size of wire rope is represented by the diameter of a circle circumscribing its cross section. It is
determined by measuring the diameter of wire rope with slide calipers in three directions at a given cross section
as described in Fig. 3-3 and then averaging the measured results. The tolerance against the nominal diameter
determined at the time of production must be 0 to +7 percent (note that for the wire rope below 10 mm diameter
is 0 to +10 percent).
Diameter
Wrong Correct
Safe Load
The safe load is the maximum load (t) that can be lifted according to the number of ropes and sling angle.
The safe load can be calculated by using the tension and mode factors and the table of safe load.
When the safe load table for the sling gear to be used is available, refer to the table to find the safe load. (Table
3-7 (a) - (d): p.75 - p.78) For example, the sale load can be calculated easily by finding the single angle and
number of ropes when the type of the wire rope is specified.
For the technical terms related to the load of the wire rope, see Chapter 2: Strength of Wire Rope, Chain and
Other Sling Gear.
38 (EN)
Tension Factor
Tension factor is the value to calculate the load (tension) applied to single wire rope for each sling angle.
Mode factor
The ratio of the safe load of the sling gear to the standard safe load at a certain number of ropes and sling angle
is called the “mode factor”. (See Table 3-3, p.72.)
For the breaking load for G and A grade wire ropes of 6 x 24 and 6 x 37, which are most widely used for
slinging, refer to the textbook. (Table 3-5: p.73)
The approximate standard safe load for a 6×24 wire rope can be calculated using the following equation:
39 (EN)
Standard Safe Load for Sling Wire Ropes by Number of Ropes and Sling
Angle
Sate Load for Two-rope Slinging with Two-point
For the safe load of wire ropes of 6 x 24 and 6 x 37 in each nominal diameter, refer to the textbook. (Table 3-7
(a): p.75, Table 3-7 (b): p.76, Table 3-7 (c): p.77, Table 3-7 (d): p.78)
Sling angle
When the load is applied evenly to all three sling wire ropes as shown in Fig. 3-5, the sling angle is twice as
large as a/2, and the safe load is 1.5 times the value that was determined from (Table 3-7), which shows the
safe loads for two-rope slinging with two points.
40 (EN)
Safe Load for Four-rope Slinging with Four-point
For four-rope slinging with four points, the safe load is twice as large as that for two-rope slinging with two
points. Therefore, the safe load is twice as large as that of the corresponding loads shown in (Table 3-7). If it is
difficult to apply the load evenly to four ropes due to slight variations in the shape of the load or the lengths of
the sling wire ropes, it is safer to calculate the safe load based on the mode factor for three-rope slinging.
al
Diagon
Since the safe load decreases according to the ratio (D/d) of the diameter D of gear such as hooks and
shackles, to the diameter d of the wire rope, the diameters must be taken into consideration when selecting the
equipment to use for the work.
(Reference)
(%)
D/d
1 5 10 20
Construction of rope
6 x 24 50 30 25 10
6 x 37 45 22 10 5
6 x Fi (25), Fi (29) 45 25 15 4
Example of Decreased Strength of Wire Rope due to Bending (Japan Wire Products Association)
41 (EN)
1.3 Finishes of Rope Ends (p.83)
It is required that wire ropes used as sling gear be endless or provided with hooks, shackles, rings or eyes at
both ends. Fig. 3-7 shows wire ropes generally used for slinging.
Eye splices at both ends Compression joint with thimble and shackle at each end
Compression joints at both ends Compression joint with thimble and hook at each end
“Makisashi” (winding insertion) is easier to make than “kagosashi” (split insertion), but when used in a situation
where the load works to turn the wire rope, this splice may untwist and come loose.
Eye splicing is performed by hand, so the strength may vary depending on the splicing skill level. While sling
wire rope is supplied for load-lifting purposes, anchoring wire is provided to fasten things to stationary matters.
(Fig. 3-14: p.84)
42 (EN)
Compression Joint
Compression jointing, also called “locking,” is a method of forming a wire rope end into a ring by fitting and
compressing a special metallic piece at the neck of the eye. But care should be taken to use compression-
jointed wire ropes supplied by a reliable special factory because the quality of these products varies, depending
on the method of processing. Compression-jointed sling wire ropes have a disadvantage in that while the wire
rope is being pulled out from under a load, its end may get caught by the load.
To use the sling wire rope safely, careful attention should be paid to the following precautions.
● Ensure that all loads will be lifted at a proper sling angle and with a safety factor of 6 or more.
● Do not use any rope that has worn away or has a kink or any other damage.
● Preferably, use plated wire ropes (G grade) if the job site is located in a coastal area or any other place
where damage from salt is likely to occur.
● Avoid single-rope slinging wherever possible. The turning of the load may untwist the wire rope, and the
load may fall off. (See p.135)
● When storing wire ropes, group them by category of uses and keep them in order at a well-ventilated place
free from high humidity, heat, dust, acid and other undesirable elements.
● Do not bend or fasten the endless wire rope at the joint part.
● Do not soak the wire rope with aluminum alloy into sea water.
● (If it is used for a long time, aluminum alloy may be damaged and the tightening force may decrease.)
● Do not let the opening angle of the eye part of the sling wire rope with compression joint exceed 60
degrees.
43 (EN)
Sling angle
Humidity
Heat
Acid
Dust
Single-rope slinging
Precautions for storage
44 (EN)
2 Chain (p.87)
Chain is often used for slinging high-temperature goods or some other special jobs because of its desirable
qualities, specifically greater resistance to heat, corrosion and deformation, compared with wire rope.
The size of chain is represented by the diameter of the component round steel bar (mm), which is called the
“nominal diameter” of chain. There is a wide variety of chains but the most widely used of them is link chain, and
sometimes stud-link chain is used for slinging heavy loads.
Link chain
Nominal diameter
Stud-link chain
Nominal diameter
Usually chain sling is comprised of chain with hooks, rings or some other pieces of metal attached to both ends
as described in Fig. 3-11.
Ring
45 (EN)
Precautions for usage
To use the chain safely, careful attention should be paid to the following precautions.
● Choose those sling chains for which the working load is known. (Working load tag is attached to the ring
part for some products.)
● Ensure that all sling chains will be used at a proper sling angle with a safety factor of 5 or more.
● Take care not to let any sling chain fall from an elevated place.
● Do not thrust the end of a hook, pin or any other article into a link in the chain to reduce its length.
● When using sling chains in a cold place, take great care to avoid giving them any shock.
● Do not use any scaffolding chain for slinging loads to be lifted. (Fig. 3-20: p.89)
For the maximum working load for each type, refer to the textbook. (Table 3-11: p.92, Table 3-12: p.92)
46 (EN)
Precautions for usage
To use the belt sling safely, careful attention should be paid to the following precautions. (Fig 3-22: p.93)
● Select and use the applicable belt for its purpose. Avoid using the one made of polypropylene outdoor.
When using new chemical materials or unknown solvent, consult the manufacturer.
● When using the belt out of the temperature range (between -30 °C and 50 °C), check the working load with
the manufacturer. Do not use it in temperatures that exceeds 100 °C.
● Be sure to put pads on the edges of the angular load to protect the load and the belt sling and also to
prevent sideway slipping.
● When a choke hitch is used, sling the load tight noosing of the belt sling.
● The crane operator must not leave the operating position while the load is lifted.
● Do not use the belt if it is twisted excessively, or tied or pulled each other.
● When pulling out the belt sling under the load, be careful not to damage it.
● Do not drag the belt on the ground or floor. Do not let the belt sling fall with the metal fittings from a high
place.
● Do not leave the belt under the load (for a long time).
● When using the belt with other sling gears or hoisting accessory, care should be taken not to damage it at
the connecting part.
● Keep the belt away from heat, chemicals and direct sunlight.
● For the belt sling used for the chemical products, wash it thoroughly before storage.
● If the belt becomes dirty due to attachment of oil or dust, wash it with neutral detergent before storage.
● If the belt sling or metal fittings are decided to be discarded after inspection, do not repair for reuse.
● When using the belt sling in uncommon situation, consult the manufacturer.
For the working load and slinging method of grade III products, refer to the textbook. (Table 3-13: p.94, Table
3-14: p.94) To secure safety, using it with the sling angle less than 60 degrees is recommended.
47 (EN)
3.2 Round Sling (p.95)
Round slings consist of a core material made of twisted strands of synthetic fiber yarn, covered by an outer
layer of surface cloth. The safety factor is the same as that of belt slings.
The JIS B 8811 standard defines the color codes used for the surface cloth to indicate the maximum working
load, as shown in the table below. However, some products may use different color codes due to agreements
between companies.
Maximum working load (t) 0.5 1.0 1.6 2.0 3.2 5.0 8.0
Color of surface cloth Gray Purple Blue Green Yellow Red Dark blue
Although the precautions for using round slings are mostly the same as those for belt slings, pay particular
attention to the points below.
● Round slings for general use must not be used with chemicals or when heat resistance is required.
● When you perform inspection and find slight damage only to the surface cloth, ask the manufacturer to
perform repairs.
48 (EN)
4 Other Sling Gear (p.97)
Ring Ring
Locking device
Locking device
Cam
Jaw
Jaw Cam
Vertical Horizontal
49 (EN)
Precautions for usage
To use the clamp safely, careful attention should be paid to the following precautions.
● Use the vertical or horizontal clamp according to the type of work. (Multiple type clamp for vertical and
horizontal slinging is also available.)
● Be sure to use the clamps within the specified working load (minimum and maximum) and plate thickness.
● Ensure that the sling angle is 60 degrees or less, and that the angle between adjacent slings is 30 degrees
or less. (Fig 3-27)
● Avoid one-point slinging as the clamp may come off due to the load swing, even it is slung at the COG.
● When installing the clamp to the load, be sure to insert it to the end of the opening, and apply the safety
lock.
● If the installation part of the load is slanted, consult the manufacturer before use.
● When the cam and jaws are clogged, be sure to remove them before use.
● Do not use the worn cams and jaws (according to manufacturer standards).
● Before slinging a load, be sure to completely remove oil, coating, rust or scales, if any, from its surfaces.
● Do not lift loads with two or more stacked or a load with pads applied.
● Be sure to use a shackle instead of inserting a wire rope directly into the ring.
50 (EN)
Clearance
Clearance
Slips
Impact
Attachment of oil
51 (EN)
4.2 Hackers (p.99)
Hacker is the sling gear that has one or two claws on its end to hold the products such as steel plates, shaped
steels, or pipes for conveyance.
Sling angle
Angle between
Draw-stringer slinging adjacent slings
52 (EN)
Do not use hackers when lifting stacked Do not use only one of two claws.
items with different dimensions.
● Select hackers that are appropriate for the shape, weight, and thickness of the load. (Fig. 3-30)
● Do not use hackers when lifting stacked items with different dimensions.
● Ensure that the sling angle is 60 degrees or less, and that the angle between adjacent slings is 30 degrees
or less.
● Find the COG of the load correctly, and use 2 or more hackers to hold the COG securely.
● Do not use the hackers to sling high-temperature objects of 150 °C or higher, or at the cold district where
ambient temperature is lower than - 15 °C. (Japan Crane Association Standard Inspection Manual for
hackers)
53 (EN)
4.3 Others (p.101)
In addition to those described above, the following devices are used for slinging.
Shackles
Shackles used for slinging comprise bow and straight shackles which are further subdivided by type of bolt or
pin.
The grade of shackle is classified into M, S, T or V, depending on the pulling strength of the material used. (Fig.
3-32: p.101, Fig. 3-33, Table 3-17: p.102)
To use the shackle safely, careful attention should be paid to the following precautions.
● Select the proper shackles according to the specified working load and usage.
● When using the screw-type shackle, connect the shackle bolt to the eyes of the sling wire rope as shown in
Fig. 3-20.
● Do not put the wire rope through the bolt side of the shackle as in Fig. 3-21. The bolt may rotate.
54 (EN)
Eyebolts and Eyenuts
Eyebolts and nuts are bolts and nuts with rings as shown in Fig. 3-22 and Fig. 3-23. Attach them to the
machinery or its components in advance so that they can be easily slung when lifting.
To use the eyebolt and eyenut safely, careful attention should be paid to the following precautions.
● Select the appropriate eyebolts and eyenuts according to the type of the load.
● Avoid exposing eyebolts to a lateral force, which reduces their strength very significantly.
● Make sure that the seating surfaces are in close contact. If the eye orientation does not match due to close
contact, use the washer to adjust.
55 (EN)
Lifting Beam
The lifting beam is used to lift a long object, or to lift a wire rope vertically so as not to damage the load.(Fig.3-
39: p.104)
To use the lifting beam safely, careful attention should be paid to the following precautions.
● Select the appropriate lifting beam according to the type of the load.
● For multipurpose lifting beams, check the slinging points and loading conditions beforehand.
● When using a lifting beam for multipoint slinging, which involves uneven distribution of load among the
slinging points, take into account such unevenly distributed load.
56 (EN)
4.4 Sling Accessories (p.105)
In slinging goods for conveyance by crane, such sling accessories as pads and bearer blocks are used to
protect the sling gear or the goods to be lifted or to make the slinging work easier.
Pad
When an angular or fragile product is to be lifted, pads are used to protect the wire rope or the load from being
damaged.
57 (EN)
Bearer Blocks
Bearer blocks are used to protect the wire rope and load as well as to ensure that slinging work will be carried
out efficiently and safely. Take care not to get your foot jammed under the load.
To use the bearer blocks safely, careful attention should be paid to the following precautions.
● Use blocks of equal size. If blocks with different height are used, the load becomes unstable.
● Hold a block from two sides with both hands. Do not put your hand on its top.
● When adjusting the position of the bearer blocks under the load, be sure to hold the left and right side of the
block.
Use blocks of equal Hold a block from two Hold the left and right side of
size. sides with both hands. the block.
The load becomes unstable. Do not put your hand on its top.
58 (EN)
5 Checkups on Sling Gear (p.106)
Sling gear must be checked regularly and as necessary to keep it in good working order. Failure to carry out
these checkups would lead to a serious accident. Before they are used for the day’s work, all articles of sling
gear have to be checked carefully to make sure that they are in order. In addition to daily routine checkups,
these articles have to be inspected periodically, e.g., once a week or a few times a month, depending on their
operating conditions, because their service life is affected by such factors as how often they are used daily and
how heavy a load is carried at each lifting. Also when they are resuming their service after being stored for a
long time, they have to be examined very carefully.
The Safety Ordinance for Cranes defines the standards for prohibiting the use of inadequate sling gear. For
details on factors such as the amount of wear or deformation, refer to “Guidelines for Periodical Self-Inspection
of Overhead Traveling Cranes”.
In addition, for items that are not stipulated in the regulations, follow the standards that are specified in the
instruction manual provided by the manufacturer. If any irregularity is found with sling gear by a checkup, which
must cover breaks, deformation and other damage, the affected sling gear has to be immediately repaired or
removed from service. What is important here is that necessary measures be taken to preclude retired sling
gear from being ever used again.
● Kinks deformation
● Corrosion
59 (EN)
Standards for Determining Unacceptable Wire Ropes
● Wire ropes of which more than 10 percent of the total number of wires (excluding filler wires) contained in
any one twist are broken.
Strand number
● Eye part of which more than 5 percent of the total number of wires (excluding filler wires) contained in any
one twist are broken. (Reference: Guideline related to Safety of Slinging Operation)
● Those which has decreased in diameter by more than 7 percent of the nominal diameter.
● Those which have any kink. (Do not repair to use it again.)
Positive kink
Negative kink
● Those which have any irregularity at either of the finished ends or compression joint. (The braided part of
eye splice or the metal sleeve of the compression joint.)
These are the criteria set under the applicable legislation for determining the wire ropes to be discarded as
such. It is desirable that wire ropes with broken wires or an appreciable decrease in diameter be replaced with
new ones sooner before they reach the criteria specified above. A wire rope affected by a combination of any
two or more of such troubles as deformation, wear and tear, and broken wires may have to be removed from
service when the combined total damage from these causes reaches a certain level even if their individual
damage is below the replacement criteria.
60 (EN)
5.2 Chain
● Wear
● Cracks
● Those which have any link whose sectional diameter has decreased by more than 10 percent of the original
size as determined immediately after they come off the production line.
● Those which have any defect or irregularity in the welded or forge-welded parts or are deformed
appreciably.
Dent Bend
Twist
L (5 links)
61 (EN)
The elongation of links is found by measuring the length of five links in the most severely elongated part of the
chain in service and then calculating the difference between this length and the original length of any five links in
the chain determined at the time of production, which serves as a reference standard or standard length. See
Fig. 3-30. Since this process involves measuring the dimensions of a new chain and comparing them with those
determined later while the chain is in service, arrangements should be made to keep the measurements of
every new chain recorded in a ledger.
Belt Sling
Inspection Points
● Damaged condition: Wear (fuzz), scratches, broken thread of sewn part, peeled surface
Peeling off at sewn part Peeling off at body part Broken thread at eye part
Fig. 3-32 Fuzz at body part Fig. 3-33 Damage on the end loop
62 (EN)
Standards for Determining Unacceptable Fiber Rope and Belt
● When the texture of the sling cannot be recognized due to fuzz, and the sewing thread is damaged or
broken. When the sewing thread is peeled away longer than the width.
● Those which have cuts or scratches equivalent to 1/10 of the width in the width direction or 1/5 of the
thickness in the thickness direction.
● When the sewing part and body part are peeled away.
● Those which have the use limit indication, and the use limit is exceeded.
● Those which have significant discoloration, coloring, melting, or dissolution due to heat or chemicals.
● Those which have cracks, bends, twists, distortion, and scratches on the metal fittings.
● When there is noticeable wear on the metal fitting. (the amount of wear exceeds 10% of the original size)
● When there is corrosion on the entire metal fitting, or there is significant corrosion on the part of the metal
fitting.
● When the service life is exceeded (Reference: 7 years indoors, 3 years outdoors)
63 (EN)
Round Sling
Inspection Points
● When the surface cloth is broken and the core can be seen
● When the thread at the joint part is frayed and the core can be seen
● When excessive fuzz, discoloration, dissolution, melting, corrosion is caused by friction, heat or chemical
products.
● When the service life is exceeded (Reference: 7 years indoors, 3 years outdoors)
Fig. 3-34 Damage on surface cloth Fig. 3-35 Damage on the thread
64 (EN)
5.4 Other Sling Gears (p.112)
● Worn state
● Cracks
● Damage
● Elongation, deformation
● Those which have noticeable wear (the amount of wear exceeds 5% of the original size).
Fig. 3-38 Opening and wear of hooks Fig. 3-39 Wear of shackles
65 (EN)
Clamp
Inspection Points before Work
● Those which have bends, hole deformation and cracks on the ring.
● When there are wear, bends and cracks on the pins in each part.
● Those which have bends, hole deformation and cracks on the link.
● Those which have an arc strike (arc welding mark during arc welding).
The clamp has many moving parts, and daily maintenance is required.
● Remove a paint residue and sludge from the moving parts, and lubricate the sliding parts.
● Remove a paint residue and sludge from the cams and jaws.
● Wipe off oil adhering to the teeth of the cams and jaws.
66 (EN)
Hacker
Inspection Points
● Elongation
● Wear
● Deformation
● Cracks
● Damage
● Arc strike
● Those which have elongation, wear, or deformation exceeding the specified value of the manufacturer.
● Those which have scratches, drooping, or damage exceeding the specified value of the manufacturer.
67 (EN)
Chapter 4
Slinging and Signaling Methods
● Preparation
Item Key points Notes
1 Confirm the rated load of Select the crane sufficient in performance. When using the crane with jib,
the crane check the rated load curve and
rated total load table.
2 Find the shape, size, Check the descriptions on the invoice or such. If it is not clear, check, find or
material, and weight of the calculate it.
load as accurately as
possible
3 Determine the location of Take note that COG locates as a point. Determine the location of the
the COG COG correctly. (See p.151)
4 Select the slinging method Decide the number of ropes, slinging method, slinging
positions.
5 Select the sling gears Determine the required number, diametrical size and (See p.123)
length of sling gears according to the shape, weigh, and
slinging method of the load.
6 Check the sling gears Check for any damage, deformation, twist or wear. Taking care to avoid getting
your hand or fingers hurt.
7 Check the unloading area ● Check that unloading area is large and hard Secure the area where workers
enough and not slanted. can evacuate.
● Check that the bearer blocks are ready.
68 (EN)
● Lifting
Item Key points Notes
1 Call for the crane ● Call the operator and indicate the loading ● Use a whistle as well.
place.
● When using wireless devices,
● Take your position at a place within full view of
the crane operator. check that it works properly.
2 Guide the hook ● Indicate the load to be lifted. Be sure to keep the hook at proper
● Move the hook above the load. height.
3 Signal for lowering Signal to lower the hook after it stops right above Make sure that the hook will not hit
the load. slingers on the head.
4 Signal for stopping Hold the hook right above the COG of load where If the load is large, stop the hook at
slinging can be done easily. the position where the slinging can be
done easily.
5 Sling the load ● Take the COG location into account. ● Taking care to avoid getting your
fingers caught.
● Avoid the collapse of the load.
● Watch your footing.
● Pad the edges of an angular load.
● Ensure to preclude the sling wire ropes from
slipping.
6 Secure the sling wire ● Take care to avoid twisting the sling wire Secure the wire ropes on the hook in
ropes to the hook ropes. the proper order.
● Make sure the eyes of the wire ropes will not See Chapter 5: Practical Slinging
cross each other. Methods.
● Put the wire ropes parallel to one another at
the center of the hook.
69 (EN)
Item Key points Notes
7 Signal for inching up ● Check the worker’s position carefully. Taking care to avoid getting your
● Take your position at a place within full view of hand or foot caught.
the crane operator.
● Inching up the load to prevent the wire ropes
from slipping.
● Make sure that the COG of the load, hook and
sling wire ropes are in vertical.
8 Signal to stop the crane ● Check the hoisting wire rope is taut, and the Check from all the directions.
sling wire ropes are taut evenly before lifting
off the bearer blocks.
● Check the sling angle.
● Check the eye is attached at the center of the
hook.
● Check the crane hoisting wire rope is in
vertical.
● If it is not in vertical, signal to move the crane,
and adjust the sling positions or lower it on
the ground to sling again.
10 Signal to stop the crane ● Check the load is slung horizontally. Judge whether lifting can be
after lifted off ● Check the load is stable. performed or not.
11 Signaling for lifting Take care not to let the load hit the objects around.
12 Signal for stopping Lift the load until the height where the workers can
move safety.
70 (EN)
● Lowering
Item Key points Notes
1 Indicate the unloading Take your position at a place within full view of the crane
place and signal to stop operator. -
2 Signal for lowering ● Make sure the workers are evacuated. Never stay under the load.
● Make sure that the load does not hit objects around.
3 Signal to stop the crane ● Set the load to the applicable height (around the waist). Stop the crane.
● Set the load in correct position.
4 Adjust unloading position Check the area around. Take care not to get
yourself being caught.
5 Signal for lowering ● Stay at the safe area. Do not put your hand on
● Check all the workers are in safe area. the load.
● Signal to the crane while taking care that the load does
not hit objects around.
6 Signal to stop the crane Check the positions of the load and bearer blocks
immediately before the load is landed.
7 Signal for inching down Check the load condition and put it on the bearer blocks.
8 Signal for stopping ● Ensure that the sling wire ropes are taut.
● Check that the bearer blocks support the load properly.
● Check that the sling wire ropes are not caught under the
load.
71 (EN)
9 Inching down the load and ● Ensure that the sling wire ropes are loosened. Avoid the collapse of the
stop ● Check that the load is stable. load.
10 Signal for lowering Stop the sling wire rope at the position where eyes can be
removed.
12 Remove the sling wire ● Wait until the hook stops completely. Watch your footing.
rope
● Remove the ropes while avoiding the collapse of the
load.
● Never pull out the sling wire ropes with the crane hook.
13 Signal for lifting ● Lift the load to the proper height. Lift the hook to at least 2 m
● Signal to the crane while taking care that the load does above the ground as a
not hit objects around. general guideline.
72 (EN)
3 General Precautions for Slinging (p.124)
● Wear a hard hat and secure the chin straps properly. To prevent the risk of falling when working in high
places, wear fall protection equipment.
● When using sling wire ropes, be sure to wear leather gloves to prevent injury.
● Wear safety shoes that are suitable for the type of work that is performed. Wear the working boots or
leggings to protect your foot depending on the type of the operation.
● The employer should designate a person to conduct overall supervision of the work, from the workers who
perform slinging (crane operator, signaler, slinger, slinging assistant, etc.). Designate the person
responsible for the slinging work, assign duties to each person, decide the arrangement of work areas,
specify the areas where entry is prohibited, establish the chain of command structure, and communicate
this information to the workers before starting the work.
● Communicate information about the load, such as the type, weight, shape, quantity, and path of
conveyance, to the person responsible for the slinging work.
● Decide on fixed signals for crane operation that are appropriate for the work location, and designate a
signaler to give the signals.
73 (EN)
3.3 Prestart Meeting (Fig 4-3: p.126)
The person responsible for the slinging work checks the details of operation and working plan with other
members.
● Check the working conditions, and select the applicable path of conveyance not to pass over the other
workers. If it is necessary to set the path of conveyance in the job site, set the evacuation location by
considering the load height, and notify the evacuation procedure to all the workers.
(a) When working with the overhead traveling crane or bridge crane with traveling and traversing functions,
evacuate in 45° from the moving directions and keep the distance of 2 m or more from the load.
(b) When working with the mobile crane or jib crane with slewing function, keep the distance of 2 m or
more from the slewing load.
Traveling
re
mo
or
2m
Evacuation location
Derricking
45°
g
in
Traversing
ew
Sl
2 m or more
Evacuation location
2 m or more
Longitudinal length of load
74 (EN)
● Communicate the work methods, work procedures, and work assignments to the workers.
● When the slinger, signaler, and slinging assistant have a work position, an evacuation location when
conveying, and tasks to prevent the load from swinging, communicate the work positions and swing
prevention methods to each worker.
● Specify the appropriate protective equipment to wear, and check that it is worn.
● Check that the signaling methods are used consistently at each work location.
● Have the signalers wear items such as arm bands and marked helmets so that the crane operator can
identify them easily.
● If wireless devices are used to give signals, check the conditions of wireless communication, such as the
transmission range, before starting the work.
75 (EN)
4 Methods of Slinging with Wire Ropes (p.126)
When lifting by crane, select wire ropes, chains, and belt slings according to the type of the load. In this section,
the slinging method by using a wire rope will be described.
Single-turn Slinging
This is a method of hanging sling wire rope on the middle part on the hook. (See Fig. 4-5: p.127.)
One-Round-Turn Slinging
This is a method of securing a wire rope on the crane hook by winding its bight around the hook once in a single
round turn. (See Fig. 4-6: p.128.)
Blackwall Hitch
The blackwall hitch means winding a wire rope around the crane hook shoulder in one round turn. It is seldom
that 2 or more wire ropes are used at the same time.
This method uses the same single loop as the one-round-turn slinging but the location of the loop is moved up
to the shoulder of the hook. (See Fig. 4-7: p.128.)
76 (EN)
4.2 Methods of Securing Wire Ropes to Load (p.130)
Single-turn Slinging
This method supports the load from the bottom by passing the bight of the sling wire ropes under it. (See Fig.
4-10: p.130.)
One-Round-Turn Slinging
This is a method of securing the load by winding a sling wire rope around it in a single round turn. (See Fig.
4-15: p.133, Fig. 4-16: p.133.)
77 (EN)
5 Methods of Slinging with Chain Slings (p.136)
In general, signaling by hand is used widely. (See p.139-141.) A primary consideration in signaling by hand is to
give distinct signals by the specified motions of hand in a clear manner.
The voice signaling by using the wireless devices is also used at the job sites such as high-rise building. It is
important that the crane operator repeats voice messages given by the signaler.
78 (EN)
The following is the points for the signaler of the crane operation to take note.
● The signaler should understand the slinging work, rated load, operating range, and operating performance
of the crane fully.
● Have the signaler work in a safe location that is visible to the crane operator, and which has a clear view of
the work.
● Use the fixed signals to indicate the operation to the crane operator clearly.
● Always lift the load in a straight line. Make sure that the load will not be lifted obliquely, and then give the
signal.
● Make sure that the slinging has been completed, and then give a signal for lifting.
● Stop the load when the sling wire ropes are taut, make sure ropes are fixed securely, and then give a signal
to lift it further.
● Indicate the transporting direction and unloading position clearly and give a signal as early as possible.
● Stop the load slightly above the bearer blocks, make sure that the load can be landed safely, and then give
a signal for lowering.
● After slinging is completed, lift the hook to a height of at least 2 meters, and all the workers confirm that
work is done correctly.
● As the method of signaling, all the workers should fully understand the method specified in each job site.
79 (EN)
Chapter 5
Practical Slinging Methods
1.1 Check the Rated Loads and Rated Total Loads of the Crane and
Other Equipment (p.149)
The rated load indicated on the overhead traveling crane is the maximum load (weight) that can be lifted by the
overhead traveling crane. The weight of the load must not exceed this amount. Since overhead traveling cranes
and bridge cranes are usually not equipped with an overload preventive device or overload limit device, careful
attention is required.
For jib cranes and mobile cranes, the rated load and rated total load varies depending on the jib angle and
operating radius, so the slingers need to coordinate closely with the crane operator.
80 (EN)
1.2 Find the Weight of the Load (p.150)
The first thing slingers have to do is to find the weight of the load to be lifted as accurately as possible. You can
easily find the weight of those products which you handle daily or which have their weight labeled. However,
when handling a load of unknown weight, you have to ask its weight of an experienced colleague or the group
leader or check it on the drawings, tags, invoice or some other papers. Or, estimate the weight by calculation.
There are many instances where you have to estimate the weight of the load by the eye. Estimation of the
weight requires work experience and it is difficult to estimate it visually. Wrong estimation causes overload of the
crane and unexpected accidents. Furthermore, it will decrease the work efficiency largely. Care should be taken
for the following points.
● Survey the shape of the load carefully and find its dimensions by the eye.
● Check the material of which the load is made. Loads of equal volume may differ in weight if they are made
of different materials
● It is dangerous to estimate the weight lighter than the actual weight. Add 20% to the weight of loads
estimated by the eye.
● If you know by heart the weight of various materials, you can readily calculate the weight of loads from their
size, quantity or volume.
● If you know by heart the weight of various materials per meter, square meter or cubic meter, you can readily
calculate the weight of loads from their size, quantity or volume.
Estimation + 20%
81 (EN)
1.3 Determine the Location of the COG (p.151)
Another important factor in slinging is to determine the location of the COG of the load to be lifted as accurately
as possible in order to select the proper sling gears and slinging method.
Be aware that the COG of load locates as a point (not a line), and it must be checked from all the directions to
perform slinging safely. Especially when turning the load, check the COG from each direction carefully to
prevent an accident from occurring.
When the load is lifted balanced, its COG locates directly under the hook. Once the load is lifted safely, indicate
its COG for reference to ensure the safety and improve the work efficiency.
(1) Determine the COG of the load as above and sling it.
(2) Lift it a little very slowly. (Without lifting off the ground)
Fig. 5-3 How to Determine the Location of the COG during the Work
82 (EN)
(3) If it does not remain horizontal on the sling, return it to the ground and move the position of the sling toward
the side of the load which stayed on the ground during lifting.
(4) Slightly lift the load again and examine its behavior.
(5) Repeat this process until the load comes to stay horizontal on the sling.
Even for the load provided with rings or COG display, the procedure is the same except for step 1 (estimation of
COG).
It is necessary to find which of sling wire rope, chain, belt sling and other sling gear to use, depending on the
COG, number of ropes to be used and the sling angle, and then select the one that has sufficient strength and
length to support the load properly.
In slinging regularly-handled or some specific loads, it is advisable that the safest and most efficient sling gear
available be selected specially for each of these loads. There are some special accessories equipped with
magnet or vacuum lifter to handle steel, glass products or such.
Check the sling gears before the work, and make sure that there is no abnormality.
83 (EN)
Guiding the Hook (p.153)
Call for the crane
When signaling by hand, take your position at a place within full view of the crane operator, and indicate the
load position.
When performing the voice signaling by using the wireless devices, check the conditions of wireless
communication in advance, and take your position at a place within full view of the load and area around it. It is
important to check the crane operator repeats voice messages given by the signaler.
As a general rule, guide the hook directly above the load. If the load is too large and slinging work cannot be
done safely, guide the hook at the position where the slinging can be done easily. Then move the hook directly
above the load before lifting off.
If sling wire ropes are too thick to handle, place the sling wire ropes on the hook first, perform slinging, and then
move the hook directly above the COG of load before lifting off, if necessary.
To lift off the load in a stable condition, COG of the load must be within the line of the lifting points.
COG
If COG of the load is out of this line, the load may slant or sling wore ropes may come off. Even if it is within that
line, when the COG of the hook is not directly above the load, the load may rotate or shift after lifting off.
Accordingly, it is important to guide the hook directly above the load before lifting off.
84 (EN)
Slinging (p.154)
To lift the different shapes of the load with sling wire ropes, it is necessary to select the most applicable method
depending on the shape to prevent the load from rotating or shifting. If the load may collapse, shift or fall over
due to swinging during conveyance, tighten or fix it with lever hoist as preventive measure. For the angular or
slippery load, put pads on the edges to sling it safely.
85 (EN)
When Securing on the Load
● If the load is too large and slinging is difficult to be performed directly above its COG, you can select the
alternative method. Sling the load at the place where the job can be done easily, and move the hook directly
above the load when lifting off. However, when moving the hook with the sling wire ropes attached, take
care not to hit the load or equipment around.
● To lift the load in stable condition, sling at the higher positions than the COG.
● When the lopsided load is lifted with single-turn slinging, the load may rotate. Extra attentions should be
taken for such cases.
G: Center of gravity
Fall over
86 (EN)
● If the long objects are lifted with larger sling angle, the sling gears may slip inward, and it can cause the
falling of the load. Attach pads between the load and sling gears, and lift the load by fastening with eyes,
one-round-turn noosing, or bale sling hitch to prevent the sling points from shifting.
● If there is a risk that the load can be broken by the component force caused due to large sling angle, check
the lift capability of the crane, and use the longer sling wire rope to decrease the sling angle. It the sling
angle is difficult to be decreased, consider the alternative method such as using the lifting beam.
Fig. 5-9 Damaged load Fig. 5-10 Slinging with lifting beam
87 (EN)
● Check that the sling wire ropes under the load are not kinked.
● Pad the edges of an angular load to protect the sling wire ropes and load.
Pad
88 (EN)
When hanging on the Hook
● Check the function of the hook latch. Depending on the conditions, the sling wire ropes may come out from
the hook as shown in Fig. 5-13. In some job sites, two latch devices are used for prevention.
● Attach the sling wire ropes to the hook one by one in order, starting from the back of the hook, so that the
eyes of the sling wire ropes do not overlap each other on the hook, and so that the wire ropes do not cross
each other under the hook. When the sling angle is large, the last sling wire rope that is attached to the
hook is more likely to become detached, or if the sling wire ropes for a load such as the one shown in Fig.
5-14 are attached in the order of 2-1-4-3, the sling wire ropes cross each other under the hook. In cases
such as these, orient the load so that the lengthwise direction is perpendicular to the direction of the hook,
as shown in Fig. 5-15 and Fig. 5-17, and attach the hooks in an order that makes the last wire rope
attached to the hook less likely to become detached, and which prevents the sling wire ropes from crossing
each other.
Fig. 5-14 Lengthwise direction is parallel to the Fig. 5-15 Lengthwise direction is perpendicular to the
direction of the hook (1-2-3-4 or 2-1-4-3 from hook direction of the hook (1-3-2-4 or 3-1-4-2 from hook
end) end)
89 (EN)
(b) Attaching order of eyes in two-rope slinging with four-point
Fig. 5-16 Lengthwise direction is parallel to the Fig. 5-17 Lengthwise direction is perpendicular to the
direction of the hook (1-2-3-4 from hook end) direction of the hook (1-2-3-4 or 2-1-4-3 from hook
end)
● Guide the hook to the place where the sling gears can be attached easily and slingers can be worked in
stable posture with the secured ground condition.
● According to the “Guideline related to Safety of Slinging Operation”, the sling angle should be within 90 ° as
a general rule, however, for single-turn slinging with two-rope and four-point, it should be within 60 °, and
for slinging adjusted with another hoisting accessory, slinging with clamp or hacker, it must be within 60 °.
For other methods, be sure to set the proper sling angle taking the shape and size of the load and lift
capability of the crane into account.
90 (EN)
Slinging a lopsided load
There is a case you have to work on the load that has irregular shapes with the COG off the center. The
following are slinging methods used to keep these lopsided loads horizontal.
● Symmetrical slinging
Find the location of the COG accurately, bring the hook directly above the COG and set the slinging positions
symmetrically.
Same angles
An error in locating the COG would result in a dangerous behavior of the load, as described in Fig. 5-19, which
lets great tension work on the left sling wire rope and may cause the slings to slip off the toad. Even if the sling
wire ropes stay in their positions, the lifted load would be significantly inclined. If it is inclined at lifting off, lower
the load and set the hook or slinging positions at the COG as shown in Fig. 5-20, and lift it again.
Wrong
Correct COG
Fig. 5-19 Slinging with COG locating error Fig. 5-20 Slinging with correct COG location
91 (EN)
● Asymmetrical slinging
Another method uses two sling wire ropes of different lengths to bring the hook directly above the COG of the
load so that the load can be lifted safely. In this method, two sling wire ropes of different lengths to be used for
right and left sides. Care should be taken to use a thicker, stronger wire rope that can lift the whole weight of the
load on the side with a smaller sling angle because a greater force works on the sling wire rope (effective rope)
on this side.
Smaller angle
Larger angle
92 (EN)
● Slinging adjusted with another hoisting accessory
To sling asymmetrical load, sling wire ropes can be adjusted with another hoisting accessory. Balance the
asymmetrical load by adjusting the right and left wire rope length. Chain blocks or lever hoists are used for
adjustment.
This method is an alternative to looping and asymmetrical slinging can be performed more safely, however, the
load with higher COG position becomes unstable. When using two sling wire ropes fastened by eyes at the
effective side, adjust the fastening direction and angle not to apply excessive bending force on wire ropes.
Fasten the eyes of the sling wire ropes on the upper and lower hooks, and adjust the supporting side not to
apply the tension too much. When using lever hoists for adjustment, set the selector to the lifting side and wind
the excessive chain to the body.
Fastening by eyes
Effective side
Supporting side
Fig. 5-22 Slinging adjusted with another hoisting Fig. 5-23 Slinging adjusted with another hoisting
accessory: Effective side: One-round-turn slinging accessory: Effective side: Fastening by eyes
93 (EN)
(Fastening by eyes)
Supporting side
(Fastening by eyes)
Inching up the load slowly until the sling wire ropes are taut. Your hands may be caught between the sling wire
rope/pad and load. Do not hold the wire rope, but push it with your palm. When sling wire ropes are taut, stop
lifting and check the following points. (See Fig. 5-31: p.101, Fig. 5-32: p.101.)
Location of Worker
● Have the signaling by hand in a safe location that is visible to the crane operator. (See Fig. 5-33: p.162.)
Have the voice signaling by using the wireless devices in a safe location which has a clear view of the work.
● Signalers and slingers must communicate closely, do not make a decision for signaling on oneself. (See
Fig. 5-34: p.162.)
● When performing sling work with 2 or more workers, be sure to communicate each other.
● The load may swing at the moment of lifting off. Singers and other workers must not enter the area such as
narrow space between the structures where no place to evacuate is secured. (See Fig. 5-35: p.162.)
● If the load may swing at lifting off, give a signal to the operator.
94 (EN)
Confirm Slinging Conditions
When sling wire ropes are taut, stop the crane and check the following points. If the slinging condition is not
stable or the load cannot be lifted horizontally, lower it back to the ground and adjust the sling position. (See Fig.
5-36: p.162.)
● COG of the load, center of the hook, and hoisting wire rope of the crane are in a straight line.
● Sling wire ropes do not slip and sling accessories such as pads are installed securely.
● Sling gears are applied correctly at the center of the hook (positions and orders).
● If the load is unstable, lower it back to the floor and adjust the sling position.
● Sling gears are installed correctly and the load and accessories are protected properly.
95 (EN)
Lifting (p.164)
Check for obstacles before lifting. Slingers should evacuate to the safe area.
Set the applicable height of the load taking the slinging method and unloading area into account.
● Lift the load until a height where the workers can move safely (higher than the worker) and normally.
● When using a floor-operated crane, lifting magnet, or vacuum lifter, move the load to close area without
obstacles, stop lifting as low position as possible.
Location of Slingers
Slingers should evacuate to safe area where free from the danger of being jammed or hit by the load in case an
unexpected accident occurs.
● Evacuate to the evacuation area that was decided in the prestart meeting.
● When walking along with the load while it is being conveyed, stay at least 2 meters away from the edge of
the lifted load.
● Use the fixed signals to indicate the direction to the crane operator, and give guidance while remaining
ahead of the load until it reaches the unloading place.
96 (EN)
● Keep the safe distance from the load.
● Do not select the path of conveyance to pass over the other workers. Select the route as far as possible
from workers.
● During the conveyance of load, do not hold the load with hands while swinging. The signalers should
instruct to the crane operator to stop swinging. (In some job sites, touching the load with hands is prohibited
from lifting off to grounding.)
● If long objects swing or rotate during the work, they may hit the structures around. To prevent such accident
from occurring, guide the load with guide ropes. Multiple guide ropes are used depending on the job site or
the load.
● If the guide ropes are caught to the equipment around, it may cause accidents such as load collapse. Use
the guide rope without eyes or notches. (See Fig. 5-44: p.166.)
Make sure that there is no worker between the load and equipment or structures, and that the workers can
evacuate in an emergency case. Furthermore, careful attention should be paid to the following precautions
before lowering. (See Fig. 5-45: p.166.)
● Do not lower the load while swinging. Stop swinging according to the signals, and then lower it.
● If it is necessary to adjust the load position at the unloading area, be sure to stop the crane.
● Do not lower the load rapidly. Stop the load slightly above the bearer blocks, and check for the safety.
● Signalers and slingers must stay at the safe area. Do not step under the load to prepare bearer blocks or
other work.
● Always place the load on the bearer blocks (not directly on the ground).
97 (EN)
Stop after grounding (p.167)
After the load is grounded by inching down, stop the crane while the sling wire ropes are taut, check for the
safety and inching down further. And then loosen the sling wire ropes within the range that the load stays in
stable. Do not loosen the sling wire ropes too much. The accessories such as pads may fall off.
● The load is in a stable condition on the bearer blocks. (If not, place it again.)
● The sling wire ropes and pads are not caught under the load.
When removing the sling gears, be sure to study the safer and easier side (hook side or load side) to be
removed.
● When removing the gears at the hook side, guide the hook to a place where removal can be performed
easily.
● Thicker sling wire rope may move suddenly due to twisting. Check the twisting state of the rope and decide
the working area. When removing the gears with 2 or more workers, be sure to communicate each other.
● Do not pull out the sling wire ropes with the crane as a general rule. If it is pulled out with the crane, it may
hit the load or cause the load to collapse or fall.
98 (EN)
End of Work, Store the Tools (p.169)
Never proceed to another work until the tools are stored in place. Store the tools for each operation.
● Remove the sling gear from the hooks and the load.
Do not leave any sling gear attached to the hooks or the load.
● Keep the sling wire ropes straight and store them to the specified location.
● Store the sling gears and hoisting accessories to the specified location.
When stowing or stacking the loads, careful attention should be paid to the following precautions.
● Select suitable bearer blocks for each type of load and set them properly to support the toad stably, so the
removal of the sling gear and the next stage of work can be done easily. Prepare the bearer blocks higher
than the safety shoes not to get the footing caught.
● Be sure to stow or stack unloaded goods stably, so they will not fall or slip off the stack. When stacking
goods, put lighter or smaller things on top of heavier or larger ones to keep the COG of the stack at the
lowest level possible. Do not stack goods into too high a pile that may, if shaken or vibrated, readily topple
down.
● Keep the repository of goods in order. Disorderly stacks of materials or finished products or the protrusion
of some of them into passageways would hamper safe passing and make the whole place dangerous,
resulting in lower efficiency of operation.
● When taking out a material or product from the lower layer of a stack, be sure to remove all things on it first.
Never try to pull it out by force from under other things.
● Store tools, spare parts, attachments and accessories properly divided into those which are needed
frequently and those which are used only now and then.
99 (EN)
Chapter 6
Relevant Laws and Regulations
1. Matters pertaining to the decision of the method of work and the assignment of workers
2. Matters pertaining to the method of guiding or supervising workers
3. In addition to the matters listed in preceding two items, matters necessary for preventing industrial
accidents, as provided for by the Ordinance of the Ministry of Health, Labour and Welfare.
100 (EN)
3 Safety Ordinance for Cranes
(Limitation on Overload) p.188
Article 23
The employer must not use a crane being loaded with the load exceeding its Rated Capacity.
2. Notwithstanding the provisions of the preceding paragraph, the employer may, in the case of having
remarkable difficulty to conform to the provisions of the same paragraph due to the unavoidable reason and
when taking the following measures, use the crane loaded over its Rated Capacity up to the load on the
load test prescribed in paragraph (3) of Article 6:
(i) to submit in advance, a crane special case report (Form No. 10) to the Chief of the Competent Labour
Standards Inspection Office,
(ii) to confirm in advance, that there is no abnormality by performing the load test prescribed in paragraph (3)
of Article 6;
(iii) to designate a person who supervises the operation, and to operate the crane under the direct supervision
by the said person.
(Limitation on Overload) p.188
Article 25
1. The employer must, when carrying out the work using a crane, set fixed signals for operation of the crane,
designate a person who gives the said signals and have the said person give the said signals. However,
this does not apply to when having only a crane operator carry out the work single-handedly.
2. The person designated pursuant to the preceding paragraph, when engaging in the work set forth in the
same paragraph, must give the signals set forth in the same paragraph.
3. Workers engaging in the work set forth in paragraph (1) must follow the signals set forth in the same
paragraph.
(Restriction on Riding) p. 188
Article 26
The employer must not carry workers by a crane, nor have workers work being hanged from the crane.
101 (EN)
(Safety Coefficient of Chain Sling) p.194-195
Article 213-2
1. The employer must not use a chain as the slinging equipment for a crane, a Mobile Crane or a derrick,
unless its safety coefficient is more than the value listed in the following items, based on the types of chain
slings.
102 (EN)