Electrical Installation Guidelines Kerala
Electrical Installation Guidelines Kerala
Guidelines
for
Electrical Installations
Contents
[Link] Subject Page No
1 Extra High Voltage Substations 3
2 Transformer Installations 5
2.1 Outdoor Transformer Installations ( 11 kV / 433 V )
2.2 Indoor Transformer Installations (11 kV / 433 V) 6
2.3 Unitized Substation 7
2.4 Parallel Operation of Transformers 8
3 Generator Installations 11
3.1 High Voltage Generators 11
3.2 Medium Voltage Generator 12
3.3 Generators Running in Parallel 13
3.4 Portable Generator 13
3.5 Generator Mounted on Trolley, Mobile Van, and for Off- 14
shore Operations
3.6 General 15
4 Motors 16
4.1 High Voltage Motors 16
4.2 Medium Voltage Motors 17
5 Power Factor Improvement 17
6 Earthing Standards 21
7 Protection against Lightning 23
8 Switch Boards 24
9 Medium Voltage Cable 26
10 Multi Storeyed Building 31
10.1 Selection of fire pumps for high-rise building 32
11 Electrical Layout in Residential Buildings 33
12 Lifts and Escalators 33
12.1 Lifts 33
12.2 Escalators 36
13 Electrical Distribution at I T / I T related Industries 37
14 Electrification of Hospitals & Health care premises 37
15 X-Ray Installations 44
16 Neon – Sign Installations 45
17 Installation of Electric Fence Energizer 45
18 Installation of Digital Projectors in Cinema Theatres 47
19 Installation of Broad Band Cable TV 47
For availing separate LT supply for mobile / wireless phone services 48
20
at HT / High rise Building premises.
21 Installation of Solar Energy System 49
Communication /Optical Fibre Cable on Distribution Network Power 52
22
Line Supports.
2
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
3
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
4
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
27. Breaking current rating of breakers shall be minimum 31.5kA for 66 & 110kV and 40kA for
220kV & above –Regulation 41(1)
28. Earthing shall be designed for fault current of minimum 31.5kA for 66kV & 110kV and 40kA
for 220kV & above – Regulation 42(5)
29. Surge arrestors shall be provided with surge counters & leakage current monitors -
Regulation 43(2)(g)
30. Disconnectors of 220kV & above shall have provision for remote & manual operation. Only
local operation is recommended for earthing switches. – Regulation 43(2)(d)
31. Two trip coils shall be provided for circuit breakers of 132kV & above - Regulation 43(2(c)(i)
32. Smoke detectors with alarm shall be provided in control room –Regulation 43(3)(b)(iii)
33. Oil evacuating, filtering, testing and filling apparatus shall be provided. - Regulation 43(3)(e)
34. SF6 filling, evacuation, filtering, & recycling plant shall be provided.- Regulation 43(3)(f)
35. PLCC shall be provided for each transmission line of 132kV & above. - Regulation 43(4)(e)
36. Diagnostic equipments like dissolve gas analyzer, winding resistance meter, frequency
response analyzer, capacitance & tan-delta measuring units, contact resistance meter, leakage
current monitor, relay test kit etc shall be provided in sub-stations of 132kV & above. -
Regulation 46
[Link] Installations
5
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
capacity of all transformers installed side by side exceeds 2000 litres. ( IS 10028 Part 2
,clause 3.6.2).
16 As per Electrical Transformer (Quality Controller) Order, 2014 oil filled transformer is an
equipment which requires mandatory ISI marking.
6
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
General
1. If there are more than one transformer and aggregate transformer capacity exceeds
1000kVA,a circuit breaker of adequate rating shall be provided after point of commencement
of supply. Regulation 35(2)(ii)
2. Minimum 1.5m clearance shall be provided between dry type transformer and D.G. set with
acoustic enclosure .
3. Minimum 2 m clearance shall be provided between two dry type transformers installed in the
same room.
4. Baffle wall of 4 hrs fire rating shall be provided between apparatus having more than 2000
liters of oil
(i) at consumers’ premises.
(ii) single phase transformer banks
(iii) where adequate clearance is not available.” – Regulation 44(2)(vii)(a)
General
6. Earthing shall conform to I.S.3043 – 2018.
7. Minimum values of insulation resistance of transformer shall be as given in Table 2.
8. Minimum size of cables laid underground at secondary side of transformers are given in Table
3.
9. Minimum protections required for transformers of different ratings are given in Table 4.
10. Transformer oil shall conform to standards given in Table 13.
11. Maximum rating of 11kV/433V transformers may be 2500kVA
12. M.V. side installation shall conform to I.S.732 – 2019
13. Current rating of 11kV, XLPE, cables are given in Table 14.
14. For CSS installed along walk ways ,play grounds etc .,a fencing or barrier with materials like
wire mesh shall be provided at the distance of 0.75m from CSS. The fencing shall be earthed
(NBC,Part8,52 4.2.1(16)).
15. Neutral conductor shall be of the same size as the phase conductor, if 3rd harmonic currents
are anticipated .
16. A comprehensive fire detection, alarm as well as fire protection system shall be installed for
the Sub- station and Switch yard in conformity with relevant IS. CEA ((Technical Standards
for Construction of Electrical Plants and Electric Lines), Regulations, 2010 43(3)(b)
17. a). Tapping from the HT feeder shall be taken to the fixed contact of the AB Switch
b). Bucket loop arrangement shall be used for the tapping. PG clamps shall be used when
conductor materials are different
c). Double break type AB Switches shall be used when AB Switch is intended to be used as
interlinking AB Switch.
18. Substation shall not be located immediately above or below plumbing water tanks or sewage
(Clause [Link] of Part 8 NBC )
19. All door openings from substation, electrical rooms, etc, should open outwards. Vertical
shutters (like fire rated rolling shutters, grilled preferably) may also be acceptable provided
they are combined with a single leaf door opening outwards for exit in case of emergency. For
large substation room/electrical room having multiple equipment, two or more doors shall be
provided which shall be remotely located from each other.
Clause [Link] of Part 8 NBC
20. In case of HV panel / main MV/ LV panel and transformers located at different floors or at a
distance more than 20 m, HV isolator /remote push button with lockable facility shall be
provided at transformer end . Clause 4.2.1 and 4.2.2 of Part 8 NBC
8
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
7. Transformers designed for parallel operation shall not be required to divide the load within
limits closer than to permit an individual variation from the rated output of any transformer of
the group amounting to +10 percent of such rated output when the total load on the group is
equal to the sum of the rated outputs of all the transformers so connected.
8. When connecting a new transformer, care should be taken to do so in accordance with the
diagram of connections supplied by the manufacturer and of the correct phase sequence of
the supply.
9. Reverse power relay shall be provided for transformers.
10. The system shall be arranged so as to trip the secondary breaker of a transformer in case the
primary breaker of that transformer trips. Regulation 45(1)(iv)
Table - 1
Minimum Safety Working Clearance for Bare Conductors or Live parts in Outdoor Substation - R 44
(2) (iii) Schedule VII
Highest System
12 36 72.5 145 245 420 800
Voltage- kV
Safety working
Clearance - 2.6 2.8 3.1 3.7 4.3 6.4 10.3
(Meters)
Table - 2
Minimum IR values at 300 C for new oil filled transformers
Related Voltage <6.6kV 6.6kV-22kV 33kV >66kV 415Volts
Value in Mega Ohms 200 300 400 500 100
1. IR Values in oil-drained condition shall be 15 to 20 times more than that in oil filled condition.
2. Polarization index (IR at 10 minutes/IR at One minute) shall be more than 1.5
Table – 3
Cables on Secondary Side of Transformers(11kV/433V)
Capacity of Secondary Current Minimum size of
Transformer AYFY cable
(kVA) (A) (mm2)
63 84 50
100 133.3 95(2*50)
160 213.3 185(2*95)
200 266.6 300(2*120)
250 333 (2*185)
315 420 (2*300) or(3*185) or equivalent
400 533 (3*300) or(2*400) or equivalent
500 666.5 (3*400) or (4*240) or equivalent
630 840 (4*400) or equivalent
800 1067 Bus bar Trunking/(4*400)[Link] A2XFY
1000 1333 Bus bar Trunking/(4*400)[Link] YFY
1250 1667 Bus bar Trunking/(4*400)[Link] 2XFY
1600 2133 Bus bar Trunking
2000 2666 Bus bar Trunking
9
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table 4
Protection of Transformers 11kV/433V
Method of Primary control and Secondary control and protection
Rating installation protection
MCCB having isolation duty• and E/F
Up to and release and standby Low set E/F relay using CT
including Outdoor A.B. switch, lightning at neutral earthing conductor or ACB with proper
400kVA arrestor, D.O. fuse current setting facility with 3 O/C and 1 E/ F
release.
MCCB having isolation duty 3 O//C and E/F
ABSF unit or VCB/
Up to and releases or ACB with proper current setting
GCB with 2 O/C and
including Indoor facility with 3 O/C and 1 E/ F release. stand by
1 E/F relays preferably
400kVA low set E/F relay using CT at neutral earthing
with DC trip
strip
ACB draw out type with 3 O/C & 1 E/F release
Above and stand by low set E/F relay usingCT at
400kVA and A.B. switch, lightning neutral earthing conductor.
Outdoor
below arrestor, D.O. fuse **For transformers up to 630kVA, MCCB(rack
1000kVA out type) having isolation duty is permitted
instead of ACB
ACB draw out type with 3 O/C & 1 E/F release
Above ABSF unit or VCB / and standby low set EIF relay using CT at
400kVA and GCB with 2 or 3 O/C neutral earthing conductor.
Indoor
below and 1 E/F relays with **For transformers up to 630kVA, MCCB(rack
1000kVA DC trip out type) having isolation duty is permitted
instead of ACB
ACB draw out type with 3 O/C and
VCB/GCB with 1 EIF release, stand by low set E/F relay with
2 or 3 O/C relays with CT a t neutral earthing strip,. If breaker is
high set elements , incorporated with micro processor based
1000kVA one instantaneous E/F programmable releases 2 O/C and 1 E/F relay
Indoor relay, Buchholz relay, may be avoided.
and above
oil' and winding
temperature relays with *REF protection relay with primary trip shall be
alarm and trip. . provided for transformers of rating above
1600kVA.
10
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
3. Generator Installations
3.1 HV Generators
1. Neutral of the generator may be earthed through NGR or earthing transformer. NGR shall be
rated for 10 second or maximum tripping time on earth fault whichever is higher.
2. VCB / GCB with DC trip shall be provided for generator control.
3. Acoustic arrangements shall be provided for generator sets according to CPCB/SPCB norms.
4. Following meters shall be provided in the control panel.
(a) Ammeters
(b) Voltmeter
(c) Frequency meter
(d) kW meter
(e) kWh meter
(f) kVA meter
(g) kVAr meter
(h) P.F. meter
(i) Winding temperature indicator
(j) Bearing temperature indicator (above 3MW)
5. Following protections shall be provided for HV generators
(a) Voltage restraint O/C relay
(b) E/F Relay
(c) Standby E/F relay using CT in neutral earthing conductor
(d) Over voltage relay.
(e) Under voltage relay
(f) REF / Differential relay
(g) Negative sequence relay
(h) Rotor E/F relay (above 3MW)
(i) Field Failure relay (above 3MW)
(j) Winding temperature high, alarm and trip
(k) Vector surge relay (when connected to grid
(l) Reverse Power and Reverse reactive Power relays (when running parallel or connected
to grid)
(m) Synchro-check relay (When running parallel or connected to grid)
(n) Under current relay may also be included for generators connected to grid
6. Following protections shall be provided for Diesel Engine
(1) High vibration (above 3MW) - alarm and trip (Max: 7mm/s)
(2) High bearing temperature (above 3MW) - alarm and trip (Max: 950C)
(3) Over speed and under speed - alarm and trip
(4) Jacket water temperature high - alarm and trip (Max: 950C)
(5) Lubricating oil temperature high - alarm and trip (Max: 650C)
(6) Lubricating oil pressure low - alarm and trip (Min: 2.5 bar)
(7) Low fuel level alarm
11
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
12
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
13
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
3.5 Generator mounted on Trolley, Mobile Van, and for Off Shore Operation.
1. The platform shall be structurally strong and stable.
A minimum clearance of 1m shall be available between the generator set and its control panel
2.
for easy operation.
Permanent cabling shall be provided between the generator and control panel. The cable shall
3.
be glanded at both ends and firmly clamped on to the platform.
MCB/MCCB rated at the full load current of the generator shall be provided in the control panel
for the protection of the generator. An energy meter of adequate rating shall be mounted on
4. the control panel for recording the energy generated. Energy meter should be got tested and
sealed by Electrical Inspectorate / KSEBL. Voltmeters and ammeters shall be mounted on the
control panel.
Adequate lighting shall be provided inside the cabin. A few lamps shall be connected to the
5.
battery of the vehicle for lighting when the generator is not in operation.
The light wiring inside the vehicle shall be of permanent nature and done through electrical
6.
grade conductors or by using armored cables.
(a) In the case of D.G. sets which are used as a standby source to be changed over to an
7. earthed system or vice versa the neutral and body of the generator shall be earthed to 2
separate and distinct earth electrodes as per standards.
(b) An equipotential bonding conductor shall be formed in the vehicle/carriage by inter-
connecting the generator, engine, control panel and other metallic parts of the carriage
with conductor of adequate size.
(c) The equipotential bonding conductor shall be connected to the ground earth electrode
system. 2 Nos earth electrodes of 38 mm. diameter and 2.5 m length with necessary
interconnecting earthing conductors shall be kept in the van/carriage for driving the earth
electrodes at places where the supply is used as a standby.
In the case of generator sets in which supply is used as an isolated/separate source, earthing
to the ground is not required. But continuity conductors shall be taken from the equipotential
8.
bonding conductor of the vehicle carriage, for the return of the fault current. The neutral and
body of the generator shall be connected to the chassis/ equipotential-bonding conductor.
(a) Where supply is extended for off-shore works in dredgers, pontoons etc. earth
9. grid/equipotential bonding conductor of the dredger, pontoon etc. shall be connected to the
generator earthing system provided on the shore with insulated conductor of adequate
size.
(b) Alternately one core of the 4-core cable to the generator from the offshore equipment shall
be treated as earthing conductor.
(c) The generator body and neutral shall be connected to at least 3 earth electrodes as per
standards. For marine applications, only marine cables shall be used for extending supply
to the offshore carriage.
Distribution from the generator control panel to the actual load center shall be taken through
joint less insulated and tough sheathed PVC cable or weather proof cables or through armored
10.
cables laid properly. The sub-switch boards shall be earthed as per standards by running earth
continuity conductors.
Suitable ELCBs shall be provided for each feeder separately or as a group for protection
11.
against earth leakage.
Sub switch boards and DBs shall be installed as per Regulation 37 and temporary wiring, if
12.
any used shall conform to G.O. (Ms.) 795/85/RD date. 20-8-1985.
At least one 5 kg. DCP type fire extinguisher and 2 Nos. fire buckets filled with dry sand shall
13.
be kept in the mobile van or vehicle.
The mobile unit shall be parked sufficiently away from crowded areas, temporary thatched
14.
sheds, and hazardous areas.
In case the mobile van is used solely for carrying D.G. set and the control gears, a safety
15. certificate, valid for one year shall be obtained from the Electrical Inspector of the area where
the unit is used and it shall be displayed in the van.
14
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
A competent operator possessing a valid wireman permit issued by the K.S.E.L Board shall be
16.
in the charge of the installation when the D.G. set is in operation.
3.6 General
Based on the protections given, generators may be divided into three categories.
Below 100kVA -Small generators
1 100 kVA - below1000kVA -Medium generators
1000kVA and above -Large generators
Generating station with more than one Generator with capacity of 5MW and above is installed
in a power station, each generator shall be provided with at least two separate gas masks in an
accessible and conspicuous place. If the Generator is to be installed in a raised platform, then
2 1. Stability certificate from the chartered structural Engineer shall be required.
2. Fuel drain facility should be provided.
3. Emergency engine stop should be provided at the ground level.
4. There should not be any passage underneath the structure.
For generators up to 30kVA, manufacturer's test certificate shall be accepted for energy
3
meters.
For PWD work, structural stability certificate shall be submitted by a civil engineer of the
4 department not below the rank of Assistant Engineer.
If D.G Sets above 600kVA are provided with AMF Logic and Synchronising Logic with the
5 Engine and Alternator protections, as a part of the Engine Controller, in such cases additional
logic and protection systems need not be insisted to be provided in the PCC.
In Sandwitch Bus Trunking, internal grounding conductors are available which work as its
6 protective Earthing. Therefore, separate parallel Earth conductors need not be insisted for
such Bus Trunkings.
Table - 5
Size of Cables, Earthing conductors and protection of Generators
Generator Full load Cable size Earth Panel
Capacity Current AYFY conductor Protection meters
kVA rating mm2 size
A mm2/SWG
5 7 4 8.3/10 MCB/MCCB
7.5 10.5 4 8.3/10 MCB/MCCB
10 14 4 8.3/10 MCB/MCCB
12.5 17.5 6 8.3/10 MCB/MCCB
15 21 10 8.3/10 MCB/MCCB
20 28 10 8.3/10 MCB/MCCB
25 35 16 18.6/6 MCB/MCCB
30 42 16 18.6/6 MCB/MCCB
35 49 25 18.6/6 MCB/MCCB AM,VM,
40 56 35 27.27/4 MCB/MCCB FM&EM
45 63 35 27.27/4 MCB/MCCB
50 70 35 27.27/4 MCB/MCCB
63 88 50 27.27/4 MCB/MCCB
75 105 95 25x3 MCB/MCCB
82.5 115 95 25x3 MCB/MCCB
100 140 120 25x3
15
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
4. Motors
4.1. H V Motors
Cables shall be rated for appropriate voltage and current. Cables shall have adequate short
1.
circuit current rating also.
Contactors used for HV motors shall be vacuum type and rated for appropriate voltage and
2.
current
Contactors shall be AC - 2, AC - 3 or AC - 4 types depending upon type of motor and mode of
3.
operation.
For auto transformer starting, the auto transformer shall be completely isolated from supply
4.
during normal running of motor.
Local supply isolation facility with locking arrangement at OFF position shall be provided with in
5.
3m from the motor.
6. Protections against the following shall be provided for HV motors.
(a) Thermal over load
(b) Short circuit
(c) Locked Rotor
(d) Earth Fault
(e) Under voltage
(f) Negative sequence
(g) Reverse phase sequence
(h) Prolonged start
(i) Repeat start
(j) Loss of load
16
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
4.2. MV Motors
1. Isolation facility with lockable feature in OFF position shall be provided for all motors with in 3 m.
Contactors used for motors shall be AC-3 or AC-4 type depending upon type of motor and mode
2.
of operation.
Motors shall conform to the Ingress Protection (IP) classification recommended for the particular
3.
location / function.
4. Maximum earth resistance at HT premises shall be limited to 1 ohm.(IS 3043, clause 25.1)
Recommended capacitor rating for direct connection to induction motors are given in
5.
Table 8.
17
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table 10.
13. Losses in capacitors are tabulated in Table 11.
Approximate capacitor ratings for required degree of power factor correction are given in Table
14.
12.
Table-6
Standard size of cables and Backup Fuse Rating for Motors
Motor Rating Approx full Backup fuse rating Cable
load current size AYFY
KW HP A DOL Assisted mm2
0.75 1 1.8 6 - 4
1.50 2 3.5 10 - 4
2.25 3 5.0 16 - 4
3.75 5 7.5 25 - 4
5.50 7.5 11.0 32 25 6
7.5 10 14.0 32 25 6
9.3 12.5 18.0 50 32 10
11.2 15 21.0 50 32 10
15.0 20 28.0 63 50 16
18.7 25 36.0 80 63 25
22.5 30 40.0 100 63 25
26.0 35 47.0 120 100 35
30.0 40 55.0 120 100 35
37.5 50 66.0 160 100 50
45.0 60 80.0 200 120 70
55.0 75 95.0 200 120 95
59.0 80 105.0 250 200 150
67.0 90 118.0 250 200 185
75.0 100 135.0 250 200 185
90.0 125 165.0 320 250 240
110.0 150 200.0 350 320 300
131.0 175 230.0 400 320 2*150
150.0 200 270.0 500 350 2*185
185.0 250 325.0 600 500 2*240
For motors of rating 250 HP and above, breaker shall be provided and
following protections
shall be incorporated
(a) Thermal O/L (b) Short circuit
(b) Earth fault (d) Negative sequence
(c) Under Voltage (f) Locked rotor
Table-7
Minimum cross-sectional area of Protective Conductors
(IS3043:2018)
Cross sectional area of Phase conductor Minimum cross-sectional area of the
S mm2 corresponding protective conductor
18
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
S<16 S
16<S<35 16
S>35 (I√t)/k (IS 3043 clause [Link])
Table-8
Recommended Maximum Capacitor rating for direct connection
To Induction Motors in kVAr
Motor Capacitor rating for motor speed in rpm
HP/kW 3000 1500 1000 750 600 500
3/2.5 1 1 1.5 2 2.5 2.5
5/3.7 2 2 2.5 3.5 4 4
7.5/5.7 2.5 3 3.5 4.5 5 5.5
10/7.5 3 4 4.5 5.5 6 6.5
15/11.2 4 5 6.7 7.5 8.5 9
20/15 5 6 7 9 11 12
25/18.7 6 7 9 10.5 13 14.5
30/22.8 7 8 10 12 15 17
50/37 11 12.5 16 18 23 25
75/57 16 17 21 23 29 32
100/75 21 17 21 23 29 32
130/102 31 33 36 38 48 55
200/150 40 42 45 47 60 67
250/187 46 50 53 55 68 76
Table - 9
Recommended cable size for group power factor improvement capacitors
Backup Size of
kVAr Fuse/ AYFY cable Backup Fuse/ Size of AYFY cable in
breaker in [Link] kVAr
breaker [Link]
25 63 16 80 200 150
30 100 25 90 200 185
40 100 35
100 250 240
50 120 50
60 150 70 200 Breaker 2 X 185
70 160 120 300 Breaker 2 X 300
400 Breaker 2 X 400
19
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table - 10
Capacitors for Welding transformers
Table - 11
Losses in Capacitors
Type of Capacitor Loss W/kVAr
Paper Oil Impregnated 2.0 to 2.5
Paper PCB Impregnated 3.0 to 3.5
Plastic Film/Paper, PCB 0.5 to 1.0
Plastic Film/Paper, Oil 0.5 to 1.0
Metalised Film Less than 0.5
Table - 12
Capacitors in kVAR for required power factor correction
Initial Correction to Initial Correction to
power 0.85 0.90 0.95 0.98 1.00 power 0.85 0.90 0.95 0.98 1.00
factor factor
0.50 1.112 1.248 1.403 1.529 1.732 0.75 0.262 0.398 0.535 0.673 0882
0.51 1.066 1.202 1.357 1.483 1.686 0.76 0.235 0.371 0.526 0.652 0.855
0.52 1.024 1.160 1.315 1.441 1.644 0.77 0.209 0.345 0.500 0.620 0.829
0.53 1.980 1.116 1.271 1.397 1.600 0.78 0.183 0.319 0.473 0.594 0.833
0.54 0.939 1.075 1.230 1.356 1.559 0.79 0.156 0.292 0.447 0.567 0.776
0.55 0.899 1.035 1.190 1.316 1.519 0.80 1.130 0.266 0.421 0.541 0.750
0.56 0.860 0.996 1.151 1.277 1.450 0.81 0.104 0.250 0.395 0.515 0.725
0.57 0.822 0.958 1.113 1.239 1.442 0.82 0.078 0.214 0.369 0.489 0.698
0.58 0.785 0.921 1.076 1.202 1.405 0.83 0.052 0.188 0.343 0.463 0.672
0.59 0.748 0.884 1.039 1.165 1.368 0.84 0.026 0.162 0.317 0.437 0.645
0.60 0.714 0.849 1.005 1.131 1.334 0.85 - 0.136 0.291 0.417 0.620
0.61 0.679 0.815 0.970 1.096 1.299 0.86 - 0.109 0.264 0.390 0.593
0.62 0.645 0.781 0.936 1.062 1.265 0.87 - 0.083 0.238 0.364 0.567
0.63 0.613 0.749 0.904 1.030 1.233 0.88 - 0.054 0.209 0.335 0.538
0.64 0.580 0.716 0.871 0.997 1.200 0.89 - 0.028 0.183 0.309 0.512
0.65 0.549 0.685 0.840 0.966 1.169 0.90 - - 0.155 0.251 0.484
0.66 0.518 0.654 0.809 0.935 1.138 0.91 - - 0.124 0.250 0.453
0.67 0.488 0.624 0.779 0.905 1.108 0.92 - - 0.097 0.223 0.426
0.68 0.459 0.595 0.750 0.876 1.076 0.93 - - 0.066 0.192 0.395
20
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
0.69 0.429 0.565 0.720 0.840 1049 0.94 - 0.034 0.160 0.363
0.70 0.400 0.536 0.691 0.811 1.020 0.95 - - 0.126 0.239
0.71 0.372 0.508 0.663 0.753 0.992 0.96 - - 0.089 0.292
0.72 0.343 0.479 0.634 0.754 0.963 0.97 - - 0.47 0.25
0.73 0.316 0.452 0.607 0.727 0.863 0.98 - - - 0.203
0.74 0.289 0.425 0.580 0.700 0.909 0.99 - - - 0.143
6. Earthing Standards
1. Earthing shall conform to I.S. 3043 / 2018 and IS 732:2019.
NGR used for HV generator/ Transformer shall be rated for 10 seconds or maximum tripping time
2.
on earth fault whichever is higher.
Minimum fault level at 11 kV side shall be assumed 150MVA for all earthing designs, if the actual
3.
fault level is less than 150MVA.
Number of earth electrodes required shall be calculated for fault current at HV side. Current
4.
loading of 1.2M x 1.2M plate shall not exceed 1300A. (I.S. 3043 – Cl.14.2.1)
Duration of fault current shall be taken as 3 sec for earthing design at HT installations and 1 sec
5.
for EHT installation.
All earth electrodes shall be interconnected using the conductors of largest size in the earthing
6.
system.
7. Maximum earth resistance at HT premises shall be limited to 1 ohm.(IS 3043, clause 25.1)
Earth mat shall be provided at EHT premises for limiting step voltage and touch voltage to
8.
tolerable values according to EEE 80.
All non-current carrying metal parts of electrical equipments shall be earthed and if voltage of
9. equipment exceeds 250V, it shall be connected in duplicate(CEA (MR&ES) Regulation – Cl.
41(xii))
Transformer and generator neutral shall be connected in duplicate. One direct connection from
10. neutral to an earth electrode shall be provided for neutral earthing. Links shall also be provided in
neutral earthing conductor. Generator neutral shall be earthed at control panel.
Lightning arrestor shall be directly connected to an earth electrode using No. 6 SWG Cu. The L.A.
11.
earth electrode may be interconnected with other earth electrodes.
When Steel conductors are used for earthing, the following allowances in cross section area of
12. earthing conductor are recommended to take effect of corrosion into account as per IS 3043-
2018.
Allowances to be
13. Type of laying of earthing conductors
considered
Conductors laid in soils having resistivity lower than 25 ohm meter or 30%
where treatment of soil around electrode is carried out
Conductors laid in soils having resistivity from 25 ohm m to 100 ohm m 15%
Conductors laid in soils having resistivity Above 100 ohm m 0 (no allowance)
A number of rods or pipes may be connected in parallel and the resistance is then practically
proportional to the reciprocal of the number employed so long as each is situated outside the
resistance area of any other. In practice, this is satisfied by a mutual separation equal to the driven
14.
depth. Little is to be gained by separation beyond twice the driven depth. A substantial gain is
effected even at 2 m separation. A Separation of two meter between plate electrode is sufficient to
get the earth resistance value with 20% variation. (IS 3043:2018 Cl.14.2.2)
15. Minimum distance between earth electrode and adjacent civil structure shall be 1.5 m.
16. In location of SBs, DBs etc. sub earth buses of 25x3mm2 copper or 32*6 mm2 GI may be provided.
17. All Copper joints in earthing conductors shall be properly tinned.
21
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
22
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Maximum current per meter of rod length for the total rod system should not exceed the values as
determined by Equation
22.
If ground currents of high magnitude and long duration are anticipated, the system must cover a
relatively large area and employ a sufficient number of electrodes and electrode connections. This
will keep the current density in the earth to a low value.
Permissible current density (for 3 seconds) for earthing conductors.
a) Copper =118A/mm2
23.
b) Aluminium =73Amm2
c) Steel(GI) =46A/mm2
24. Protective equipotential bonding shall be carried out in all buildings as specified in IS 3043/IS 732.
Earth fault protection at every LT consumer premises shall be achieved by the following
a) The earth fault loop impedance has to be low enough to allow adequate earth fault current flow
to cause and over current protective device (for example, a fuse or circuit breaker) in the faulty
25.
circuit to operate in a sufficiently short time : or
b) Where it is not possible to achieve a low enough earth fault loop impedance, disconnection may
initiated by fitting a residual current device (RCD) of 30 mA (IS 3043:2018, clause 23.1)
23
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
If a particular rod of the reinforcement steel is used as the down-conductor, care should be taken in
9 the route to earth to ensure that the rod that is located in the same position will be used all the way
down, thereby providing direct electrical continuity. (Clause E.4.3.7)
If the vertical continuity of the natural down-conductors, providing a straight path from roof to
ground cannot be guaranteed, additional dedicated conductors should be used. These additional
conductors should be lashed or clamped to the reinforcement steel. (ClauseE.4.3.7) In order to
10
avoid confusion between the different types of steel rods in concrete it is recommended that round
steel rods of atleast 8mm diameter with a smooth surface be used as additional conductors in
contrast to the ordinary ribbed surface of the reinforcing rods.(Clause 4.3.4)
If the direct route of the down-conductor (i.e. for existing buildings) is not clear an external down
11.
conductor system should be added. (Clause E.4.3.7)
In the case of large, low buildings such as halls, the roof is supported not only at the building
circumference but also by internal columns. Such conductive columns should be connected to the
air-termination system at the top and to the equipotential bonding system at the floor, creating
12.
internal down-conductors; this is to prevent dangerous sparking inside the building. Increased
electromagnetic interference occurs in the vicinity of such internal down-conductors, for which
adequate care should be given. (Clause E.4.3.7)
When ring conductors are proposed for individual floors of a building for the purpose of equi
13 potentialisation, it should be interconnected by means of vertical rods at intervals not greater than
10 m. (Clause E.4.3.8)
If prefabricated reinforced concrete parts are used for lightning protection, connection points should
be attached to them to allow later interconnection of the prefabricated reinforcement with the
reinforcement of the structure in a simple manner. These connection points should be located so
14
that in the prefabricated concrete part a continuous reinforcing rod runs from one bonding joint to
the next. In general, one connection point and a bonding conductor is required at each corner of a
plate-like prefabricated reinforced concrete part. (Clause E.4.3.11)
When the structure comprises a number of sections with expansion joints, in order to ensure low-
impedance potential equalization and effective shielding of the space inside a structure, expansion
15 joints between sections of a structure should be bridged at short intervals (between 1 m and one
half of the distance between down-conductors) by flexible or sliding bonding conductors depending
on the required shielding factor. (Clause E.4.3.12)
[Link] Boards
In case of outgoing circuits from the switchboard, where the current rating exceeds 63A, connection
1. between the busbar chamber and the automatic circuit breaker or switch fuse or any other control
gear shall be made only by solid connections.
Current density in buses shall not exceed 1.2 A/mm2 for copper and 0.8 A/mm2 for aluminium.
2.
Minimum thickness of aluminium buses shall be 6mm.
When ACB is provided at the incoming side of a switchboard the outlet switch rating shall not be
3.
less than 1/3 of the incomer setting.
When MCCB is provided at incoming side, the outlet switch rating shall not be less than 1/5th of the
4.
incomer setting.
Outlet fuse rating shall not exceed 1/3 of the incomer breaker setting from the point of view of
5.
grading.
If ACB is provided as incomer and MCCBs as outlets in a switchboard, outlet MCCB can be set up
6.
to 80% of incomer ACB settings.
If MCCB is provided as incomer, the maximum current setting of MCCBs proposed as outlets in
7.
switch board shall be half that of incomer MCCB setting.
8. In the case of transformers of rating above 1600 kVA only extra current limiting type MCCBs shall
24
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Test certificates may be insisted for electronic change over switches regarding its ampere rating
33.
and proper supply change over.
Table -13
Standard requirements for insulating oils
Characteristics Equipment Voltage Permissible Limits
Dielectric Strength 145 kV and above 30 kV(Min)
Break down voltage Below72.5 kV 40 kV (Min)
72.5 kV and <145 kV 50 kV (Min)
Water content Below 145 kV 35ppm (Max)
145 kV and above 25ppm (Max)
Specific resistance All voltages
(Ohm-cm)at 90°C 0.1 x 1012ohm-cm (Min)
Dielectric dissipation All voltages
factor 0.005(Max):
(tan -o) at 900 c
..
Neutrlaisation value All voltages 0.4 mg KGlH/gr (Max)
(Total acidity)
Interfacial tension at All voltages 0.018N/M (Min)
27°C
Min. -125°C
Flashpoint All voltages Max - 15°C decrease of initial value
Sediment or precipitable All voltages No sediment or precipitable sludge should
sludge be detectable
Dissolved gas analysis 145 kV and above Refer I.S. 10593 - 1993 & DGA
study chart
26
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table -14
Current rating of 11kV UG Cables (XLPE-Aluminium)
Current ratincis (A)
Nominal area of Three - Core cables Single - Core cables
conductor In Ground In Air In Ground In Air
([Link])
50 125 135 140 175
70 155 170 170 215
95 185 205 205 255
120 210 240 230 300
150 235 275 260 335
240 305 375 330 460
300 345 425 370 520
Table -15
Cable Code (IS 7098-Part 2- 2011)
Constituent Code Letter
Aluminium Conductor A
XPLE 2X
PVC Insulation V
Steel round wire armoured W
Non-magneticround wire armoured Wa
Steel Strip armoured F
Non-Magnetic strip armoured Fa
Double steel strip armoured FF
Double steel wire armoured WW
PVC outer sheath Y
Table 16
Current rating of AYFY Cables IS : 3961Part II 1967
Nominal area of conductor (mm2) Corresponding current rating (A)
1.5 16
2.5 21
4 28
6 35
10 46
16 50
25 76
35 93
50 110
70 135
95 165
120 185
150 210
185 235
240 275
300 305
400 335
27
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table - 17
Current rating of AYFY Feeder cables
Fuse/Feeder Size in [Link] Feeder rating in A Size in [Link]
Rating in A
16 4 150 150
25 6 160 185
32 10 200 240
40 16 250 400
50 25 320 2x185
63 35 400 2x240
80 50 500 240
100 70 630 400
120 95 800 4x400
125 120
Table - 18
Voltage drop and resistance of AYFY Cables
Conductor Installation method (Clipped direct) AC
Cross- One Twin Single Phase Three Core Three Phase Backup resistance
Sectional Current Volt Drop/ A Current Volt Drop/ A Fuse at 20°c
Area Carrying /m Carrying /m Ohm/km
mm2 Capacity Capacity A (apprx.)
A mV A mV
1.5 16 - - - 10 -
2.5 21 29 19 25.1 16 14.491
4 28 18.2 25 15.8 16 9.122
6 35 12.1 32 10.5 25 6.062
10 46 7.3 43 6.3 32 3.637
16 60 4.5 58 3.9 40 2.252
25 76 2.9 74 2.5 50 1.443
35 92 2.1 90 1.8 63 1.039
50 110 1.6 115 1.3 80 0.751
70 135 1.1 135 0.93 100 0.537
95 165 0.79 165 0.68 120 0.393
120 185 0.65 190 0.54 125 0.312
150 210 0.53 215 0.45 150 0.250
185 235 0.45 250 0.37 160 0.214
240 275 0.36 295 0.30 200 0.173
300 305 0.31 340 0.25 225 0.144
400 335 0.26 415 0.225 250 0.090
2x185 423 - - - 320 -
28
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table - 19
Voltage drop in PVC insulated Copper Cables
Conductor Cross- Installation method (Clipped direct)
Sectional Area
Twin Core Three Core
mm2
Current Carrying Volt Drop/ A Current Carrying Volt Drop/ A
Capacity /m Capacity /m
A mV A mV
1.5 20 29 18 25
2.5 29 18 24 16
4 37 12 31 9.5
6 48 7.4 41 6.3
10 66 4.3 56 3.8
16 86 2.7 73 2.3
25 115 1.8 97 1.6
35 142 1.3 119 1.1
50 168 0.92 147 0.81
70 209 0.65 180 0.57
95 257 0.48 219 0.42
120 295 0.40 257 0.34
150 337 0.32 295 0.29
185 390 0.29 333 0.24
240 461 0.25 399 0.18
300 523 0.23 451 0.18
400 589 0.22 523 0.17
29
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table -20
XLPE Cable current rating
3.5core Aluminum conductor, XLPE insulated and PVC sheathed unarmored/armoured cable
conforming to IS:7098(PT-1)/1988
4 core Aluminum conductor, XLPE insulated and PVC sheathed unarmored/armoured cable
conforming to IS:7098(PT-1)/1988
Nom. Unarmoured Armoured Max. D.C Max. A.C Current Rating
Cross Overall Net wl. of Overall Net wl. of Resistance Resistance Direct in In Air
sectional Diameter cable Diameter cable Temp. 200C OperatingTemp. Ground
area (Approx.) (Approx.) (Approx.) (Approx.) /Km 900C Amps Amps
mm2 (mm) (Kg/Km) (mm) (Kg/Km) /Km
4 15 242 17 596 7.140 9.50 34 31
6 16 289 18 664 4.610 5.90 43 40
10 17 378 20 750 3.080 3.940 57 53
16 19 445 22 700 1.910 2.440 73 70
25 22 650 24 940 1.200 1.540 94 96
35 25 800 27 1130 0.868 1.110 113 117
50 28 1000 30 1400 0.641 0.820 133 142
70 33 1370 34 1800 0.443 0.567 164 179
95 35 1740 38 2190 0.320 0.410 196 221
120 39 2170 42 2690 0.253 0.325 223 257
150 44 2630 47 3220 0.206 0.265 249 292
185 49 3250 52 3920 0.164 0.211 282 337
240 55 4110 59 4850 0.125 0.162 326 399
300 61 5070 64 5900 0.100 0.130 367 455
400 69 6420 72 7310 0.0778 0.1023 418 530
30
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Lightning protection shall be provided and shall conform to IS/IEC 62305 Class of LPS and details
19.
are given in Table 21.
20. When generator supply is extended to individual consumers, it shall be through an emergency DB.
Emergency supply isolation facility using push buttons shall be provided in a conspicuous place at
21.
ground floor at a maximum height of 1.70 metres above the ground. (CEA Regulation – Cl. 36(3))
Transformers and generators shall be installed at the periphery of the building having easy access
22.
and ventilation.
23. Exhaust pipe of DG set shall be brought above roof top level as per CPCB.
24. Acoustic arrangements of DG shall be provided as per CPCB.
Rigid standards shall be followed in selection of quality wiring materials and for standard
25.
maintenance practices. Wiring shall conform to I.S. 732, I.S. 4648 and NEC.
26. For fire pumps, starters without over load relay shall be provided.
Height of meter display in metering panels shall be 0.75M to 1.8M. (CEA Installation of Meters
27.
Regulations – Cl. 7(2) (c) & I.S. 15707 – Cl. 11.3.1(b))
It is essential to provide independent feeders for installations such as fire lift, fire alarm,fire pumps,
28.
etc.
In commercial premises and high-rise buildings, a few lifts and circulation area lights and
29.
fire-fighting equipment have to be kept working by supply from stand-by sets (NEC part 2, 8.2)
30. In multi-storeyed building with HT metering, use of bus ducts are advisable than cable ducts.
The power supply HV cables voltage shall not be more than 12 kV and a separate dedicated and
31. fire compartmented shaft should be provided for carrying such high voltage cables to upper floors
in a building. Clause 4.2.1 of Part 8 NBC
If dry type transformers are installed above ground level in multi-storied building of height more than
15m, 11kV ABSFU/Breaker shall be provided at ground floor. Structural fitness certificate from a
32.
competent structural engineer shall also be furnished. Regulation 36(3). Also refer section General
(under transformer) Sl. No 20
10.1 Selection of fire pumps for high-rise building
The minimum requirements for firefighting installation in high rise building are given in the National
1.
Building Code Part IV, Table 31.
2. Installation and selection of Fire extinguishers shall conform to IS 2190 :2010 and IS 15683:2006.
Electrically operated fire pumps along with booster pumps of adequate rating as per National
3.
Building Code shall be provided.
Main fire pumps (electric & diesel) and jockey fire pump are to be provided near surface level,
4.
under-ground static tank.
5. Booster fire pump is to be provided at terrace level.
Table 21
Lightning Protection
Protection angle w.r.t height Rolling Distance
Class Mesh size Sphere between
of LPS in meters 10 meter 20 meter 30 meter 45 meter 60 meter redius in down
meters Conductor
I 5x5 46 23 NA NA 20 10
II 10 x 10 54 38 23 NA 30 10
III 15 x 15 62 48 36 23 NA 45 15
IV 20 x 20 65 53 46 33 23 60 20
32
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
33
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Even dimensions are to be maintained throughout the lift well with proper plastering.
Lintel may be cast above a height of 2100 mm for door opening at all floors.
No column projection should be extended to the lift well area.
For passenger lifts having sliding door facility till projection of 105 mm to be provided on all
landings.
External power cables (other than lift car and central cables) should not be run through lift well.
3. Machine Room
The machines should be as far as possible, be placed immediately above the lift well.
If construction of machine room is not possible above lift well it shall be below the lift well or in the
basement.
High-speed lift with gearless machine should have machine room above the lift well.
Lightning protection shall be provided as per I S 62305 over the lift machine room
The machine room shall be segregated from the lift well by fire resistant separation in the
basement.
The machine room shall be kept closed, except to those who are concerned with the operation
and the maintenance of the machinery. When the electrical pressure exceeds 250 Vdc or 125
Vac, a danger notice shall be displayed permanently on the outside of the door.
The machine room shall be equipped with an insulated portable hand lamp provided with flexible
cord for examining the machinery.
The machine room shall be kept clean.
There shall be a direct independent access from the topmost landing to the lift machine room.
All open rotating parts shall be guarded from accidental contact.
The machine room shall be well ventilated during normal operation.
The motor of each lift machine or the worm shaft shall be arranged so as to provide hand-winding
facilities and shall be suitably marked for the direction of up and down travel of the lift car.
4. Electrical Wiring
All electrical supply lines and apparatus in connection with the lift installation shall be so
constructed, installed, protected, worked and maintained that there may be no danger to persons
there from.
All metal casings or metallic coverings containing or protecting electric supply lines of apparatus
shall be effectively earthed.
No bare conductor shall be used in any lift car.
All cable and other wiring in connection with the lift installations shall be of suitable grade for the
voltage at which they are intended to be worked and shall confirm to IS 4289-1967.
Cable to the motor shall be segregated and the power cables should not be mixed with control
and safety cables.
A trailing cable, which incorporates the control circuit, shall be separate and distinct from that
which incorporates lighting and signaling circuits.
Separate feeders shall be provided for power and lighting circuits.
Proper ventilation shall be provided for the motor control panel and shall be guarded against
accessibility to live parts.
Clearance between lift motor control panels shall be sufficient for easy maintenance from both
sides of the control panel.
Dressing of control cables from the motor control panel to lift car shall be checked to ensure
trouble free operation and detection of faults.
Local isolation shall be provided for both power and lighting feeders.
Cables from the motor control panel to lift motor and electro magnetic brake shall not be laid over
the floor directly.
Insulating mats as per IS 15652 shall be provided in front of panels, switch boards etc.
34
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
The earthing conductor shall be secured to earthing terminal in accordance with recommendation
made in IS 3043/2018 and also in conformity with the latest provisions of Central Electricity
Authority (Measures Relating to Safety and Electric Supply) Regulation 2010.
It is recommendatory that lift car be provided either with an emergency signal that is operative
from the lift car and audible outside the lift well or with a telephone. The supply to the alarm
system should be taken from the machine room light circuit.
When lift is operated through generator, the capacity of generator should be 6 times the rating of
lift motor in kW and 4 times in the case of variable voltage variable frequency lift motors.
ELCBs shall be provided in lift motor and lighting feeders.
Emergency stopping device in car operating panel for automatically operated lifts with
imperforated doors is prohibited.
5. Lift car
Emergency stopping device in car operating panel for automatically operated lifts with
mperforated doors is prohibited.
An alarm button, yellow in colour shall be provided on the car-operating panel.
A load plate giving the rated load of the lift shall be fitted in each lift car. For passenger lifts the
rated load shall be given in number of persons and kilograms.
Net inside car areas for various passenger capacities with corresponding minimum rated loads
shall be as given in Table 22
6. Protection
Every passenger lift shall be provided with an overload protection device, which will prevent the
lift from starting in case the lift car is loaded to 110% of the rated capacity of the lift or more. Lift
shall remain stationary with door open.
Audio and visual warning shall be provided to alert the passenger in case of over load.
Battery operated Automatic Rescue Device (ARD) shall be provided on all lifts to take the lifts to
the nearest possible landing in case of power failure. If lifts are equipped with back up generator
with AMF Panel the provision of ARD is optional. Capacity of battery for ARD shall be such that
minimum three rescue operatations can be performed without recharging.
For all lifts with ARD, an audio and visual indication shall be provided inside the lift car to alert the
person trapped inside that he / she is being rescued.
For calculating fee for escalators, each escalator motor shall be taken as a unit.
Table : 22
Minimum and Maximum Net inside Car area for Lifts
(IS 14665 (Part 3/Sec.1):20000)
No. of Passengers Minimum Rate Load Minimum Net Inside Maximum Net Inside
Kg Car Area, M2 Car Area, M2
4 272 0.68 0.77
5 340 0.85 0.95
6 408 1.00 1.12
7 476 1.16 1.28
8. 544 1.31 1.45
9 612 1.46 1.60
10 680 1.61 1.76
11 784 1.92 1.91
12 816 1.92 2.05
13 884 2.06 2.20
14 952 2.23 2.34
15 1020 2.35 2.47
35
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
[Link]
1. Escalator and its installation shall conform to IS 4591.
2. An SDF/CB shall control the escalator circuit.
3. An electrical motor shall not drive more than one escalator.
4. Key operated type starting switch shall be provided near the escalator.
5. Angle of Inclination -It shall not exceed 30 degrees from the horizontal, but for rises not exceeding
6 metres and a nominal speed not exceeding 0.5m/s an angle up to 35 degrees is permitted. (IS
4591:2020, Part 1 sec 5.2.2)
6. Manually operated type emergency stop switches shall be provided at accessible height at top
and bottom landing spaces.
7. Local supply isolator shall be provided near the escalator main motor.
8. Step treads shall be properly illuminated throughout the run.
9. Each escalator shall be provided with an electrically released, mechanically applied brake
capable of stopping the traveling escalator travel with any load up to its rated load.
10. Rated speed shall not exceed 38 m/min.
11. A speed governor has to be provided to stop the escalator travel if the speed exceeds a
predetermined value subject to maximum 140% of the rated speed.
12. Broken step chain device shall be provided to cut off power supply to the driving machine, if the
step chain breaks.
13. Balustrades shall be provided at each side and comb plates at top and bottom of escalator.
14. Finger guards shall be provided at the point where the handrail enters the balustrades.
15. Skirt guards shall be provided at bottom portion of balustrades.
16. Clearance between step and skirt guard shall be max. 5mm.
17. Clearance between step treads shall be max. 4mm.
18. Handrails shall extend to min. 30cm to top and bottom landing spaces.
19. Step tread width shall be min. 40cm. and max. 102cm.
20. The depth of step tread shall be more than 40cm. and the rise between treads shall be less than
22cm.
21. Door to the machine room shall be outward opening type.
36
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
2 In medical locations the distribution system should be designed and installed to facilitate the
automatic change-over from the main distribution network to the electrical safety source feeding
essential loads
• Group 0
Medical location where no applied parts are intended to be used.
• Group 1
Medical location where applied parts are intended to be used as follows:
– Externally;
– Invasively to any part of the body, except where Group 2 applies
Group 2
Medical location where applied parts are intended to be used in applications such as intra
cardiac procedures, operating theatres and vital treatment where discontinuity (failure) of the
37
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
When using SELV and/or PELV circuits in medical locations of group1 and group 2, the
nominal voltage applied to current-using equipment shall not exceed 25 V [Link] 60 V
ripple free dc. Protection by insulation of live parts and by barriers or enclosures is
essential.
When safety extra voltage is obtained from supply mains, it is to be through a safety
isolating transformer or a convertor with separate winding, the insulation of which complies
with the double insulation or reinforced insulation requirement.
4 I. TN systems:
In medical locations of group 1, in final circuits with over current protective devices rated
up to 32 A, residual current protective devices with a rated residual operating current not
38
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
39
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
connections, between the terminals for the protective conductor of socket-outlets and of fixed
equipment or any extraneous- conductive-parts and the equipotential bonding bus bar shall not
exceed 0.2 Ω.
NOTE — This resistive value can also be determined by the use of a suitable cross-sectional
area of the conductor.
7 Fire Protection shall be provided as per National Building Code of India part 4 Fire and Life
safety applies.
8 SELECTION AND ERECTION OF ELECTRICAL EQUIPMENT(IS 17512 sec 7)
a) Transformers for medical IT systems
It is recommended that the medical IT distribution board is located within 25 m of the point of
use. The distribution board should be easily accessible for maintenance which will require it
to be located on the same level and the same fire section as the load it serves. Distribution
boards shall be installed outside the group2 medical locations and should be safely guarded
against unauthorized persons.
The rated voltage Un on the secondary side of transformers shall not exceed 250 V ac.
b) Medical IT systems for group 2 medical locations
Transformers shall be in accordance with IEC 61558-2-15, with the following additional
requirements:
1) The leakage current of the output winding to earth and the leakage current of the
enclosure, when measured in no-load condition and the transformer supplied at rated
voltage and rated frequency shall not exceed 0.5 m A.
2) Single-phase transformers shall be used to form the medical IT systems for portable
and fixed equipment and the rated output shall not be less than 0.5 kVA and shall not
exceed 10 kVA.
3) 3)If the supply of three-phase loads via an IT system is also required, a separate three-
phase isolation transformer shall be provided for this purpose without put line-to-line
voltage not exceeding 250 V.
9 Where appropriate, attention should be given to prevention of electromagnetic interference.
Explosion risk
1) Requirements for medical electrical equipment for use in conjunction with flammable
gases and vapours are contained of IS 13450 (Part 1).
2) Where hazardous conditions are likely to occur (for example, in the presence of
flammable gases and vapours), special precautions may be required.
3) Prevention of build-up of static electricity is recommended.
Electrical devices (for example, socket-outlets and switches) shall be installed at a distance of at
least 0.2 m horizontally (centre to centre) from any medical gas- outlets, so as to minimize the
risk of ignition of flammable gases.
10 Any wiring system within group 2 medical locations shall be exclusive to the use of equipment
and fittings in that location. (IS 17512 sec 7.2)
11 Protection of Wiring Systems in Medical Locations of Group 2:
Total selectivity shall be ensured for any prospective over current: In case of a short-circuit in a
final circuit, the incoming circuits of the upstream distribution board shall not be interrupted.
Over current protection against short-circuit and over load current is necessary for each final
circuit. Overload current protection is not allowed in the feeder circuits upstream and downstream
of the transformer of medical IT-system.
12 Lighting Circuits
In medical locations of group 1 and group 2, at least two different sources of supply shall be
provided for some of the luminaries by two circuits. One of the two circuits shall be connected to
the safety service. In escape routes, alternate luminaries shall be connected to the safety service
40
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
41
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
The power supply shall be restored within a change-over period not exceeding 0.5 s.
The duration of 3 h battery may be reduced to 1 h, if a power source as diesel generator is
installed.
b) Power Supply Sources with a Change-over Period/less than or equal to 15 s
Equipment according to Safety lighting and Other services shall be connected within 15 s to
a safety power supply source capable of maintaining it for a minimum period of 24 h, when
the voltage of one or more-line conductors at the main distribution board for the safety
services has decreased by more than10 percent of the nominal value of supply voltage and
of a duration greater than 3 s.
c) Power Supply Sources with a Changeover Period greater than 15 s
Equipment other than those covered above, which is required for the maintenance of hospital
services, may be connected either automatically or manually to a safety power supply source
capable of maintaining it for a minimum period of 24 h. This equipment may include, for
example:
– Sterilization equipment;
–Technical building installations, in particular air conditioning, heating and ventilation
systems, building services and waste disposal systems;
– cooling equipment;
– cooking equipment
Safety Lighting
In the event of mains power failure, the necessary minimum illuminance shall be provided from
the safety services source for the following locations.
a) The changeover period to the safety source shall not exceed 15 s:
– escape routes;
– Lighting of exit signs;
– Locations for switchgear and control gear for emergency generation sets and form a in
distribution boards of the normal power supply and for power supply for safety services;
– Rooms in which essential services are intended. In each room at least one luminary shall
be supplied from the power source for safety services;
– Rooms of group 1 medical locations. In each room at least one luminary shall be
supplied from the power supply source for safety services;
– Rooms of group 2 medical locations. A minimum of 50 percent of the lighting shall be
supplied from the power source for safety services.
b) Services other than lighting which require a safety service supply with a changeover period
not exceeding 15 s may include, for example, the following:
– selected lifts for firemen;
– ventilating systems for smoke extraction;
– paging systems;
– Medical electrical equipment used in group 2 medical locations which serves for
surgical or other measures of vital importance. Such equipment will be defined
by responsible staff authorized by the management;
– Electrical equipment of medical gas supply including compressed air, vacuum
supply and narcosis (anesthetics) exhaustion as well as their monitoring
devices;– Fire detection, fire alarms and fire extinguishing systems.
16 VERIFICATION
The dates and results of each verification shall be recorded.
Initial Verification
The tests specified below under items a) to e) in addition to the requirements of 6 of IS 732 shall
be carried out, both prior to commissioning and after alterations or repairs and before re-
commissioning.
42
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Periodic Verification
Periodic verification of items a) to e) of Initial verification shall be carried out in accordance with
local/national regulations. If no local/national regulations exist, the following intervals are
recommended:
43
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
theatres.
A dedicated adequately rated standby supply for thetres and ICUs are strongly recommended with
10. AMF panel. Supply source and AMF logic should be able to restore power supply in less than 15
seconds and enough fuel storage should be available for 24hours continuous operation.
11. Acceptable time delay in restoring power supply for various devices, areas of medical
establishment given in the standards should be followed strictly.
12. The limits of touch voltage in operation theatre and ICU are limited to 25 V ac rms.
13. Only TN –S & IT system power supplies are allowed in theatres/ ICUs.
14. Screening/shielding should be completed for CAT/MRI if required /recommended by manufacturer.
44
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Table 23
Cables for X Rays
Cable size Earth
Capacity of X Ray Current rating Backup Fuse
AYFY Conductor
mA kVA Phase A A mm2 mm
30 (Portable) 5 1 22 32 2x6 3.251
50 (Portable) 7.5 3 10.8 32 3x6 3.251
50 7.5 3 10.8 32 3x6 3.251
100 10 3 16 32 3x6 3.251
300 30 3 45 50 3x16 4.064
500 65 3 98 100 3x35 4.064
Note : For equipments such as X Ray, Neon Sign, Lift, Escalator and CT scanner, the fee
specified in the Govt. order will be inclusive of the associated switch boards, earth electrodes
etc...
45
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
46
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
ground. In such place, ‘Ground wire return system’ of earthing shall be preferable.
For Electric security fences used for security purpose shall comprise an electric fence and a
22. physical barrier not less than 1.5 meter in height intended to prevent inadvertent contact with the
pulsed conductors of the Electric fence.
23. Electric fence installation should conform to IS 302-2-76/1999 and IEC 60335-2-76/2002.
Inspection fee of Rs 2500/- (Rupees Two Thousand and Five Hundred Only) per circuit of
24.
energizer shall be remitted by the applicant under the head of account 0043-102.
11kV distribution transformer body, capacitor, switchgear body etc, Expansion loops shall be
provided at supports to prevent unrestrained movement of RF cables.
The connectors used shall be weather proof, and made of material with lowest co-efficient of
11. expansion to avoid loose contacts. Connectors at the customer premises shall be fully insulated
and shock proof.
Low voltage double wound isolation transformer shall power the booster amplifier used in the
Network. The operating voltage of the amplifier shall not exceed 110 Volts. The primary supply to
12.
the transformers shall be 240V single phase, controlled by an MCB and 30 m A rated ELCB. The
power cubicle shall be effectively earthed using standard earth electrodes.
Customer drop cables shall be taken only through standard tap-off box installed at the support
poles, and the drop cable shall be supported on separate bare wire tied to the pole. The bare wire
carrying the drop cable shall be strung to a suitable non-metallic point, using tension insulator, at
13.
the consumer’s premises. The bare wire carrying the drop cable shall be connected to the main
bare wire using Britannia joint. Under no circumstances shall the drop cable taken along the
trunk/sub distribution RF, cable and teed.
Power block shall be provided to the drop cable brought to the customer’s premises. The
14. capacitors used for AC blocking shall be 2kV rated and the capacitance value shall be 220pf to
470pf.
Copy of the agreement with the KSEBL/Licensee and sanction received if any shall be forwarded
15. immediately. The updated list of eligible applicants will be furnished to the District Offices from
time to time.
Erection of cables and subsequent maintenance of the Network shall be carried out under the
16.
supervision of the authorized person of the utility adopting all safety precautions.
When crossing of Public/Private property, necessary sanction from appropriate agency shall be
17.
obtained.
The owner of the network shall submit the application for renewal of Safety Certificate at least one
18. month before the expiry of validity along with the fee for such inspection prescribed by the Chief
Electrical Inspector
Statement giving details of number of customers, length of cable Network, number of power
19. connections availed for amplifiers, area of jurisdiction of the supplier (Electrical Section) shall be
furnished to the Chief Electrical Inspector at the end of every financial year ending 31st March.
Details of the customers, including name, address etc. shall be maintained at the administrative
20.
office and made available when called for.
Safety provisions under the Indian Electricity Act, 1910 Indian Electricity Rules, 1956, Electricity
21.
(Supply) Act, 1948 shall be strictly adhered to.`
The fee for Cable TV Network inspections will be Rs. 10/- per pole per year for both initial and
22. periodical inspections. The fee is debatable under the head "0043 - 102". The fee is tentatively
fixed and it is subjected to revision as per Government decision.
The applicant will have to submit a formal application to the Electrical Inspector. The application
should contain the area map and other details such as number of KSEBL poles utilized, cable
23.
route, copy of sanction order issued by the KSEB and necessary technical particulars of the cable
TV network.
20. For availing separate LT supply for mobile / wireless phone services
at HT / High rise Building premises.
The KSEBL/ Licensee LT supply availed for such mobile/ wireless phone services shall not be
1. 2.
extended to any electrical installation / premises inside the HT / High rise Building premises or
1.
outside.
2. The supply from the independent generator of the Mobile / Wireless phone service shall not be
48
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
9. If it is grid tied, it shall be ensured that Bi-directional meter (Net meter) is provided at the
interconnection point to record the import and export of energy.
Battery and inverter shall be segregated properly with fire proof partition or minimum 75 cm
10. clearance shall be ensured between them. Easy and safe accessibility to panel for cleaning
shall be provided.
If the proposed installation is having a DG set and intended to work in synchronization with
11. Solar system, reverse power relay shall be provided to avoid back feeding to DG set. In the
case of back feeding, reverse power relay shall trip Solar inverter.
A lockable isoIator should also be Installed at the point of inter connection with the grid
12. connected SPV system which should be accessible to the utility staff to isolate the system at
the time of maintenance of the distribution system.
PV module frames, array structures, equipment and enclosures, AC conductors and lightning
13. conductors shall be earthed as per IS 3043/2018 and section 7.4.2 of IEC 62458/2016. AC and
DC side earthing shall be interconnected
Frames of all PV modules shall be connected to one continuous earthing conductor. The
14. earthing conductor shall be rated for 1.56 times the maximum short circuit current of the PV
array.
49
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
The minimum size of earthig conductor for PV equipment shall be 6 mm2 if copper, 10 mm' if,
aluminium or 70 mm2 if hot-dipped galvanized iron. Resistance between any point of the PV
15.
system and earth should not be greater than 5Ω. All the earthing should be provided with two
parallel paths with separate earth electrodes.
Each string should be provided with two fuses, one connected to the positive and the other to
16.
the negative terminal of the string.
PV string connected in parallel shall have matched open circuit voltage within 5% per string to
17.
avoid circulating current. (Refer section 5.1.6 of IEC 62548/2016).
Cable size for PV string cable, PV sub-array cable and PV array main cable shall be selected
18.
as per section 7.3.7 of IEC 62548/2016
DC surge arresters shall be Provided at DC side and it shall be of Type 2 (as per IEC 61643-1
IEC 62548/2016) rated at a continuous operating voltage of at least 125 percent of the open-
circuit voltage of the PV string, and a flash current of more than 5 A. As the string inverters used
for roof top PV systems do not allow more than 800 VDC, surge arrestors rated for 1,000 VDC
19. are commonly used. The surge arrestors should be connected to both positive and negative
outgoing terminal of the string junction box. If the inverter is provided with in-build SPD this may
not be insisted. AC side of inverter shall also be provided with a SPD of adequate rating. SPDs
shall be selected based on the voltage impulse withstanding capacity of the equipment to be
protected.
For large PV systems a dedicated lightning protection system shall be provided as per IEC
20. 62305 and section 7.4.2 of IEC 62548/2016. Existing lightning protection of a building may be
considered sufficient for this purpose, provided it adequately protects the installation area.
All PV equipment installed outdoors should have an increase protection rating of at least IP 65.
21. All the inverters installed outdoors shall be recommended to provide an additional shading
arrangement to avoid direct sunlight.
All The PV Equipment shall be labeled as per IEC 62446-2009-05.
• All circuits, protective devices, switches and terminals shall be suitably labeled.
• All DC junction boxes shall be labelled for indicating active parts inside the boxes fed from
a PV array.
22.
• Main AC isolating switch shall be clearly labelled with dual supply warning and a single
line wiring diagram shall be displayed.
• Inverter protection settings, installer details and emergency shutdown procedures shall be
displayed on site
23. PV system shall not inject DC current greater than 1 percent of the inverter rated output current
into the grid.
24. Solar inverters shall be rated for THD(I) of less than 3 percent of power injected into the grid.
25. Galvanized iron (GI) or aluminium shall be used for module mounting structures.
The installation shall conform to the following Act, Rules, Regulations & Standards .
• Central Electricity Authority( installation and operation of meters) Regulation 2010 as
amended from time to time.
• The relevant provision of the Central Electricity Authority (Measures Relating to Safety
and Electric Supply) Regulations, 2010 and The Electricity Act, 2003.
• The Relevant provision of CEA regulation as notified by CEA (Standard fot Connectivity of
Distributed Generation Resources), Regulations, 2013.
• CEA (Technical Standard for connectivity of the Grid) Regulation 2007 as amended from
the time to time.
• Kerala State Electricity Regulatory Commission (Renewable Energy and Net metering)
50
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
Regulations 2020
• National Solar Mission-Best Practice Guide published by MNRE, Govt of India 2016 shall
be referred for general guidelines.
• Various orders/circulars/Technical specifications related to solar plants published by the
State Government & Kerala State Electricity Regulatory Commission
b) General
Solar Installation capacity <10kW Scheme Approval and sanction for energisation are not
required from the department of Electrical Inspectorate.
10kW≥Solar Installation capacity Scheme Approval not required from the department of
≤30kW Electrical Inspectorate. Completion report and single line
diagram shall be submitted by the consumer through a
competent eIectrical contractor and sanction for
1.
energisation shall be obtained from the district office
concerned.
Solar Installation capacity >30kW Scheme Approval and sanction for energisation shall be
obtained from the office concerned.
Note:- If the said installation is an addition to the existing HT installation, then the as-fitted
drawings for such changes shall get approved from the district office.
For the installation above 30kW and below 500kW, prior scheme approval and sanction for
2.
energisation orders shall be obtained from the district office concerned.
For the installations including 500kW and above, prior scheme approval and sanction for
3.
energisation orders shall be obtained from the office of the Chief Electrical Inspector.
4. for the scrutiny and inspection, the check list given in the annexure shall be followed.
The following tests shall be conducted at the time of inspection:
a. PV Module: Irradiance measurement, angle of inclination, temperature of the PV module
5. and V-I characteristics using PV Array Tester.
b. Solar Inverter: Efficiency, input voltage, output voltage, power, THD, DG injection flicker
etc. and anti-islanding protection.
While issuing sanction for energisation for Solar Energy System, following conditions to be
6. included in addition to normal conditions:
a. Consent from the licensee shall be obtained (In case of grid tied system).
c) scrutiny / inspection of Solar Energy System
1. Up to 5kW solar plants, two numbers of earth electrodes are sufficient and LA shall be provided in
lightning prone area.
2. Above 5kW and up to 100kW solar plants, three numbers of earth electrodes are sufficient and
LA shall be provided.
3. These earth electrodes shall be interconnected to existing earth electrodes and total earth
resistance shall be less than 5 Ω.
4. Equipotential bonding shall be done as per IEC TR 63227:2020.
5. Lockable CB/SFU shall be installed at the point of interconnection with the grid connected SPV
system which should be accessible to the utility staff to isolate the system at the time of
maintenance of distribution system.
51
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
22. Communication /Optical Fibre Cable on Distribution Network Power Line Supports.
A minimum ground clearance of 4000mm shall be maintained for Optical Fibre cables taken along
1.
the street.
When cables are drawn across the road, a minimum ground clearance of 5800mm shall be
2.
maintained
A minimum vertical clearance of 1200mm shall be maintained for Optical Fibre cables from lowest
3.
power conductor when run under LT lines and 2440mm from 11kV lines.
All Dielectric Self Supporting (ADSS) cable shall possess good performance characteristics such
4. as anti-impact, anti-vibration, anti-bending, prevention of thermal aging, flame retardant and UV
protected.
ADSS cable specification shall conform to the latest editions of the relevant International Electro
5.
Technical Commission (IEC), IEEE and BIS.
Elements consisting of ADSS cable shall be non-metallic, shall possess anti-electromagnetic,
strong endurance of electrical effect and in worst case scenario no electricity should be conducted
6.
from the surface of the ADSS cable, when charged electrical conductor touches the surface of
ADSS cable.
In work sites, all metallic equipment including hardware anchors and structures shall be common
bonded together and then grounded to ensure safety. ADSS cable shall be grounded between the
7. work area and the spans when splicing ADSS cable during wet or rainy conditions near active high
voltage phase conductors for preventing dangerous leakage currents and transients from flowing
through personnel.
Pole Attachment Hardware / Brackets and supporting assembly for Fiber Optic Cable in electric
8.
poles shall be earthed.
9. Optical Fiber Cables Should not pass through/connected to Transformer Structures
10. Maximum of two cables of all service providers put together per pole may be allowed due to
technical constraints and electrical safety concern.
11. Erection of cables and subsequent maintenance of the network shall be carried out under the
supervision of the authorized person of the Utility adopting all safety precautions. No such works
shall be carried out on the electric poles from 6PM to 8 AM except on emergency situations.
12. Copy of the agreement with the KSEB Ltd/Licensee and sanction received, if any shall be
forwarded while applying for Safety Certificate.
13. Optical Fibre Cables should not be run above the power lines. It should always be below power
lines.
14. Pole Attachment Hardware / Brackets and supporting assembly for Optical Fibre Cable shall be
fixed to the utility pole, such that, a minimum horizontal clearance of 130mm is maintained
between the cable and the pole.
15. Power supply to the booster unit/Optical Amplifier unit/MUX, if required, should not be taken
directly from the power lines. The primary supply to the such units shall be controlled by an
MCB/MCCB and 30mA rated ELCB. The power cubicle shall be effectively earthed.
16. When crossing of Public/Private Property, necessary consent from appropriate agency shall be
obtained
17. The network shall be subjected to periodical inspection by the Electrical Inspector and fee for such
inspection prescribed by the Government shall be paid on demand.
18. Statement giving details of number of customers, length of cable network, route map shown,
number of poles, number of power connections availed for amplifiers/node, area of jurisdiction of
the supplier (Electrical Section) shall be furnished to the Deputy Chief Electrical Inspector/
Electrical Inspector at the end of every financial year ending on 31st March.
19. Details of the customers, including name, address etc shall be maintained at the administrative
office and made available when called for.
20. The relevant provisions of Regulation 68 & 69 of Central Electricity Authority (Measures relating to
52
Draft- Technical guidelines (Dept. of Electrical Inspectorate, Kerala)
(Sd/-)
Chief Electrical Inspector
53