Cost Management Exam Summary
Cost Management Exam Summary
02 of 1
5102 ملخص االمتحانات لمادة إدارة التكاليف
Indirect Costs: Overhead items incurred for the benefit of more than 1 project.
Examples include Taxes, cleaning, lighting and so on.
Q5) What are the Input ,tools & Techniques and output of:
1. Estimate Costs
2. Determine Budget
3. Control Costs
3) If earned value (EV) =350, actual cost (AC) =400, planned value (PV) =325, what is cost variance (CV)?
A. 350
B. -75
C. 400
D. -50
02 of 0
5102 ملخص االمتحانات لمادة إدارة التكاليف
4) The customer responsible for overseeing your project asks you to provide a written cost estimate that is 30
percent higher than your estimate of the project's cost. He explains that the budgeting process requires managers
to estimate pessimistically to ensure enough money is allocated for projects. What is the best way to handle
this?
A. Add the 30 percent as a lump sum contingency fund to handle project risks.
B. Add the 30 percent to your cost estimate by spreading it evenly across all project
activities.
C. Create one cost baseline for budget allocation and a second one for the actual
project management plan.
D. Ask for information on risks that would cause your estimate to be too low.
5) Analogous estimating:
A. Uses bottom-up estimating techniques.
B. Is used most frequently during the executing processes of the project.
C. Uses top-down estimating techniques.
D. Uses actual detailed historical costs.
6) All of the following are outputs of the Estimate Costs process EXCEPT:
A. An understanding of the cost risk in the work that has been estimated.
B. The prevention of inappropriate changes from being included in the cost baseline.
C. An indication of the range of possible costs for the project.
D. Documentation of any assumptions made during the Estimate Costs process.
11) Which of the following is not needed in order to come up with a project estimate?
A. A WBS
B. A network diagram
C. Risks
D. A change control system
02 of 3
5102 ملخص االمتحانات لمادة إدارة التكاليف
12) Which of the following is an example of a parametric estimate?
13) A rough order of magnitude estimate is made during which project management process group?
A. Planning
B. Closing
C. Executing
D. Initiating
15) During which project management process group are budget forecasts created?
A. Direct
B. NPV
C. Indirect
D. Fixed
A. Variable costs.
B. Fixed costs.
C. Overhead costs.
D. Opportunity costs.
19) Who has the cost risk in a fixed price (FP) contract?
A. The team
B. The buyer
C. The seller
D. Management
02 of 4
5102 ملخص االمتحانات لمادة إدارة التكاليف
20) Which of the following represents the estimated value of the work actually accomplished?
21) Which of the following are ALL items included in the cost management plan?
A. The level of accuracy needed for estimates, rules for measuring cost
performance, specifications for how duration estimates should be stated.
B. Specifications for how estimates should be stated, rules for measuring cost
performance, the level of accuracy needed for estimates.
C. Rules for measuring team performance, the level of accuracy needed for
estimates, specifications for how estimates should be stated.
D. Specifications for how estimates should be stated, the level of risk needed for
estimates, rules for measuring cost performance.
22) Your project has a medium amount of risk and is not very well defined. The sponsor hands you a project charter
and asks you to confirm that the project can be completed within the project cost budget. What is the best method
to handle this?
24) The seller tells you that your activities have resulted in an increase in their costs. You should:
25) Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following
should you do?
26) A new store development project requires the purchase of various equipment, machinery, and furniture. the
department responsible for the development recently centralized its external purchasing process and
standardized its new order system. In which document can these new procedures be found?
02 of 5
5102 ملخص االمتحانات لمادة إدارة التكاليف
27) Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques
should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would
be best to:
28) You have just completed the initiating processes of a small project and are moving into the planning processes
when a project stakeholder asks you for the project's budget and cost baseline. What should you tell her?
A. The project budget can be found in the project's charter, which has just been
completed.
B. The project budget and baseline will not be finalized and accepted until the
planning processes are completed.
C. The project management plan will not contain the project's budget and
baseline; this is a small project.
D. It is impossible to complete an estimate before the project management plan is
created.
29) The project manager is allocating overall cost estimates to individual activities to establish a baseline for
measuring project performance. What process is this?
A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs
30) Monitoring cost expended to date in order to detect variances from the plan occurs during:
32) A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of
0.91. Generally, what is the BEST explanation for why this occurred?
33) Although the stakeholders thought, there was enough money in the budget, halfway through the project the cost
performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover
the project cost budget was estimated analogously. Although the activity estimates add up to the project
estimate, the stakeholders think something was missing in how the estimate was completed. Which of the
following describes what was missing?
02 of 6
5102 ملخص االمتحانات لمادة إدارة التكاليف
A. Estimated costs should be used to measure CPI.
B. SPI should be used, not CPI.
C. Bottom-up estimating should have been used.
D. Past history was not taken into account.
A. Performance reporting.
B. Planning control.
C. Ishikawa diagrams.
D. Integrating the project components into a whole.
35) You are about to take over a project from another project manager and find out the following information about
the project. Activity Z has an early start (ES) of day 15 and a late start (LS) of day 20. Activity Z is a difficult
activity. The cost performance index (CPI) is 1.1. The schedule performance index (SPI) is 0.8. There are 11
stakeholders on the project. Based on this information, which of the following would you be the MOST
concerned about?
A. Schedule.
B. Float.
C. Cost.
D. The number of available resources.
36) The difference between the cost baseline and the cost budget can be best described as:
37) You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate,
because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should
you do?
39) A project manager needs to analyze the project costs to find ways to decrease costs. It would be best if the
project manager looks at:
02 of 7
5102 ملخص االمتحانات لمادة إدارة التكاليف
41) To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______ level of the WBS
A. Highest
B. Lowest
C. Major work effort
D. Third
A. CV = BCWP - BCWS
B. CV = BCWP - ACWP
C. CV = SV / BCWS
D. A and c
A. The process of developing the future trends along with the assessment of
probabilities, uncertainties, and inflation that could occur during the project
B. The process of assembling and predicting costs of a project over its life cycle
C. The process of establishing budgets, standards, and a monitoring system by
which the investment cost of the project can be measured and managed
D. The process of gathering, accumulating, analyzing, reporting, and managing
the costs on an on-going basis
A. The process of developing the future trends along with the assessment of
probabilities, uncertainties, and inflation that could occur during the project
B. The process of assembling and predicting costs of a project over its life cycle
C. The process of assembling and predicting costs of a project under its life cycle
D. The process of gathering, accumulating, analyzing, reporting, and managing
the costs on an on-going basis.
46) The BCWS = $250, the ACWP = $350, and the BCWP = $200. Calculate the Cost Variance.
A. -$150
B. $150
C. -$50
D. $50
02 of 8
5102 ملخص االمتحانات لمادة إدارة التكاليف
47) Life Cycle Costing is a term that is:
48) The project manager is making sure that the product of the project has been completed according to
the project management plan. What part of the project management process is he in?
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing
49) A project manager is employed by a construction company and is responsible for the furnishing of
the completed building. One of the first things that the project manager for this project should do is
to write a:
A. At this time, we expect the total project to cost 89 percent more than planned.
B. When the project is completed, we will have spent 89 percent more than
planned.
C. The project is only progressing at 89 percent of that planned.
D. the project is only getting 89 cents out of every dollar invested.
51) In which project management process group is the detailed project budget created?
A. Initiating
B. Before the project management process
C. Planning
D. Executing
53) You have two possible projects to manage, but you can only choose one. Project MKTG is worth
$23,000, while Project SALESPTR is worth $25,000. Management elects to choose Project SALESPTR.
Which one of the following is the opportunity cost of this choice?
A. $23,000
B. $27,000
C. $50,000
D. $4000
02 of 9
5102 ملخص االمتحانات لمادة إدارة التكاليف
54) You are a project manager of a project. Till today you have actually completed $34,000 of work, but based on
the cost plan it should be $50,000. What is percentage Schedule Variance (SV) in this case?
A. -32%
B. -16%
C. 32%
D. None of the above
55) Your project has a budget of $10,000 and is expect to last for 1 year, with the work and budget spread evenly
across all months. Right now CPI is 0.8. What is Variance at Completion in this case?
A. -$2,500
B. $10,000
C. $12,500
D. $12,000
56) Your project has a budget of $12,000 and is expect to last for 1 year, with the work and budget spread evenly
across all months. The project is now in the fourth month, but till now total spending for this project is $5,000.
What is Variance at Completion in this case?
A. -$3,000
B. -$5,000
C. $12,000
D. $13,000
A. Resource leveling
B. Resource planning
C. Cost estimating
D. Cost budgeting
E. Cost control
58) Which of the following choices indicates that a project has a Cost Performance Index of 1.2?
59) The Input to Cost Budgeting includes all of the following except:
A. Cost estimates
B. Cost baseline
C. WBS
D. Project schedule
60) During the six month update on a 1 year, $50,000 project, the analysis shows that the BCWS is $25,000; the
BCWP is $20,000 and the ACWP is $15,000. What can be determined from these figures?
02 of 12
5102 ملخص االمتحانات لمادة إدارة التكاليف
61) Earned value is:
62) Which of the following Cost Management processes are concerned with cost baseline?
A. Cost estimating
B. Cost budgeting
C. Cost control
D. B and C
E. A and B
A. The cost and accuracy of bottom-up estimating is driven by the size of the
individual work items.
B. Smaller work items increase both cost and accuracy.
C. Larger work items increase both cost and accuracy.
D. A and C
E. A and B
A. ACWP / BAC
B. BCWP - ACWP
C. BCWP / BAC
D. EAC / BAC
A. ETC + ACWP
B. BAC - ETC
C. BAC / CPI
D. A and C
E. A and B
A. Resource planning
B. Estimating
C. Budgeting
D. Control
E. Closeout
73) BCWS is the sum of the approved cost estimate for activities scheduled to be performed during a given period
A. True
B. False
74) The relationship between the budgeted actual cost, actual work completed, and work planned will determine
the:
02 of 10
5102 ملخص االمتحانات لمادة إدارة التكاليف
75) All work packages are complete:
A. at EAC time
B. when BAC is equal to EAC
C. when BCWP intersects BCWS
D. when schedule variance is zero
E. C and D
77) Richard was so concerned about his project that he woke up dreaming about it. He thought to himself, "Well,
our BCWP is 2, our ACWP is 4, and our BCWS is 6, so that means
78) The measurement which best shows the difference between actual work and actual costs is
A. Cost variance
B. Percent Over or under
C. Schedule variance
D. CPI
A. +75, -25
B. +25, -10
C. 85
D. 10 to 15
E. 25 to 50
80) If the ACWP exceeds the BCWP, the cost estimate at completion will
A. Increase
B. Decrease
C. Depend on the BCWS
D. Exceed the schedule estimate at completion
E. A and D
81) If the BCWS = $1,000,000, the BAC = $2,000,000, the ACWP = $1,500,00 the BCWP = $500,000 and you
are halfway through the project after two years, what is the cost estimate at completion?
A. $2,000,000
B. $4,000,000
C. $6,000,000
D. $8,000,000
02 of 13
5102 ملخص االمتحانات لمادة إدارة التكاليف
82) The cost estimate that has a range for error of minus 10 percent to plus 25 percent is the _________ estimate.
A. Budget
B. Definitive
C. Parametric
D. Analogy
E. Contingency
83) In the earned values system, the focus is on "cost of work," which is divided into "scheduled" and "performed"
work. This is further defined as "budgeted" and "actual" work. The formula "BCWP - BCWS" provides the
__________.
A. cost difference
B. schedule variance
C. overrun conditions
D. schedule difference
E. cost variance
84) Indices can provide an indication of the status of a project. In the earned values system, there are two indices:
Cost Performance Index (CPI) and Schedule Performance Index (SPI). The formula for CPI is _________.
A. ACWP / BCWS
B. ACWP / BCWP
C. BCWP / ACWP
D. BCWS / ACWP
E. BCWS / BCWS
85) Suppose that in the earned value system, the status of the project is reported as BCWS = 100, ACWP = 110,
BCWP = 95. The project is now __________.
86) Projects have direct and indirect costs that the project manager must track to ensure the budget is not exceeded.
The project manager has the most control over direct costs such as __________.
87) Suppose the corporate CEO has decided to delay the start of a major project by one year and you have been
asked to compute the difference in cost to complete the three-year project. The only major increase will be in
the labor and material costs. Assume the labor is level for the entire three years and the material will be
purchased at the midpoint (i.e. 18 months after project start). The project was to start immediately with a cost
for labor at $12,000,000 per year, and total material cost is:
A. $1,250,000
B. $770,000
C. $1,289,168
D. $5,191,682
02 of 14
5102 ملخص االمتحانات لمادة إدارة التكاليف
88) The most accurate estimates (and the most expensive to produce) are __________.
A. analogous estimates
B. parametric estimates
C. top-down estimates
D. bottom-up estimates
E. function point estimates
89) The __________ identifies the project elements that cost will be allocated to.
90) The EAC is a forecasting technique based on past project performance. It can be calculated using the formula
__________.
93) Which of the following is used to determine how efficient the project team must be to complete the remaining
work within the remaining money?
A. Generally Accurate
B. Generally less accurate
C. Uses statistical relationship between historical data and other variables
D. Bottom-up estimating
96) You are creating your Cost Performance Baseline. What process are you in?
A. Determine Budget
B. Control Costs
C. Estimate Costs
D. Cost Base lining
97) If AC (ACWP) is greater than your EV (BCWP), what does this mean?
98) A junior project manager is studying for her PMP exam, and asks you for advice. She’s learning about Earned
Value Management, and wants to know which of the variables represents the difference between what you
expect to spend on the project and what you’ve actually spent so far. What should you tell her?
99) Project A has a NPV of $75,000, with an internal rate of return of 1.5% and an initial investment of $15,000.
Project B has a NPV of $60,000 with a BCR of 2:1. Project C has a NPV of $80,000, which includes an
opportunity cost of $35,000. Based on these projects, which is the BEST one to select:
A. Project A
B. Project B
C. Project C
D. There is not enough information to select a project
100) You are managing a project for a defense contractor. You know that you’re over budget, and you need to tell
your project sponsor how much more money it’s going to cost. You’ve already given him a forecast that
represents your estimate of total cost at the end of the project, so you need to take that into account. You now
need to figure out what your CPI needs to be for the rest of the project. Which of the following BEST meets
your needs?
A. BAC
B. ETC
C. TCPI (BAC calculation)
D. TCPI (EAC calculation)
02 of 16
5102 ملخص االمتحانات لمادة إدارة التكاليف
Q7) The following table for five tasks with values of BCWS, ACWP, BCWP:
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5
02 of 17
5102 ملخص االمتحانات لمادة إدارة التكاليف
Solution
02 of 18
5102 ملخص االمتحانات لمادة إدارة التكاليف
7. What is the Percent Complete?
EV/BAC $55/$137 = 40%
Solution
1)
PV (5) = $1000/ (1.12) **5 = $567.44
So, if $567.44 is invested at a rate of 12%/year for 5 years, we will have $1000 at the end of the fifth year.
2)
Yr 1/(1+.10)**t PV
1 .909 $1600*.909 = $1454.55
2 .826 $1600*.826 = $1322.31
3 .751 $1600*.751 = $1202.10
3)
4)
02 of 19
5102 ملخص االمتحانات لمادة إدارة التكاليف
Q11) Given the following problem:
A. Calculate the present value of both revenue and cost assuming a 10% interest rate.
B. Calculate the benefit-cost ratio.
C. Based on the BCR and profitability alone, would you do this project?
Solution
BCR = PV(r)/PV(c)
BCR = 148,672/117,833 = 1.26
C)
Depends on who you ask. Should be 1.3 x cost before considering.
_______________________________________________________________________________________
2015
02 of 02