Stage-wise Payment Schedule for Construction

This document outlines the proposed construction of a residence for Pushpendra Singh Ji in Udaipur with a total area of 5,300 square feet split between 3,300 square feet on the ground floor and 2,000 square feet on the first floor. It provides the payment schedule with percentages of the total construction cost of Rs. 18,60,300 to be paid at various stages of completion such as foundation, plastering, and masonry work. The full amount due is Rs. 18,60,300.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
41K views1 page

Stage-wise Payment Schedule for Construction

This document outlines the proposed construction of a residence for Pushpendra Singh Ji in Udaipur with a total area of 5,300 square feet split between 3,300 square feet on the ground floor and 2,000 square feet on the first floor. It provides the payment schedule with percentages of the total construction cost of Rs. 18,60,300 to be paid at various stages of completion such as foundation, plastering, and masonry work. The full amount due is Rs. 18,60,300.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROJECT : -PROPOSED RESIDENCE FOR PUSHRENDRA SINGH JI AT , UDAIPUR

AREA STATEMENT
GROUND FIRST %OF
SR. FLOOR (IN FLOOR (IN WORK AMOUNT OF
NO AREA LEGEND [Link]) [Link]) TOTAL (IN [Link]) DONE WORK DONE

1 RESIDENCE 3300 2000 5300

TOTAL AREA 5300

PERCENTAGE OF PAYMENT STAGE WISE


SR.
NO PARTICULARS 1ST LEVEL 2ND LEVEL REMARKS
RATE FOR CONSTRUCTION PER [Link] 351
ADVANCE BEFORE
10% 0% 186030
1 STARTING WORK 186030
AFTER FOUNDATION
15% 0% 279045
2 COMPLETION 279045
AFTER PLINT LEVEL
10% 0% 186030
3 COMPLETION 186030
AFTER SLAB HEIGHT
4 COMPLETION
a) GROUND FLOOR 15% 173745 173745

15% 105300
b) FIRST FLOOR 105300
AFTER SLAB CASTING
5 WORK
a) GROUND FLOOR 25% 289575 289575
b) FIRST FLOOR 25% 175500 175500
AFTER BRICK
6 MASONARY WORK
GROUND FLOOR 10% 115830 115830
FIRST FLOOR 10% 70200 70200
AFTER INTERNAL
7 PLASTER WORK
a) GROUND FLOOR 10% 115830 115830
b) FIRST FLOOR 10% 70200 70200
AFTER OUTER PLASTER
8 WORK
a) GROUND FLOOR 5% 57915 57915
b) FIRST FLOOR 5% 35100 35100

TOTAL CONSTRUCTION COST 1860300 1860300

TOTAL PROJECT CONSTRUCTION AMOUNT 1860300


TOTAL CONSTRUCTION AMOUNT STAGE WISE 1860300
AMOUNT RECEIVED TILL DATE IN RS
AMOUNT DUE TILL DATE IN RS 18,60,300.00